Skip to main content

Full text of "The Golden Gate Bridge; report of the Chief Engineer to the Board of Directors of the Golden Gate Bridge and Highway District, California, September, 1937"

See other formats


Th 

GOLDEN  GA 


I 


Digitized  by  the  Internet  Archive 
in  2014 


https://archive.org/details/goldengatebridge1970gold 


PUBLISHED  BY 

GOLDEN  GATE  BRIDGE 
AND  HIGHWAY  DISTRICT 

JANUARY  1938 


REPRODUCTION    OF    AN    ORIGINAL  PAINTING 

S.F.  PUBLIC  LIBRARY 


D  REF  624.5  G56 


Golden  Gate  Bridge  and 
Highway  District. 

The  Golden  Gate  bridge; 
report  of  the  chief 


7*  -  77 


S.F.  PUBLIC  LIBRARY 


1 


was  <a®!L®ssf  (aa^  smbsxss 

REPORT  OF  THE  CHIEF  ENGINEER 
TO  THE  BOARD  OF  DIRECTORS  OF 
THE  GOLDEN  GATE  BRIDGE  AND 
HIGHWAY  DISTRICT  •  CALIFORNIA 


SEPTEMBER 
19  3  7 


D 

G56 


S.F.  PUBLIC  LIBRARY 


COPYRIGHT   1938  BY 
GOLDEN  GATE  BRIDGE  AND 
HIGHWAY  DISTRICT 

Lithographed  in  the  United  States  of  America 
by  Schwabacher-Frey  Company 
San  Francisco,  California 


7SI-77 


JOSEPH  B  STRAUSS 
President 


RICHARD  K.STRAUSS 
Contracting  Engineer 


CLIFFORD  E.  PAINE 
Vice  President 


CABLE  ADDRESS    BASCULE,  CHICAGO 
A  B.  C  COOE.  FIFTH  EDITION 
BENTLEY'S  CODE 


BASCULE.  LIFT.  SWING  AND 
LONG  SPAN  BRIDGE  DESIGNS 


REPORTS 
ESTIMATES 
SUPERVISION 


VESTIGATIONS 


TELEPHONES 

EXbrook  one  -  0119- 0120 


lit    SUTTER  STREET 


OFFICE  OF  CHIEF  ENGINEER 
Golden  Gate  Bridge  and  Highway  District 


September  30,  1937 


To  the  Honorable  Board  of  Directors 
Golden  Gate  Bridge  and  Highway  District 


* 


Gentlemen: 

I  have  the  honor  to  transmit  herewith  the  final  report 
of  the  Chief  Engineer  on  the  building  of  the  Golden  Gate  Bridge, 
covering  the  history  of  the  project  from  its  inception  to  its 
completion  and  including  a  description  of  the  technical  and 
other  phases  of  the  work. 


Respectfully  submitted, 


jyf     Joseph  B.  Strauss 
"  CHIEF  ENGINEER 

GOLDEN  GATE  BRIDGE  AND  HIGHWAY  DISTRICT 


JBS-m 


GOLDEN  GATE  BRIDGE 
AND  HIGHWAY  DISTRICT 

OFFICERS 

William  P.  Filmer  President 

Robert  H.  Trumbull  Vice  President 

James  Reed  General  Manager 

Joseph  B.  Strauss  Chief  Engineer 

W.  W.  Felt,  Jr  Secretary 

Roy  S.  West  .  .  .'  Auditor 

George  H.  Harlan  Attorney 

DIRECTORS 

William  P.  Filmer   San  Francisco  County 

Hugo  D.  Newhouse  San  Francisco  County 

Richard  J.  Welch  San  Francisco  County 

Warren  Shannon  San  Francisco  County 

Arthur  M.  Brown,  Jr  San  Francisco  County 

John  P.  McLaughlin  San  Francisco  County 

William  D.  Hadeler  San  Francisco  County 

Robert  H.  Trumbull  Marin  County 

Harry  Lutgens  Marin  County 

Thomas  Maxwell   Napa  County 

Frank  P.  Doyle  Sonoma  County 

Joseph  A.  McMinn  Sonoma  County 

A.  R.  O'Brien  Mendocino  County 

Henry  Westbrook,  Jr  Del  Norte  County 


gs^asssisisiaasfl®  grips' 


Joseph  B.  Strauss   Chief  Engineer 

Clifford  E.  Paine  ,  .  .  .  Principal  Assistant  Engineer 

Russell  G.  Cone  Resident  Engineer 

Charles  H.  Clarahan,  Jr  Assistant  Engineer 

Dwight  N.  Wetherell  Assistant  Engineer 

Herbert  J.  Baker  Inspecting  Engineer 

CONSULTANTS 

O.  H.  Ammann  Consulting  Engineer 

Charles  Derleth,  Jr.  Consulting  Engineer 

Leon  S.  Moisseiff  Consulting  Engineer 

Sydney  W.  Taylor,  Jr.  .  .  Consulting  Traffic  Engineer 

Irving  F.  Morrow  Consulting  Architect 

Andrew  C.  Lawson  Consulting  Geologist 

Allan  E.  Sedgwick  Consulting  Geologist 


f 


BOOK  ONE  — GENERAL  HISTORY 

The  District  and  Its  Characteristics,  Page  16;  Early  History  of  the  Site,  Page  19;  Develop- 
ment of  Need  for  the  Bridge,  Page  21;  First  Study,  Reconnaissance  and  Estimate,  Page  25; 
Evolution  of  the  Golden  Gate  Bridge  and  Highway  District,  Page  27 ;  Organization  of  the 
District,  Page  33;  Chief  Engineer's  Report  of  193  0,  Page  37;  The  Bond  Election,  Page  40; 
Bidding  Plans  and  Bids,  Page  42;  Second  Stage  of  Litigation,  Page  45;  Award  of  Contracts, 
Page  47;  Building  the  Structure,  Page  48;  Construction  Cost,  Page  58;  The  Completed 
Structure,  Page  61;  Forecasts,  Trends  and  Influences,  Page  62;  General  Aspects,  Page  71; 
Principal  Dimensions  and  Quantities,  Page  73;  List  of  Contractors,  Page  74. 

BOOK  TWO  — PLANNING 

Basis  of  Design,  Page  80;  Main  Piers,  Page  85;  Anchorages,  Page  87 ;  Main  Towers,  Page  90; 
Cables,  Page  106;  The  Suspended  Structure,  Page  108;  Approaches,  Page  11);  Toll  Plaza, 
Page  1 14;  Power,  Lighting  and  Signal  Facilities,  Page  116. 

BOOK  THREE  — CONSTRUCTION 

Concrete  Materials  and  Handling,  Page  123;  Anchorage  Construction,  Page  127;  Marin 
Pier  Construction,  Page  132;  San  Francisco  Pier  Construction,  Page  134;  Tower  Erection, 
Page  146;  Cable  Construction,  Page  151;  Erection  of  Stiffening  Trusses  and  Floor, 
Page  173;  Roadway  Pavement  and  Sidewalks,  Page  178;  Construction  of  San  Francisco 
and  Marin  Approaches,  Page  181;  Construction  of  Presidio  Approach  Road,  Page  182. 

BOOK  FOUR  — MATERIALS 

Structural  Steel,  Page  189;  Heat-Treated  Eye-Bars,  Page  197;  Wires  and  Ropes,  Page  201 ; 
Cast  Steel,  Page  21 1 ;  Forged  Steel,  Page  216;  Other  Materials,  Page  227. 

BOOK  FIVE  — FABRICATION 

Tower  Legs,  Page  23  0;  Stiffening  Trusses,  Page  241;  Shop  Painting,  Page  244. 


GENERAL  HISTORY  AND  RUNNING 
STORY  OF  PLANNING.  DESIGNING, 
BUILDING  THE  WORLD'S  LARGEST 
BRIDGE  SPAN.  PRECONSTRUCTION 
DIFFICULTIES  AND  OBSTRUCTIONS 
ARE  SURMOUNTED  AND  NOVEL 
ENGINEERING  PROBLEMS  INCIDENT 
TO  THE  BRIDGING  OF  THE  GOLDEN 
GATE  ARE  SOLVED. 


THE      GOLDEN      GATE  BRIDGE 


tbout  seventy  years  ago,  William  H.  Seward,  Andrew  Johnson's  secretary  of  state 
/\  and  the  man  whose  vision  moved  the  United  States  to  purchase  Alaska,  uttered 
JL  3L  this  prophecy:  "The  Pacific  Ocean  with  its  shores — its  islands  and  the  vast  region 
beyond— will  become  the  chief  theater  of  events  of  the  world's  great  hereafter."  Seward's 
prophecy  is  in  course  of  fulfillment  today,  and,  as  the  drama  of  the  Pacific  unfolds,  the 
Great  West  Coast  Region  of  North  America  is  to  play  a  leading  part.  That  same  region, 
with  its  system  of  transcontinental  highways  leading  eastward,  is  in  a  larger  sense  the 
hinterland  of  the  Golden  Gate  Bridge;  and  San  Francisco  by  virtue  of  its  strategic 
location  is  the  natural  commercial  and  banking  center  of  that  hinterland. 

THE  DISTRICT  AND  ITS  CHARACTERISTICS 

The  Golden  Gate  Bridge  is  a  project  conceived  and  justified  as  a  toll  bridge.  And 
since  successful  toll  bridges  have  almost  invariably  been  sustained  by  local  patronage— 
for  the  local  patron  will  use  a  bridge  perhaps  a  dozen  times  each  year  while  the  itinerant 
tourist  may  cross  but  once— it  will  be  appropriate  first  to  examine  the  physiographic  and 
political  characteristics  of  the  region  more  immediately  contiguous  to  the  project's 
bridge  site.  The  remoter  areas  may  be  dismissed  with  the  brief  statement  that  the  Pacific 
Slope  is  a  region  of  high  relief  with  limited  coastal  plain  and  generally  north-south 
trending  mountain  ranges  and  valleys.  Long-distance  travel  for  pleasure  therefore  is 
confined  by  mountain  barriers  to  the  north-south  routes.  And  since  the  interior  valleys 
of  California  and  Oregon  are  oppressively  hot  in  summer,  and  the  passes  of  the 
Siskiyous— a  choppy  cross  range  of  indefinite  trend  at  the  California-Oregon  line— are 
snowbound  and  hazardous  in  winter,  such  travel  tends  to  seek  the  all-year-climate  routes 
of  the  narrow  coastal  strip  where  the  summers  are  cool,  the  winters  mild  and  snow  is 
virtually  unknown.  The  Golden  Gate  Bridge  links  the  north  and  south  sections  of  these 
all-year  coastal  routes  together. 

PHYSIOGRAPHY:  The  San  Francisco  Bay  Region  is  topographically  unique.  It 
consists  of  463  square  miles  of  saltwater-flooded  basin,  largest  land-locked  harbor  in 
the  world,  the  marginal  occupiable  lands  about  its  shores,  and  the  mountains  round 
about,  rising  at  some  places  to  the  maximum  elevation  of  3000  feet.  The  nine  counties 
tributary  to  the  bay,  with  their  combined  area  of  4,750,000  acres,  are  embraced  within 
the  compass  of  this  circumferential  rim  of  mountains,  and  the  present-day  population 
of  these  counties  is  nearly  2,000,000  persons,  owning  5  50,000  automobiles. 

The  rim  is  cleft  at  but  two  places:  on  the  west  where  the  gorge  of  the  Golden  Gate 
cuts  through  the  coastal  highlands  and  permits  access  to  the  tidal  waters  of  the  Pacific; 
on  the  east  where  chains  of  considerable  altitude,  which  shut  off  the  bay  region  from 


16 


GENERAL  HISTORY 


the  vast  reaches  of  California's  highly  developed  central  basin,  are  cut  by  Carquinez 
Strait.  The  strait  carries  the  discharge  of  California's  two  central  basin  rivers,  the 
Sacramento  and  the  San  Joaquin. 

Long  rugged  spurs  thrust  toward  the  bay  from  the  circumferential  mountains  and 
divide  the  alluvial  plain  into  extended  valleys  radiating  from  the  marginal  levels  of  the 
shore.  It  was  along  these  valleys  that  the  early  settlements  were  made.  Availability  of 
fresh  water,  accessibility  of  the  lands,  and,  generally,  the  possibility  of  water  transpor- 
tation to  San  Francisco  determined  their  locations.  The  older  towns  will  be  found  today 
on  navigable  water  where  they  still  serve  as  subports  for  the  produce  of  the  hinterland. 

The  entire  occupiable  area  within  the  bay  region,  including  plain  and  upland,  is 
nearly  9,000,000  acres,  or  an  area  easily  capable  of  supporting  a  future  population  of 
some  6,000,000  persons.  Omitting  lands  not  now  strictly  urban  or  suburban  in  character 
the  district  contracts  to  about  6,000,000  acres,  and  this  contracted  area  is  truly 
susceptible  of  development  as  San  Francisco's  tributary  metropolitan  district.  It 
includes  the  entire  city  and  county  of  San  Francisco;  the  flat  and  rolling  lands  on  the 
west  side  of  the  bay  where  the  settlement  now  is  almost  continuous  as  far  south  as  and 
including  San  Jose;  the  alluvial  plain  and  adjoining  uplands  along  the  east  side  of  the  bay 
with  its  2 5 -mile  fringe  of  compactly  continuous  East  Bay  cities;  the  terrain  along  the 
south  shoreline  of  Carquinez  Strait  and  Suisun  Bay  extending  eastward  to  Antioch;  the 
opposite  northbank  of  the  strait  from  Benicia  westward,  thence  northerly  to  Napa  and 
vicinity;  the  land  west  of  Petaluma  Creek  and  San  Pablo  Bay  extending  southward  to 
the  bridge  site;  and  the  towns  north  of  Petaluma  to  and  including  Santa  Rosa.  Excluding 
Santa  Rosa  and  its  environs,  this  area  is  circumjacent  to  the  tidal  and  navigable  waters 
of  San  Francisco  Bay  and  its  saltwater-flooded  extensions.  It  embraces  more  than  ninety 
per  cent  of  the  population  of  the  9  bay  counties,  and  it  may  be  depended  upon  to 
contribute  more  than  ninety  per  cent  of  the  traffic  over  the  Golden  Gate  Bridge  until 
such  time  as  the  State  of  California  will  have  built  a  proper  highway  link  between  the 
Sacramento  Valley  and  the  north  approach  of  the  bridge,  and  opened  up  the  Inland 
Empire  to  the  project. 

POLITICAL  CHARACTERISTICS:  It  is  natural  that  the  development  of  an  area 
such  as  we  have  described  should  exhibit  considerable  diffusion.  Metropolitan  growth 
elsewhere  in  the  country  has  usually  evolved  more  or  less  concentrically— as  topography 
permitted— about  the  early  settlement.  For  this  reason  metropolitan  areas  elsewhere  are 
generally  more  compact  and  uniform  in  structure.  Had  it  not  been  for  the  intervening 
bay  and  the  intrusion  of  radial  hilly  spurs,  both  of  which  have  acted  as  barriers  to 
contiguous  growth,  there  is  no  doubt  that  San  Francisco's  metropolitan  district  would 
have  developed  according  to  the  conventional  pattern.  But  although  the  individual 
settlements  which  constitute  the  bay  region  have  of  necessity  spread  out  from  the 
central  hub  more  or  less  like  the  spokes  of  a  wheel,  the  inhabitants  of  this  cluster  of  towns 
and  cities  are  as  closely  welded  together  by  commerce,  by  social  contacts  and  by  habit  of 

T7 


THE     GOLDEN     GATE  BRIDGE 


thought  as  are  the  inhabitants  of  districts  more  compactly  and  uniformly  developed; 
and  the  life  of  the  people  of  the  entire  area  is  industrially,  commercially  and  socio- 
logically homogeneous  to  an  exceptional  degree. 

GEOLOGY:  San  Francisco  Bay  was  once  a  wide  valley,  part  of  the  present-day 
system  comprising  the  valleys  of  Santa  Clara,  Sonoma  and  Napa.  The  Golden  Gate  was 
then  a  river  gorge  through  which  the  greater  part  of  the  drainage  of  California  flowed 
as  a  fresh  water  stream  to  the  ocean.  Gradual  subsidence,  as  it  deepened  the  gorge,  per- 
mitted the  waters  of  the  ocean  to  invade  the  valley  till  it  became  the  463  square-mile, 
saltwater-flooded  area  we  have  already  noted. 

The  rocks  traversed  by  the  Golden  Gate  belong  to  a  series  of  formations  known  to 
geologists  as  the  Franciscan  Series  and  comprise  many  different  kinds  of  rocks,  some 
sedimentary  and  some  of  igneous  origin.  These  formations  are  widespread  and  exten- 
sively exposed  throughout  the  coastal  ranges  of  California. 

After  the  Franciscan  Series  had  accumulated  to  a  thickness  of  a  mile  or  more 
throughout  a  basin  coextensive  with  the  coastal  ranges,  the  region  was  greatly  disturbed 


Geological  cross-section  of  the  Golden  Gate  on  bridge  alignment 


by  igneous  intrusions.  As  a  result,  two  general  types  of  igneous  rock  are  to  be  found  in 
many  localities.  One  of  these  is  peridotite,  now  generally  altered  to  serpentine,  and  the 
other,  basalt.  It  happens  that  the  south  pier  of  the  Golden  Gate  Bridge  is  founded  on 
serpentine  and  the  north  pier  on  basalt.  The  fact  that  the  narrowest  part  of  the  Golden 
Gate— which  is  the  location  selected  for  the  bridge— is  bounded  on  one  side  by  basalt  and 
on  the  other  by  serpentine,  exemplifies  the  relatively  great  resistance  of  these  rocks  to 
the  ordinary  agencies  of  erosion. 

Because  of  the  intense  internal  shearing  which  takes  place  during  its  alteration  by  the 
process  of  hydration  from  peridotite,  the  tensile  strength  of  serpentine  is  apt  to  be 
relatively  low.  But  it  is  entirely  adequate  when  confined— as  it  is.  The  load  stress  trans- 
mitted by  the  south  pier  to  the  foundation  rock  is  less  than  150  pounds  on  the  square 
inch,  and  this  is  relatively  a  small  load.  This  fact  was  practically  demonstrated  by  the 
writer  at  Fort  Point  on  a  representative  section  of  serpentine  at  sea  level  during  his 


18 


GENERAL  HISTORY 


preliminary  investigation.  The  test  section,  20  by  20  inches  in  area,  was  loaded  to  the 
extent  of  92  tons,  or  460  pounds  per  square  inch,  without  yielding.  Subsequent  pressure 
tests  were  conducted  in  the  inspection  wells,  which  were  built  into  the  pier  and  used  for 
access  to  the  rock  bottom  for  this  purpose  and  for  purposes  of  inspection.  These  tests, 
together  with  direct  examination,  fully  confirmed  the  adequacy  of  the  bedrock  for  the 
support  of  the  pier. 

It  is  reasonable  to  assume  that  once  or  twice  in  a  century  San  Francisco  will  be 
shaken  by  a  violent  earthquake.  The  trace  of  San  Andreas  fault,  upon  which  a  sudden 
slip  occurred  in  1906  with  disastrous  results  to  San  Francisco,  lies  six  miles  to  the  west 
of  the  bridge  site.  But  there  is  no  evidence  that  the  Golden  Gate  itself  is  in  danger  of  a 
dislocation  such  that  differential  movement  between  the  two  bridge-ends  might  be 
caused.  Even  when  we  contemplate  the  possible  destruction  of  the  Golden  Gate  Bridge 
by  an  earthquake  of  exceptional  violence,  it  should  be  borne  in  mind  that  any  earthquake 
so  violent  that  it  would  destroy  the  bridge  would  also  completely  destroy  San  Francisco. 
Despite  this,  the  city  still  continues  to  build  and  grow,  and  growth  necessarily  involves 
the  erection  of  large  and  expensive  structures. 

EARLY  HISTORY  OF  THE  SITE 

Historians  tell  us  that  the  early  navigators,  led  by  such  sixteenth  century  worthies 
as  Cabrillo  and  Drake,  had  sailed  past  the  Golden  Gate  for  200  years  without  suspecting 
the  existence  of  the  great  land-locked  harbor;  and  that  it  remained  for  a  party  traveling 
overland  to  make  the  discovery.  One  Caspar  de  Portola,  it  seems,  had  been  dispatched 
from  Mexico  to  civilize  the  Indians  and  establish  Spanish  authority  in  California.  He 
was  en  route  to  Monterey  Bay  to  found  a  Mission.  Missing  his  objective,  he  sent  his 
sergeant,  Ortega,  on  ahead  to  explore  the  coast,  and,  on  November  1,  1769,  Ortega 
unexpectedly  came  upon  the  entrance  of  the  bay  of  San  Francisco.  Six  years  later, 
Lieutenant  Ayala  sailed  his  good  ship  "San  Carlos"  through  the  "uncharted  narrows" 
and  opened  the  Golden  Gate  to  the  commerce  of  the  world.  Ayala's  was  the  first  ship  of 
record  to  anchor  in  the  harbor. 

Then  came  Captain  Juan  Bautista  Anza,  redoubtable  soldier  of  Old  Spain,  under 
orders  to  establish  a  permanent  settlement  on  the  bay.  He  sailed  through  the  Golden 
Gate  in  March,  1776,  and,  after  planting  a  cross  on  the  narrow  bench  where  Fort  Point 
now  stands,  selected  sites  for  the  Presidio  and  Mission  Dolores.  Padre  Fout,  Anza's 
secretary,  declared  the  harbor  to  be  a  marvel  of  nature,  "the  port  of  ports". 

But  the  establishment  of  great  cities  does  not  come  about  by  directed  processes,  but 
fortuitously  and  by  the  shaping  of  events.  It  happened  that  the  city  did  not  grow  up  at 
Anza's  Presidio,  as  he  had  hoped,  but  some  four  miles  eastward  at  Yerba  Buena  Cove 
under  the  lee  of  Telegraph  Hill,  where  the  waters  of  the  bay  came  up  to  what  is  now 
Montgomery  Street.  To  this  sheltered  cove,  boats  from  the  Missions  around  the  bay 
brought  hides,  tallow  and  produce  to  trade  with  the  sea-going  ships  that  found  safe 


19 


GENERAL  HISTORY 


anchorage  there;  for  the  opposite  mainland  shores  were  exposed  to  the  gales,  shoaled  and 
fringed  with  tide  flats. 

The  little  village  of  Yerba  Buena,  which  took  its  name  from  the  cove,  prospered 
exceedingly.  It  remained  Yerba  Buena  until  January  10,  1847,  when  "Washington 
Bartlet,  an  American  and  alcalde  at  that  time,  changed  its  name  by  executive  order  to 
San  Francisco.  Thus  the  great  city  of  the  bay  region,  its  site  having  been  decreed  by  the 
exigencies  of  commerce,  grew  up  at  the  tip  of  a  narrow  40-mile-long  peninsula,  invested 
on  three  sides  by  water  and  otherwise  cut  off  from  its  natural  mainland  trade  area  by 
mountain  barriers  on  the  south,  instead  of  on  the  opposite-lying  mainland  shores. 

Even  the  coming  of  the  first  transcontinental  railroad  in  1869,  with  its  terminus 
four  miles  east  across  the  bay  at  Oakland's  waterfront,  failed  to  shake  San  Francisco's 
preeminence.  Other  railroads  entered  the  Bay  Region.  Ferry  services  multiplied  with 
the  coming  of  the  railroads.  Commuting  by  rail  and  ferry  began  to  be  a  settled  habit  by 
1900;  but  the  automobile  was  still  many  years  away. 

Following  the  arrival  of  the  first  transcontinental  railroad,  some  began  to  dream 
about  bridging  the  main  bay  and  its  tributaries.  The  Southern  Pacific's  Dumbarton  rail 
crossing  over  the  narrows  of  the  lower  bay,  a  low-level,  single-track  structure,  was  built 
in  1910.  Freight  could  now  be  routed  to  San  Francisco  via  the  round-about  route  over 
Dumbarton  crossing.  Oakland,  however,  still  remained  the  terminus  for  mainline 
trains.  Other  proposals  followed,  many  of  them  impractical  and  all  of  them  relating  to 
the  bridging  of  the  main  bay,  Carquinez  Strait  or  the  lower  San  Joaquin.  But  no  definite 
plan  had  been  submitted  for  bridging  the  Golden  Gate  until  the  publication  of  this 
writer's  original  plan  of  1919.  This  plan  opened  the  door  and  out  of  it  grew  the  activities 
which  gradually  made  the  city  bridge-minded.  We  shall  have  occasion  to  describe  that 
plan  more  in  detail  later. 

The  rapid  industrial  growth  of  the  San  Francisco  Bay  Region  dates  from  the  opening 
of  the  Panama  Canal  in  1915.  The  Canal,  almost  overnight,  brought  about  profound 
readjustments  in  the  world's  trade  routes;  the  Pacific  Coast  and  the  Atlantic  Seaboard 
became  close  neighbors;  and  California,  once  the  most  distant  land  on  earth  from  the 
centers  of  white  civilization,  suddenly  found  itself  at  the  cross-roads  of  the  world's 
commerce.  About  five  years  later,  the  automobile  began  to  be  a  factor  to  be  reckoned 
with  as  a  means  of  transportation. 

DEVELOPMENT  OF  NEED  FOR  THE  BRIDGE 

San  Francisco  has  been  a  complacent  city,  "supreme,  indifferent  to  fate".  Its 
rolling  hills  and  intervening  valleys  have  fostered  a  certain  sectionalism  and  discouraged 
community  thinking.  We  have  seen  that  its  growth  and  importance  as  a  world  city 
have  come  about  through  the  operation  of  extraneous  forces,  and,  we  are  to  suppose, 
with  little  conscious  effort  on  the  part  of  the  inhabitants. 

Future  historians  will  record  that  this  self-sufficiency  was  rudely  shaken  by  the  rise 
of  the  automobile  with  its  insistent  demand  for  better  highways,  and  that  San  Francisco 


As  the  bridge  neared  com-  21 
pletion  the  work  of  the 
derricks  on  the  tower-tops 
was  brought  to  an  end  so 
they  could  be  dismantled 
and  removed 


THE     GOLDEN     GATE  BRIDGE 


did  not  begin  to  assume  its  proper  place  as  the  natural  center  of  the  great  Bay  Region 
Metropolitan  Area  until  archaic  ferry  services  had  given  place  to  modern  bridges.  It  will 
be  appropriate,  then,  to  trace  the  effect  of  the  rise  of  the  automobile  on  bay-crossing 
facilities. 

In  the  year  1919,  following  the  World  War  the  volume  of  automobile  travel 
across  San  Francisco  Bay  was  relatively  small  compared  with  the  tremendous  present-day 
movement.  The  two  ferry  lines  then  operating  out  of  San  Francisco — one  to  Sausalito 
in  Marin  County  across  the  Golden  Gate,  and  the  other  to  the  foot  of  Broadway, 
Oakland,  were  controlled  by  an  unprogressive  rail  monopoly.  The  service,  grudgingly 
vouchsafed  and  infrequent,  was  rendered  by  rebuilt  boats  of  ancient  vintage,  and  the 
tolls  charged  were  excessively  high.  A  growing  and  insistent  patronage  was  clamoring 
even  then  for  relief,  but  somnolent  operating  officials  gave  no  evidence  of  an  awareness 
that  real  service  was  needed  and  must  some  day,  somehow  be  provided. 

It  remained  for  enterprising  outsiders,  who  invaded  the  monopoly's  field  in  1921,  to 
perceive  the  need  and  prove  that  fast,efficientDiesel-powered  boats,  designed  exclusively 
for  the  transportation  of  automobiles,  were  demanded  by  the  mounting  traffic.  The 
invaders  promptly  reduced  tolls  and  the  new  lines  prospered  exceedingly.  Belatedly,  the 
monopoly,  having  acquired  one  of  the  competing  lines  by  purchase  meanwhile, 
improved  its  service,  reduced  tolls  and  recaptured  a  part  of  the  profitable  business.  By 
1929,  motor  vehicle  ferry  travel  to  and  from  San  Francisco  had  increased  more  than 
seven-fold,  and  in  May  of  that  year,  all  of  the  services  were  taken  over  by  interests 
associated  with  the  monopoly  and  merged.  The  toll  level,  however,  remained  unchanged, 
for  the  interests  in  control  were  opposed  to  concessions  as  well  as  to  progress.  We  shall 
have  occasion  later  to  mention  those  interests  again,  in  connection  with  obstructive 
litigation  and  activities  initiated  by  them  by  which  they  sought  to  delay  the  building  of 
the  Golden  Gate  Bridge. 

It  has  been  a  characteristic  of  the  San  Francisco  Bay  vehicular  travel  that  every 
expansion  of  ferry  service  in  the  past  has  been  met  at  once  by  increased  response  on  the 
part  of  the  motoring  public,  and  the  volume  of  traffic  induced  by  the  expanded  services 
has  soon  built  up  to  the  limit  of  the  capacity  of  the  new  equipment.  Service  naturally 
improved  somewhat  following  the  merger,  for  the  pooling  of  the  fleets  made  possible 
the  immediate  diversion  of  extra  boats  during  periods  of  peak  flow  to  points  where  traffic 
pressure  for  the  moment  was  greatest.  But  the  capacity  of  the  lines  taken  over  at  the 
time  of  the  merger  had  already  begun  to  be  overtaxed  long  prior  to  May,  1929.  Even 
the  pooled  fleets  were  wholly  inadequate  to  cope  with  the  normal  week-end  and 
holiday  rush. 

Travel  across  the  Golden  Gate  is  exceptionally  heavy  during  week-ends  and  holidays. 
Maximum  hourly  offerings  to  the  Marin  ferry  services  of  upwards  of  3000  vehicles 
during  unusually  heavy  holiday  peaks  had  already  been  observed  long  before  the  opening 
of  the  Golden  Gate  Bridge,  and  the  utmost  capacity  of  the  services,  even  under  stress  of 
dire  necessity  with  all  possible  spare  boats  diverted  thereto,  was  little  more  than  a 


22 


ENERAL  HISTORY 


Map  of  San  Francisco  Bay  region 
23 


THE      GOLDEN      GATE  BRIDG 


GENERAL  HISTORY 


thousand  cars  per  hour.  The  highways  leading  to  the  Sausalito  ferry  plaza,  therefore, 
were  often  jammed  for  miles  by  lines  of  irate  motorists  returning  of  a  Sunday  night 
from  an  outing  in  the  northern  counties. 

Now  the  utmost  capacity  of  San  Francisco's  combined  fleet  of  vehicular  ferries  is 
but  two  thousand  cars  per  hour,  one  way.  This  divides,  one  thousand  north  to  Marin; 
one  thousand  east  to  the  East  Bay  cities.  A  thousand  cars  per  hour  is  approximately  the 
capacity  of  an  old-time,  horse-and-buggy  road,  but  even  such  a  road  is  faster  than  the 
ferries  and  the  automobilist  using  it  would  not  have  to  wait  for  boats.  It  was  this  type  of 
traffic  facility  that  had  isolated  San  Francisco  as  respects  the  northern  peninsula  and 
eastern  mainland  and  that  San  Francisco  had  endured  long  after  high  speed  roads  and 
high-speed  traffic  facilities  had  become  general. 

FIRST  STUDY,  RECONNAISSANCE  AND  ESTIMATE 

For  some  time  the  possibility  of  a  bridge  across  the  Golden  Gate  had  been  considered. 
In  1918  a  resolution  was  introduced  by  the  then  Supervisor  Richard  J.  Welch,  now 
Congressman  and  a  Director  of  the  Bridge  District,  authorizing  and  directing  a  survey 
to  be  made  by  the  City  of  San  Francisco  in  order  to  determine  the  physical  conditions 
at  the  site.  During  the  same  year  the  matter  was  brought  to  the  attention  of  the  writer 
by  the  city  engineer,  M.  M.  O'Shaughnessy,  who  made  inquiry  as  to  whether  the  writer 
would  be  interested  in  the  solution  of  the  problem.  He  accompanied  this  inquiry  with 
the  statement  that  "Everybody  says  it  can't  be  done  and  that  it  would  cost  over 
$100,000,000  if  it  could  be  done". 

The  writer  thought  it  could  be  done  and  said  so,  and  thus  was  initiated  the  first  serious 
attempt  to  break  through  San  Francisco's  encircling  water  barriers.  At  that  time,  as  we 
have  noted,  except  for  the  Southern  Pacific's  single-track,  low  level  railroad  bridge 
across  the  Dumbarton  narrows,  neither  San  Francisco  Bay  nor  any  of  its  arms  had  been 
bridged,  and  all  bay  traffic  was  handled  by  a  private  monopoly  which  failed  to  meet  the 
rapidly  expanding  needs  of  the  community.  This  first  practical  proposal  to  bridge  the 
Golden  Gate  altered  all  this.  It  stimulated  local  bridge-mindedness  as  it  unfolded  and 
became  the  inspiration  for  all  subsequent  bridge-the-bay  projects. 

At  the  Golden  Gate  the  problems  presented  were  many  and  difficult.  Old  precedents 
would  have  to  be  set  aside,  new  ones  established.  We  have  seen  that  the  channel  is  more 
than  three  hundred  feet  deep,  and  5  3  57  feet  wide  at  its  narrowest  part,  where,  for 
cogent  physical  reasons  having  to  do  with  foundation  conditions  and  length  of  bridge, 
the  structure  would  have  to  be  located,  leaving  little  room  to  spare  for  adjustments  of 
alignment.  The  conditions  indicated  a  main  span  length  of  about  4000  feet,  and  at  that 
time  spans  of  such  great  length  had  not  been  contemplated.  In  addition,  the  locality  is 
subject  to  fog  and  high  prevailing  winds.  It  is  exposed  to  the  sweep  of  ocean  storms  and 
heavy  swells  from  the  Pacific,  and  the  tidal  current  reaches  the  velocity  of  seven  knots. 

The  site  lay  entirely  within  two  military  reservations— the  Presidio  on  the  south  and 


25 


THE     GOLDEN     GATE  BRIDGE 


GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  CALIF. 


Fort  Baker  in  Marin  County  on  the  north— so  that  the  bridge  approaches  would  interfere 
seriously  with  important  military  works,  buildings  and  roads.  The  entrance  to  a  great 
harbor  had  never  been  bridged,  and  there  was  a  deep-seated  objection  to  the  establish- 
ment of  such  a  precedent.  There  were  strong  military  and  naval  objections  on  the  ground 
that  an  enemy  might  by  bombing  the  structure  bottle  up  the  harbor.  The  minimum 
permissible  vertical  clearance  would  be  greater  than  that  of  any  other  bridge  over 
navigable  water.  These  considerations  and  the  unprecedented  size  of  the  various 
component  units  of  the  structure,  the  vast  quantities  of  materials  to  be  assembled  and 
routed  to  their  rather  inaccessible  place  of  use,  the  new  and  original  methods  of  con- 
struction to  be  devised  for  building  a  structure  of  such  great  magnitude  virtually  in  the 
open  sea,  and,  finally,  the  question  of  doing  all  this  within  practical  limits  of  cost— all 
made  the  challenge  to  the  engineer  a  formidable  one. 

Then,  too,  there  were  questions  by  no  means  less  difficult  of  solution  having  to  do 

with  the  financing  of  a  project  of  this 

mm  ?nnn  anon  wv>  finnn         7nnn«  A  ' 

nature,  and  the  legislative  steps  to  be 
taken  in  order  to  create  a  political 
entity  for  building  an  inter-county 
structure.  And  finally,  any  movement 
set  afoot  to  bridge  the  Golden  Gate 
would  without  doubt  be  violently  op- 
posed by  well -organized,  powerful 
vested  interests  who  had  long  enjoyed 
without  question  a  monopoly  of  Bay 
Region  transportation.  We  shall  pres- 
ently see  that  such  opposition  did 
develop,  with  a  vehemence  and  per- 
sistence unique  in  the  annals  of  bridge 
construction. 

Following  a  brief  personal  inspec- 
tion and  reconnaissance  of  the  site  and 
its  approaches,  the  writer  returned  to 
the  city  engineer  naming  two  condi- 
tions under  which  he  would  under- 
take the  task:  first,  a  determination 
by  the  City  of  the  limit  of  cost  which 
would  have  to  be  met,  and,  second, 
the  assembly  by  the  City  of  the  neces- 
sary sounding  and  topographical  data 
Brooklyn  bridge  fundamental  to  the  making  of  such  a 

NEW  YORK.  NY  1        T<1  1        r  1- 

study.  1  he  answer  to  the  nrst  condi- 

Spans  from  the  world's  notable  suspension  bridges  drawn  .  r\r\i\  r\r\i\  T*1 

to  the  same  scale  for  purpose  of  comparison  with  the  tion  was  $25,000,000.  I  he  answer  to 

Golden  Gate  span 


-3S00'- 


HUDS0N    RIVER  BRIDGE 

NEW  YORK,  NY 


SAN  FRANCISCO -OAKLAND  BAY 

SAN  FRANCISCO,  CALIF 


BRIDGE 


DELAWARE    RIVER  BRIDGE 

PHILADELPHIA,  PA 


26 


GENERAL  HISTORY 


the  second  was  the  survey  already 
authorized  by  the  Board  of  Supervisors 
under  the  resolution  by  Supervisor 
Welch.  As  already  stated,  Supervisor 
Welch  had  previously  given  such  a 
project  consideration  and  the  Welch 
resolution  was  the  first  official  action 
in  the  movement  for  a  bridge  to  span 
the  Golden  Gate,  and  the  resulting  sur- 
vey became  the  basis  of  the  first  Strauss 
design. 

The  survey  was  duly  carried  out 
with  the  cooperation  of  the  United 
States  Coast  and  Geodetic  Survey.  In 
May,  1920,  the  results  thereof  were 
transmitted  by  the  City  of  San  Fran- 
cisco with  request  for  proposals  not 
only  to  the  writer  alone,  as  he  had  ex- 
pected, but  also  to  two  other  engineers. 
One  appears  not  to  have  responded; 
the  other,  replying  two  years  later, 
gave  as  a  minimum  cost  $60,000,000 
and  a  maximum  of  $77,000,000. 

The  writer's  preliminary  sketch  and  estimate  were  transmitted  June  28,  1921,  and 
embodied  a  symmetrical  cantilever  suspension  design  with  1320-foot  anchor  arms  and 
a  4010-foot  channel  span,  the  latter  being  a  composite  of  two  68  5 -foot  cantilever  arms 
with  a  2640-foot  span  of  the  conventional  suspension  type  between  them.  The  vertical 
navigational  clearance  was  200  feet  at  the  center,  the  towers  800  feet  high,  and  the 
8 0-foot- wide  single  deck  provided  space  for  two  surface  tracks,  four  traffic  lanes  and 
two  7-foot  sidewalks.  The  estimated  cost  was  $21,000,000  for  foundations  and 
superstructure,  $4,500,000  for  highways  and  structural  approaches,  $1,500,000  for 
engineering  and  administration,  or  a  total  of  $27,000,000.  Interest  during  construction 
was  not  included  in  these  figures. 

EVOLUTION  OF  THE  GOLDEN  GATE  BRIDGE  AND 
HIGHWAY  DISTRICT 

The  writer's  proposal,  which  was  submitted  jointly  to  City  Engineer  O'Shaughnessy 
and  the  Mayor's  able  and  progressive  secretary,  Edward  Rainey,  was  received  with 
enthusiasm;  for  here  at  last  was  a  feasible  conception— a  structure  that  could  be  financed 
and  built  for  a  sum  within  the  limits  set  down  as  reasonable.  At  a  first  meeting  between 
Mr.  Rainey,  Mr.  O'Shaughnessy  and  the  writer,  the  difficulty  arising  out  of  the  fact  that 


27 


THE      GOLDEN      GATE  BRIDGE 


the  bridge  would  have  to  be  an  inter-county  undertaking  was  discussed.  Out  of  this 
discussion  and  the  previous  activity  in  connection  with  road  districts  grew  the  suggestion 
of  a  Bridge  District,  a  new  procedure  in  bridge  building.  Mr.  Rainey,  full  of  enthusiasm, 
and  with  the  active  support  of  Supervisor  Welch,  at  once  set  about  presenting  the 
project  to  the  people  of  the  north  coastal  counties  on  this  basis  and  coordinating  public 
interest.  His  efforts  were  conspicuously  public-spirited  and  soon  bore  fruit. 

In  January,  1923,  Frank  P.  Doyle,  banker  and  president  of  the  Santa  Rosa  Chamber 
of  Commerce,  called  and  presided  at  a  meeting  of  representatives  from  San  Francisco 
and  the  North  Bay  counties  in  the  Chamber's  assembly  room.  This  was  the  first  public 
meeting  called  for  the  purpose  of  considering  ways  and  means  for  carrying  out  the 
proposal  to  bridge  the  Golden  Gate.  Among  those  who  were  in  attendance  at  this  historic 
gathering  were  the  Honorable  James  Rolph,  Mayor  of  San  Francisco,  Mr.  Edward 
Rainey,  his  secretary,  Supervisors  Richard  J.  Welch  and  Warren  Shannon,  City  Engineer 
M.  M.  O'Shaughnessy  and  other  public  officials  and  citizens  of  San  Francisco.  At  that 
meeting,  which  the  writer  did  not  attend,  the  Bridging  the  Golden  Gate  Association 
was  formed.  The  assembled  delegates  elected  an  executive  committee  comprising  W.  J. 
Hotchkiss,  chairman;  Supervisor  Richard  J.  Welch,  Captain  L  J.  Hibbard,  all  of  San 
Francisco;  Assemblyman  Frank  L.  Coombs  of  Napa  and  Frank  P.  Doyle  of  Sonoma.  The 

writer  was  requested  to  serve  as  the  com- 
mittee's engineer,  George  H.  Harlan  of 
Marin  as  its  attorney,  and  Mark  Lee  as 
secretary.  Messrs.  Doyle,  Welch  and 
Shannon  have  continued  their  active 
connection  with  the  project  as  Directors 
of  theBridgeDistrict  from  the  date  of  its 
organization.  Mr.  Harlan  became  its  at- 
torney on  January  23,  1929,  and  the 
writer  its  engineer  on  October  7,  1929. 

The  Association  devoted  its  efforts  to 
the  promotion  of  the  Bridge-the-Gate 
idea  amongst  the  north  coastal  counties, 
and  the  securing  of  suitable  legislation 
for  carrying  out  the  project  in  ac- 
cordance with  the  program  tentatively 
agreed  upon  at  the  initial  discussion  of 
this  phase  of  the  project.  In  pursuance 
of  this  purpose  the  Golden  Gate  Bridge 
and  Highway  District  Act  was  drafted 
by  Assemblyman  Coombs,  Attorney 
Harlan  collaborating,  following  the  lines 
of  similar  legislation  which  created  the 


Map  of  Golden  Gate  Bridge  and  Highway  District 


28 


GENERAL  HISTORY 


Marin  Municipal  Water  District.  Mr.  Coombs  took  charge  of  the  legislative  procedure 
at  Sacramento  and,  aided  by  the  officers  and  directors  of  the  Association,  the  service  and 
business  organizations,  the  civic  bodies  and  the  press,  the  Act  became  a  law  on  May  25, 
1923.  The  Bridge  District  as  finally  constituted  comprises  the  counties  of  Del  Norte, 
Sonoma,  Marin  and  San  Francisco  and  parts  of  Napa  and  Mendocino.  (See  District  map 
and  brief  summary  of  the  Act.) 

The  services  that  Mr.  Hotchkiss  rendered  the  Association  were  invaluable.  He  gave  it 
not  only  his  own  time  but  the  necessary  financial  support,  and,  together  with  the  writer, 
carried  the  principal  burden  during  the  long  and  trying  preorganization  period.  The  full 
story  of  that  period  is  an  epic  which  has  no  place  in  this  report,  but  it  would  be  unjust 
not  to  permanently  record  the  great  contribution  made  by  that  small  company  of  early 
pioneers— Congressman  Welch,  Mr.  Hotchkiss,  Mr.  Rainey,  Mr.  Doyle,  Mr.  Shannon, 
Captain  Hibbard,  Assemblyman  Coombs  and  all  those  who  labored  so  long  and 
faithfully  and  purely  as  a  public  service  in  those  days  when  the  Golden  Gate  Bridge  was 
still  just  a  dream  and  when  so  many  sought  to  keep  it  so. 

On  the  following  pages  will  be  found  a  brief  summary  of  the  Golden  Gate  Bridge 
and  the  Highway  District  Act,  which  created  the  Golden  Gate  Bridge  and  Highway 
District  and  by  which  it  functions. 

BRIEF  SUMMARY  OF  THE  BRIDGE  AND  HIGHWAY 
DISTRICT  ACT  OF  CALIFORNIA 

The  Golden  Gate  Bridge  and  Highway  District  was  incorporated  under  the  provisions  of  an  act  of  the 
Legislature  of  the  State  of  California  approved  May  25,  1923  (Stats.  1923,  page  452;  Deering's  General 
Laws  of  California,  1931,  Act  No.  936) .  The  original  act  of  1923  was  amended  by  the  state  legislature  in 
1925,  1927  and  1931.  Some  of  the  essential  features  of  the  Bridge  and  Highway  District  are  as  follows: 

Formation:  The  proceedings  for  the  formation  of  the  district  include  the  adoption  of  ordinances  by 
counties  proposing  to  unite  for  the  purpose  of  forming  a  bridge  and  highway  district  and  the  circulation 
and  filing  of  petitions  for  the  formation  of  the  district  within  such  counties.  The  petitions  are  filed  with  the 
Secretary  of  State,  who  is  required  to  give  notice  of  a  time  and  place  at  which  protests  against  the  formation 
of  the  district  may  be  filed.  Protests,  if  any,  must  be  submitted  to  the  Superior  Courts  in  the  respective 
counties  from  which  they  were  filed  and  after  a  hearing  judgment  is  rendered  by  such  Superior  Courts, 
from  which  appeals  may  be  taken  to  the  State  Supreme  Court.  If  the  final  judgment  is  in  favor  of  the 
validity  of  the  district,  the  Secretary  of  State  issues  a  certificate  of  incorporation,  declaring  the  district 
with  the  boundaries  as  finally  established  to  be  duly  incorporated  as  a  bridge  and  highway  district. 

Directors:  The  district  is  governed  by  a  board  of  directors,  the  members  of  which  are  appointed  by 
the  various  boards  of  supervisors  of  the  different  counties  comprising  the  district.  Each  county  is  entitled 
to  representation  and  the  number  of  directors  to  be  appointed  from  each  county  varies  in  proportion  to  the 
population.  The  board  of  directors  selects  one  of  its  members  to  act  as  president  and  appoints  a  secretary  and 
other  officers  of  the  district,  including  a  general  manager,  auditor  and  attorney. 

Powers:  A  bridge  and  highway  district  has  perpetual  existence,  may  sue  and  be  sued,  may  acquire, 
construct,  maintain  and  operate  bridges,  roads  and  other  properties  of  a  revenue  producing  character.  The 
district  has  the  right  of  eminent  domain,  may  borrow  money  and  issue  bonds  and  cause  taxes  to  be  levied 
and  collected. 


29 


THE     GOLDEN     GATE  BRIDGE 


Bonded  Indebtedness:  In  order  to  incur  a  bonded  indebtedness,  the  directors  must  submit  a  proposi- 
tion to  the  electors  of  the  district  at  a  special  election  called  for  that  purpose.  Such  election  can  be  held  only 
after  due  notice,  and  it  requires  the  vote  of  two-thirds  of  the  qualified  electors  to  authorize  the  issuance  of 
the  bonds.  No  bonded  indebtedness  can  be  incurred  in  excess  of  fifteen  per  centum  of  the  assessed  value  of 
all  property  in  the  district.  The  maximum  term  of  the  bonds  must  not  exceed  forty  years  and  the  maximum 
rate  of  interest  must  not  exceed  six  per  centum  per  annum.  All  such  bonds  are  declared  to  be  legal  invest- 
ments for  savings  banks  and  may  be  used  to  secure  the  deposit  of  public  funds.  The  bonds  may  be  made 
registerable  as  to  principal  alone,  or  as  to  both  principal  and  interest. 

Taxation:  If  the  revenues  of  the  district  are  inadequate  to  pay  the  principal  or  interest  of  the  bonded 
indebtedness  as  it  becomes  due,  the  board  of  directors  is  required  to  cause  a  tax  to  be  levied  upon  all  of  the 
taxable  property  in  the  district,  in  addition  to  all  other  taxes  levied  for  county  or  city  and  county  purposes. 
In  the  month  of  July  of  each  year,  the  board  of  directors  is  required  to  determine  the  amount  necessary  to 
be  raised  by  taxation.  It  must  also  fix  the  rate  of  taxes  to  be  levied  which  will  raise  the  amount  of  money 
required  by  the  district.  The  rate  is  then  certified  to  the  board  of  supervisors  of  each  county  within  the 
district,  with  the  direction  that  at  the  time  and  in  the  manner  required  by  law  for  the  levying  of  taxes  for 
county  purposes,  such  board  of  supervisors  shall  levy  and  collect  a  tax  at  the  rate  so  specified  and  deter- 
mined, and  it  is  made  the  duty  of  the  county  or  city  and  county  officers  to  levy  a  tax  so  required  and  to 
collect  the  same  in  the  time,  form  and  manner  that  county  or  city  and  county  taxes  are  collected.  Such 
taxes  shall  be  a  lien  upon  all  property  within  the  territory  comprising  the  district  and  of  the  same  force  and 
effect  as  other  liens  for  taxes,  and  their  collection  may  be  enforced  by  the  same  means  as  provided  for  the 
enforcement  of  liens  for  county  taxes. 

Supporting  Legislation  and  Judicial  Confirmation  of  the  Acts  Listed:  The  State  Legislature 
by  an  act  approved  April  10,  1929,  validated  the  Golden  Gate  Bridge  and  Highway  District  (Stats.  1929, 
page  165),  and  by  a  comprehensive  validation  act  of  March  12,  1931  (Stats.  1931,  page  77;  Deering's 
General  Laws  of  California,  1931,  Act  No.  93  8)  validated  the  formation  and  organization  of  all  bridge  and 
highway  districts,  the  boundaries  thereof,  the  proceedings  of  the  boards  of  directors,  all  bonds  and  the 
proceedings  for  the  issuance  of  such  bonds,  and  the  levy  and  collection  of  taxes  for  their  payment.  The 
constitutionality  of  the  Bridge  and  Highway  District  Act,  the  proceedings  for  the  formation  of  Golden 
Gate  Bridge  and  Highway  District  and  the  issuance  of  its  bonds,  and  the  power  of  the  District  to  levy  and 
collect  taxes  upon  all  of  the  taxable  property  in  the  District,  was  upheld  by  the  Supreme  Court  of  California 
in  the  cases  of  Doyle  v.  Jordan,  200  Cal.  170;  Wheatley  v.  Superior  Court,  207  Cal.  722;  Dempster  v. 
Superior  Court,  207  Cal.  795;  Crawford  v.  Superior  Court,  207  Cal.  797;  Esaisa  v.  Superior  Court,  207 
Cal.  796,  and  Golden  Gate  Bridge  and  Highway  District  v.  Felt,  82  Cal.  Dec.  683.  An  appeal  from  the 
decision  in  the  Crawford  case  to  the  Supreme  Court  of  the  United  States  was  dismissed  by  that  court  for 
want  of  a  substantial  federal  question  (1930,  281  U.S.  692,  5  0  Sup.  Ct.  23  8,  74  L.  Ed.  1 1 2 1 ).  The  United 
States  District  Court  for  the  Southern  Division  of  the  Northern  District  of  California,  in  Del  Norte 
Company  v.  Filmer  et  al.  (In  Equity  No.  3174-L),  and  Garland  Co.  v.  Filmer  et  al.  (In  Equity  No. 
3  109-K)  again  overruled  the  objections  raised  by  certain  taxpayers,  under  the  Constitution  of  the  United 
States,  to  the  formation  of  the  district,  the  proceedings  for  the  issuance  of  the  bonds  and  the  right  of  the 
district  to  levy  and  collect  taxes. 

Immediately  following  the  passage  of  the  Act,  steps  were  taken  by  the  writer  to 
submit  an  application  to  the  Secretary  of  War  for  a  permit  to  build  the  bridge  and  make 
use  of  the  Federal  property  necessary  for  the  proper  location  and  maintenance  of 
structures  and  approach  roads.  In  view  of  the  current  rumor  that  no  such  permit  would 
be  granted,  and  since  without  a  permit  the  project  would  have  failed,  it  was  essential 
that  the  application  should  be  made  prior  to  the  formation  of  the  District.  The 


30 


GENERAL  HISTORY 


application  was  made  in  the  names  of  the  counties  of  Marin  and  San  Francisco  jointly, 
and  heard  before  Colonel,  now  General,  Herbert  Deakyne  in  San  Francisco  in  May, 
1924— the  City  of  San  Francisco,  City  Engineer  O'Shaughnessy  and  the  Bridging  the 
Golden  Gate  Association  assisting  and  the  writer  presenting  the  case.  The  testimony  in 
favor  of  the  project  was  overwhelming  and,  after  due  deliberation,  Secretary  of  War 
Weeks  issued  a  provisional  permit  December  20,  1924,  granting  authority  to  proceed 
pending  the  submission  of  later,  definite  plans.  This  grant,  as  became  evident  later, 
definitely  committed  the  Government  and  made  the  project  possible. 

The  reader  will  have  noted  that  the  Act  provides  among  other  things  for  the 
financing  of  the  project  by  the  issuance  of  bonds  secured  as  to  interest  and  principal 
primarily  by  the  tolls  derived  from  the  bridge,  supplemented  as  a  secondary  resource  by 
the  power  of  the  District  to  levy  taxes  to  make  up  deficiencies  of  operating  revenue. 
Before  the  component  parts  of  the  District  could  be  put  together,  therefore,  and  incor- 
porated as  a  responsible  political  entity,  it  was  necessary  first  to  give  the  taxpayers  who 
objected  to  the  inclusion  of  their  properties  full  opportunity  to  protest.  And  this  was  a 
made-to-order  opportunity  for  the  project's  enemies.  Taking  full  advantage  of  the 
situation  by  means  of  taxpayers'  suits,  the  opposition,  well-organized  and  with  plenty  of 
money  to  spend,  launched  a  vigorous  campaign  of  obstruction.  For  nearly  six  years  the 
District  was  dragged  through  the  courts  of  the  various  counties  in  succession.  During 
these  years  of  litigation  Humboldt  County  first  joined  in  the  project  and  then  withdrew 
and  parts  of  Mendocino  did  the  same.  In  fact  all  of  Mendocino  County  would  have 
withdrawn  but  for  the  courageous  fight  made  by  Mr.  A.  R.  O'Brien,  publisher  of  the 
Ukiah  Republican  Press,  who  later  became  a  Director  of  the  District,  and  who  has 
always  taken  a  leading  part  in  the  furtherance  of  the  best  interests  of  the  bridge. 

Mr.  George  H.  Harlan  conducted  the  litigation  in  behalf  of  the  District,  with  the 
writer  as  key  witness  and  aided  by  experts  he  brought  from  Chicago  and  New  York.  The 
opposition  had  as  its  witnesses  reputable  engineers  who  stated  under  oath  that  the  project 
would  cost  a  total  of  $1 12,344,788  and  that  the  piers  and  anchorages  alone  would  cost 
$28,800,500.  These  estimates  when  compared  with  the  Chief  Engineer's  estimate  and 
the  actual  cost  as  hereinafter  mentioned  will  be  of  special  interest.  The  opposition  was 
represented  by  vigorous  counsel,  who  left  no  stone  unturned  to  prevent  the  formation 
of  the  District.  Nevertheless  the  District  prevailed  in  all  the  suits,  and  finally  on 
December  4,  1928,  was  incorporated. 


3i 


GENERAL  HISTORY 


ORGANIZATION  OF  THE  DISTRICT 

The  Board  of  Directors  of  the  newly  incorporated  Golden  Gate  Bridge  and  High- 
way District  was  seated  on  January  23,  1929.  The  Board  comprised  the  following: 

County 

William  P.  Filmer,  director  and  President  San  Francisco 

Henry  Westbrook,  Jr.,  director****  Del  Norte 

Robert  H.  Trumbull,  director  and  Vice-President  Marin 

A.  R.  O'Brien,  director   .Mendocino 

Thomas  Maxwell,  director  Napa 

Carl  A.  Henry,  director*  San  Francisco 

Warren  Shannon,  director  San  Francisco 

William  P.  Stanton,  director*  *  San  Francisco 

Francis  V.  Keesling,  director*  *  San  Francisco 

Richard  J.  Welch,  director  San  Francisco 

Frank  P.  Doyle,  director  Sonoma 

Joseph  A.  McMinn,  director  Sonoma 

The  first  act  of  the  Board  was  the  appointment  of  the  following  officers: 

Alan  MacDonald,  General  Manager,  ***  1929  to  1933   San  Francisco 

Joseph  B.  Strauss,  Chief  Engineer,  October  1929  to 

October  1937   San  Francisco 

George  H.  Harlan,  Attorney,  1929  Marin 

John  R.  Ruckstell,  Auditor,  *  1929  to  193  5   San  Francisco 

William  W.  Felt,  Jr.,  Secretary,  1929  San  Francisco 

Later  the  Board  was  increased  to  fourteen  by  the  addition  of  the  following  two 
members: 

George  T.  Cameron,  ***  1930  to  1933  San  Francisco 

Harry  Lutgens,  1930   Marin 

Vacancies  created  by  the  deaths  and  retirements  noted  above  were  filled  as  they 
occurred  by  the  following  appointments: 

John  P.  McLaughlin,  director,  1934  San  Francisco 

Hugo  D.  Newhouse,  director,  1933  San  Francisco 

Arthur  M.  Brown,  Jr.,  director,  1934  San  Francisco 

William  D.  Hadeler,  director,  1936  San  Francisco 

James  Reed,  General  Manager,  1933  to  1937  San  Francisco 

Roy  S.  West,  Auditor,  1936  San  Francisco 

*Died.  **Retired  at  expiration  of  term.  ***Subsequently  resigned. 

****Mr.  Westbrook  at  the  expiration  of  his  first  term  was  succeeded  by  Milton  M.  McVay,  who  in  turn  was  succeeded  by 
Mr.  Westbrook. 


33 


THE      GOLDEN      GATE  BRIDGE 


The  Board  of  Directors  met  on  Wednesdays  three  times  monthly  throughout  the 
construction  period  and  functioned  through  appropriate  committees.  The  two  com- 
mittees having  the  most  direct  contact  with  construction  were  the  Building  Committee, 
under  the  efficient  chairmanship  of  Mr.  Keesling  up  to  the  time  of  his  retirement,  when 
he  was  succeeded  by  Mr.  Maxwell,  an  able  leader,  and  the  Highways,  Roads  and  Traffic 
Committee,  with  its  fearless  and  dynamic  chairman,  Mr.  O'Brien.  The  Building  Com- 
mittee served  as  the  liaison  medium  between  the  Board  and  the  Chief  Engineer  and 
under  the  splendid  leadership  of  Mr.  Keesling  was  a  most  constructive  force.  The 
Finance  Committee  has  been  ably  headed  by  Mr.  Trumbull  throughout,  as  chairman, 
while  Mr.  Shannon  was  the  capable  chairman  of  the  Printing  Committee. 

Immediately  after  taking  office  the  Board  was  confronted  with  the  necessity  of 
providing  funds  for  carrying  out  the  purpose  for  which  it  was  appointed,  namely  the 
building  of  the  Golden  Gate  Bridge.  The  Act  provides  that  such  funds  may  be  raised 
in  the  preliminary  stages  of  the  enterprise  by  taxation.  Accordingly,  a  tax  rate  of  3 
cents  per  $100  was  levied  on  all  taxable  property  in  the  District  on  July  24,  1929  for 
preliminary  expenses,  and  an  additional  2  cents  was  levied  in  July  the  following  year, 
making  a  total  of  5  cents,  yielding  about  $465,000.  The  assessed  value  of  all  District 
property  for  taxation  purposes  is  a  little  under  one  billion  dollars. 

The  Chief  Engineer  was  appointed  August  15,  1929.  He  was  selected,  on  the  basis 
of  a  written  proposal,  after  the  Board  had  carefully  considered  proposals  from  nine  of 
the  leading  engineers  of  the  country.  He  is  a  bonded  officer  of  the  District. 

Under  the  contract  entered  into  between  the  District  and  the  writer  as  Chief  Engi- 
neer October  7,  1929,  the  latter  was  given  complete  charge  of  the  engineering  work  of 
the  project  including  architectural  design,  geology,  traffic,  inspection  and  supervision 
of  construction.  Messrs.  O.  H.  Ammann  and  Leon  S.  Moisseiff  of  New  York  City, 
named  in  the  writer's  proposal  as  Consulting  Engineers,  were  so  appointed.  Subse- 
quently, the  Directors  added  the  name  of  Charles  Derleth,  Jr.  of  the  University  of 
California.  These  four  men  were,  by  contract,  constituted  an  Advisory  Engineering 
Board  operating  under  the  direction  of  the  Chief  Engineer  as  Chairman. 

In  November  1929,  the  Chief  Engineer  opened  a  local  office  in  San  Francisco  in  the 
Russ  Building.  A  year  later  he  moved  to  the  Financial  Center  Building  in  offices  adjacent 
to  those  of  the  General  Manager.  From  these  two  offices  he  personally  conducted  the 
operations  prior  to  the  beginning  of  construction.  In  March,  1933,  the  District's  offices 
were  permanently  located  in  the  Hunter-Dulin  Building  and  the  Chief  Engineer  then 
moved  his  own  offices  adjacent  to  the  District's  offices  in  that  building.  This  office 
remained  throughout  as  the  personal  headquarters  of  the  Chief  Engineer  and  the 
clearing  house  through  which  all  the  engineering  operations  were  conducted. 

There  were  three  additional  offices  maintained  by  the  Chief  Engineer;  one,  the  home 
office  in  Chicago,  where  the  designing,  computing,  detailing  and  the  major  portion  of 
the  plans  were  executed;  two,  a  principal  Field  Office  at  Fort  Point,  serving  as  head- 
quarters of  the  Resident  Engineer,  and,  three,  a  secondary  Field  Office  in  Marin  County. 

J4  The  old  fort  at  Fori 

is  now  dwarfed  b 
structure  which  t 
above  it.  The  Toll 
can  be  seen  in  th 
foreground 


THE    GOLDEN     GATE  BRIDGE 


As  geologist,  the  Chief  Engineer  appointed  Professor  Andrew  C.  Lawson  of  the 
University  of  California.  As  traffic  engineer  he  appointed  Sydney  W.  Taylor,  Jr.  of 
Berkeley,  and  to  carry  out  the  details  of  the  architectural  design  as  laid  down  he  ap- 
pointed Irving  F.  Morrow  as  consulting  architect.  Later  Allan  E.  Sedgwick  of  Los 
Angeles  was  added  as  associate  consulting  geologist.  These  men  were  all  preeminent  in 
their  profession. 

When  the  writer  left  Chicago  to  assume  his  duties  as  Chief  Engineer  of  the  Dis- 
trict, he  placed  Mr.  Clifford  E.  Paine  in  charge  of  the  Chicago  office,  and  later,  in  1931, 
he  designated  Mr.  Paine  as  his  Principal  Assistant  Engineer  on  the  Golden  Gate  Bridge 
and  Mr.  Charles  H.  Clarahan,  Jr.  and  Mr.  Dwight  N.  Wetherell  of  the  Strauss  &  Paine, 
Inc.  staff  in  Chicago  as  Assistant  Engineers.  From  that  time  on,  the  Chicago  office,  with 
its  staff  of  approximately  forty  men,  was  devoted  almost  exclusively  to  the  Golden 
Gate  Bridge  work.  Most  of  the  development  of  the  design  and  the  details  and  most  of 
the  plans  were  executed  there. 

Later  on,  as  the  work  in  the  field  progressed,  the  Chief  Engineer  arranged  for  a 
division  of  Mr.  Paine's  time  between  San  Francisco  and  Chicago  and  during  the  last 
three  years  most  of  Mr.  Paine's  time  has  been  devoted  to  assisting  the  Chief  Engineer  in 
the  San  Francisco  office,  where,  under  his  direction,  he  supervised  the  work  in  the  field 
and  shops  to  insure  its  execution  in  accordance  with  the  intent  of  the  design. 

On  February  15,  1933  Mr.  Russell  G.  Cone,  whom  the  Chief  Engineer  had  earlier 
appointed  as  Resident  Engineer,  entered  upon  his  duties  in  the  field  at  San  Francisco, 
with  Mr.  Theodore  M.  Kuss  as  his  assistant.  At  the  same  time  Mr.  W.  J.  Evans  was 
placed  in  charge  of  the  surveying  staff  in  the  field.  These  men  with  their  staff  were 
housed  in  the  field  offices  at  the  site. 

Inspection,  being  a  highly  important  function  of  the  Chief  Engineer,  was  organized 
with  great  care.  After  thorough  consideration  Mr.  Herbert  J.  Baker  was  selected  to 
organize  and  head  the  District's  eastern  inspection  staff  with  headquarters  in  New  York 
City.  This  staff  inspected  the  work  performed  in  the  eastern  mills  and  shops.  Inspection 
in  the  western  mills  and  shops  was  placed  with  Smith,  Emery  and  Company  of  San 
Francisco. 

The  total  engineering  force,  including  designers,  detailers,  surveyors  and  inspectors 
numbered  approximately  one  hundred  men.  This  staff,  operating  under  the  direction 
of  the  Chief  Engineer,  handled  all  of  the  work  on  the  project  from  its  inception  to  its 
conclusion,  with  one  exception,  namely  that  on  February  1,  1933  the  Board  of  Direc- 
tors by  resolution  transferred  the  planning  of  the  Sausalito  Lateral  work  to  the  Cali- 
fornia State  Highway  Commission.  The  work  was  executed  as  a  W.P.A.  project 
sponsored  by  the  District.  Certain  parts  of  the  Military  replacement  program  were 
similarly  handled.  The  Waldo  Point  Approach  and  the  Funston  Avenue  roads,  in  ac- 
cordance with  the  original  program,  are  a  part  of  the  California  State  Highway  Com- 
mission's contribution  to  the  project  and  the  design  and  construction  of  these  roads  as 
built  and  to  be  built  are  in  their  hands. 


36 


GENERAL  HISTORY 


CHIEF  ENGINEER'S  REPORT  OF  1930 

The  first  meeting  of  the  Board  of  Engineers  was  held  in  San  Francisco  during 
August  1929.  This  meeting  resulted  in  the  adoption  of  design  specifications  and  definite 
methods  of  procedure,  including  among  other  things  the  decision  to  carry  out  immedi- 
ately the  necessary  exploratory  drilling  and  soil  tests  in  connection  with  the  foundations 
and  anchorages.  In  the  interval  which  had  elapsed  any  advantages  possessed  by  the 
cantilever-suspension  type  bridge  had  practically  disappeared  and  on  recommendation 
of  the  Chief  Engineer,  the  cantilever-suspension  type  was  abandoned  in  favor  of  the 
simple  suspension  type. 

The  following  month  preliminary  surveys  were  started  in  connection  with  the 
bridge  approaches  in  the  Presidio  and  Fort  Baker  military  reservations.  Conferences 
followed  with  civic  organizations  and  improvement  clubs,  with  the  military  authorities, 
the  City  and  the  State  for  the  purpose  of  ascertaining  their  views  respecting  bridge  out- 
lets and  road  connections.  Negotiations  were  concluded  with  the  Highway  Commission 
whereby  they  would  undertake  the  construction  of  the  Waldo  Point  and  Funston 
Avenue  roads  as  a  part  of  the  State  Highway  system.  And  in  October  the  writer  ac- 
companied President  Filmer  to  Washington,  D.  C,  where  during  a  conference  with 
the  Secretary  of  War  the  latter  stated  that  the  provisional  permit  issued  in  December, 
1924,  was  regarded  as  an  agreement,  but  that  it  would  be  desirable  later  to  hold  another 
hearing  for  consideration  of  a  final  permit. 

Bids  were  invited  for  borings  at  the  site  of  the  south  pier  a  short  time  later  and  the 
E.  J.  Longyear  Exploration  Company  was  awarded  the  contract.  Meanwhile  Geologist 
Andrew  C.  Lawson  had  begun  his  geological  studies,  and  preparations  were  made  for 
carrying  out  the  soil  pressure  test  behind  Old  Fort  Point,  the  results  of  which  the  reader 
may  have  noted  in  his  reading  of  the  section  on  Geology. 

The  second  session  of  the  Engineering  Board  was  held  in  San  Francisco  in  February, 
1930,  the  General  Manager,  Traffic  Engineer,  and  Geologist  Lawson  attending.  Results 
of  the  borings,  soil  pressure  test  and  other  foundation  data  gathered  since  the  Board's 
previous  session  were  examined  and  it  was  concluded  that  foundation  conditions 
throughout  were  entirely  satisfactory.  It  was  at  this  session  that  the  Board  approved 
the  Chief  Engineer's  recommendation  that  the  span  be  increased  to  4200  feet  in  order 
to  permit  the  location  of  the  north  pier  on  a  projecting  ledge  at  the  Marin  shoreline. 
This  would  minimize  under-water  work.  The  Chief  Engineer  presented  his  outline 
studies  of  the  general  design,  the  architectural  treatment  and  the  structural  ap- 
proaches—the latter  based  on  non-interference  with  Old  Fort  Point.  The  main  dimen- 
sions of  the  structure  were  fixed  in  accordance  with  this  design,  remaining  substantially 
the  same  as  those  of  the  original  design,  except  that  the  distance  center  to  center  of 
main  trusses,  on  Mr.  Moisseiff's  suggestion,  was  increased  from  80  feet  to  90  feet.  The 
original  type  of  floor  system  was  retained,  but  the  surface  tracks  provided  in  the  original 
design  were  eliminated.  It  was  felt  that  the  era  of  surface  cars  as  a  means  of  rapid  mass 


37 


GENERAL  HISTORY 


transportation  had  passed.  This  provided  six  clear  10-foot  traffic  lanes  and  two  10-foot 
sidewalks.  Tentative  design  specifications  were  agreed  upon,  and  the  Traffic  Engineer 
presented  his  preliminary  traffic  report. 

The  hearing  for  the  final  War  Department  permit  was  set  for  June  30,  1930,  in  the 
Board  of  Supervisors'  Chambers,  San  Francisco.  Meanwhile  the  organized  opposition 
had  not  been  slumbering.  Here  was  another  ready-made  opportunity,  and  this  time  the 
shipping  interests  assumed  the  role  of  principal  spearhead.  The  hearing  was  conducted 
by  a  Special  Army  Board  comprising  three  high-ranking  officers  of  the  Engineering 
Corps  appointed  by  the  Secretary  of  War.  The  District's  case,  conducted  by  the  Chief 
Engineer,  was  supported  by  a  battery  of  experts,  each  a  distinguished  specialist  in  his 
own  particular  line.  The  protestants  did  not  contest  the  horizontal  clearance.  They 
merely  questioned  the  adequacy  of  the  vertical  clearance,  and  in  addition,  pointed  out 
that  enemy  bombing  or  gun  fire,  by  destroying  a  bridge  located  at  the  very  entrance  of 
the  harbor,  would  without  doubt  most  effectually  bottle  up  the  harbor.  They  con- 
tended further  that  the  vertical  clearance  in  a  bridge  spanning  the  entrance  of  a  harbor 
like  San  Francisco's  should  be  unlimited,  in  other  words,  no  bridge  at  all  should  be  per- 
mitted across  the  Golden  Gate. 

Upon  conclusion  of  the  hearing  the  Special  Board,  after  due  deliberation  forwarded 
its  report  to  General  Lytle  Brown,  the  then  Chief  of  Engineers  of  the  U.  S.  Engineer 
Corps.  Shortly  thereafter  the  writer  accompanied  by  Attorney  Harlan,  went  to  Wash- 
ington where,  after  an  extended  hearing,  and  with  the  help  of  California's  Senator 
Shortridge  and  Congressman  Welch,  the  writer's  position  was  sustained,  and  on  August 
11,  1930,  the  War  Department  issued  its  permit  on  the  basis  of  a  4200-foot  span  and  a 
vertical  clearance  of  220  feet  at  mid-span  and  210  feet  at  the  towers.  General  Brown 
stated  that  he  was  opposed  to  granting  the  permit,  but  that  the  provisional  permit  of 
1924  left  him  no  alternative. 

These  preliminaries  paved  the  way  for  the  preparation  of  the  Chief  Engineer's  offi- 
cial report  to  the  Directors  which,  according  to  the  program  laid  down,  was  to  be  sub- 
mitted to  the  electors  of  the  District  as  the  official  plans  and  estimate  upon  which  they 
were  to  vote.  The  report  briefly  described  the  project,  summarized  the  data  gathered 
since  the  writer's  appointment  as  Chief  Engineer  and  included  general  plans,  architec- 
tural sketches,  layout  of  approach  roads,  terminals  and  Toll  Plaza,  estimates  of  cost  and 
forecasts  of  traffic  and  revenue.  In  short  this  report  covered  the  entire  project.  It  was 
completed  August  27,  1930  and  issued  in  three  volumes— Volume  I  being  the  printed 
report  proper,  with  Synopsis;  Volume  II,  the  printed  report  on  traffic  matters,  and 
Volume  III,  the  drawings. 

In  submitting  this  report  the  writer  informed  the  Directors  of  the  District  that  he 
had,  in  many  conferences  with  the  responsible  State  Highway  and  City  officials  and 
officers  of  the  Ninth  Corps  Area  stationed  at  the  Presidio,  reached  general  agreements 
on  certain  military  replacements  and  the  alignment  of  the  approach  roads  and  the  points 
at  which  traffic  should  be  delivered;  and  that  he  had  been  successful,  as  well,  in  obtain- 


ie  Presidio  Approach 
>ad  as  seen  from  the  top 
the  San  Francisco  Tower 


39 


THE     GOLDEN     GATE  BRIDGE 


ing  a  firm  commitment  from  the  California  Highway  Commission  to  the  District  that 
the  State  would  build  the  bridge's  main  north-south  approaches  on  both  sides  of  the 
Golden  Gate. 

The  report  showed  an  estimated  construction  cost  of  $27,165,000.  The  Board  of 
Directors  of  the  District  concluded  that  the  proceeds  of  a  $3  5,000,000  bond  issue 
would  be  ample  to  meet  this  construction  cost  plus  a  liberal  allowance  for  administra- 
tion, engineering  and  financial  costs.  It  was  accordingly  decided  that  the  project  should 
be  presented  to  the  voters  of  the  District  in  the  form  and  manner  as  described  in  the 
Chief  Engineer's  official  report  of  August  27,  1930. 

THE  BOND  ELECTION 

While  these  steps  were  being  taken  by  the  District,  the  opposition  had  organized  a 
body  known  as  the  Citizens'  Committee  against  the  Golden  Gate  Bridge  bonds,  number- 
ing among  its  members  many  businessmen,  professional  men  and  taxpayers  who  were 
honestly  convinced  that  the  bridge  was  physically  and  financially  impossible.  This  com- 
mittee took  space  in  a  downtown  office  building,  organized  a  considerable  staff  of  paid 
employees,  and  set  about  with  the  aid  of  speakers— volunteer  and  hired— with  broadcasts, 
paid  advertising  and  printed  matter,  with  house-to-house  canvassers,  to  put  on  a  deter- 
mined campaign  against  the  bonds. 

Debates  were  staged  by  the  opposition  at  various  places.  The  radio  was  widely  used. 
Women's  organizations  and  others  were  beseeched  to  stop  what  was  termed  an  outrage 
and  a  wildcat  scheme.  Directors  and  officers  were  subjected  to  a  constant  campaign 
designed  to  shake  their  confidence  and  break  down  their  resistance. 

The  committee's  propagandists  claimed  that  a  bridge  across  the  Golden  Gate  would 
mar  the  natural  beauty  of  San  Francisco's  world-famed  harbor  entrance,  that  it  would 
destroy  Sausalito's  splendid  isolation,  that  that  city  would  be  overrun  by  week-end 
picnickers,  and  that  an  enemy  fleet  with  well-directed  gunfire  from  distant  points  off- 
shore could  demolish  the  bridge  and  bottle  up  our  fleet. 

The  earthquake  hazard  was  enlarged  upon  and  the  false  information  which  had 
been  circulated  regarding  the  south  pier  site  was  expanded.  Thirteen  local  engineers 
signed  a  roundrobin  asking  that  the  bond  issue  be  defeated.  This  roundrobin  and  other 
alarming  statements  were  given  wide  circulation.  A  banker  of  standing  characterized 
the  bridge  as  an  economic  crime. 

The  picture  painted  of  Marin  was  that  of  a  sparsely  settled  territory  which  would 
not  support  sufficient  traffic  to  permit  a  toll  bridge  to  meet  its  financial  obligations. 
Constantly  reiterated  throughout  the  whole  campaign  was  the  charge  that  the  cost  of 
the  project  was  grossly  underestimated.  This  thought  was  so  deeply  bedded  in  the  minds 
of  the  public  that  it  persisted  almost  up  until  the  time  the  bridge  was  opened  to  traffic. 
Articles  in  the  local  and  eastern  press  spread  the  story  throughout  the  nation  until  the 
public  generally  came  to  believe  that  the  bridge  could  not  and  would  not  be  built. 

./->  Tower-top  details.  Not 

'  the   cable-housings  o 

either  side  of  the  saddl 
and  the  airway  beaco 
above 


THE      GOLDEN      GATE  BRIDGE 


The  writer  in  the  beginning  of  this  campaign  was  authorized  by  the  Directors  of 
the  District  to  organize  a  Bureau  of  Information  in  order  that  the  opposition's  unin- 
formed statements  and  misleading  propaganda  and  fear  campaign  might  be  counter- 
acted and  the  voting  public  given  the  true  facts.  This  bureau  was  placed  under  the 
direction  of  Charles  W.  Duncan,  aided  by  two  technical  experts  assigned  to  him  from 
the  Chief  Engineer's  staff.  Mr.  Duncan  selected  Miner  Chipman,  who,  as  head  of  the 
newly  created  organization's  Speakers'  Bureau  (in  which  the  Junior  Chamber  of 
Commerce  cooperated)  performed  notable  service  in  addresses  to  the  civic  and  im- 
provement clubs  all  over  the  district  and  in  the  broadcasting  rooms  of  the  radio  studios. 

This  Bureau  of  Information,  ably  supported  by  the  bridge  Directors,  all  of  the  offi- 
cials and  consultants,  and  with  some  exceptions  the  press,  was  successful  in  securing 
endorsement  of  the  project  by  one  hundred  separate  civic  organizations,  and  as  a  result 
of  its  intelligently  directed  labors  the  electors  of  the  District,  on  November  4,  1930,  by 
a  majority  well  over  the  two  thirds  required  by  law,  voted  approval  of  the  issuance  of 
$3  5,000,000  face  value  of  Golden  Gate  Bridge  and  Highway  District  bonds. 

BIDDING  PLANS  AND  BIDS 

With  the  District's  bonds  approved  by  the  unprecedented  majority  of  145,057  to 
46,954  the  way  now  seemed  cleared  to  start  the  project  without  further  delay,  and  the 
Chief  Engineer  was  so  directed.  Accordingly,  arrangements  were  made  with  the  Coast 
and  Geodetic  Survey  for  a  triangulation  survey,  and  conferences  were  held  with  the 
State  Highway  Engineer  in  connection  with  the  State's  program  for  building  the  Waldo 
Point  and  Funston  Avenue  approach  roads  and  with  the  military  authorities  in  deter- 
mining the  rights  of  way  for  these  roads  within  the  Fort  Baker  and  Presidio  reservations. 

We  have  noted  the  opposition's  insistence  throughout  the  bond  campaign  that  the 
Chief  Engineer  had  grossly  underestimated  the  project's  cost.  If,  then,  the  District's 
Directors  could  be  induced  to  pledge  themselves  that  construction  would  not  be  started 
unless  the  total  of  the  contractors'  bids  came  within  the  amount  of  the  bond  issue,  the 
project  by  this  means  might  effectually  be  killed.  The  Directors,  toward  the  end  of  the 
bond  campaign,  with  entire  confidence  in  the  estimates,  had  so  pledged  themselves.  But 
while  they  were  influenced  in  so  doing  partly  by  the  opposition's  attack,  they  neverthe- 
less felt  that  the  electors  of  the  District  were  entitled  to  definite  assurance  that 
$3  5,000,000,  and  only  that  sum,  would  be  the  total  amount  of  the  financing.  We  shall 
presently  see  that  the  total  of  the  contractors'  bids  came  well  within  this  amount,  leav- 
ing a  comfortable  margin  for  interest  during  construction  and  all  other  costs  besides. 

Pursuant  to  their  pledge,  therefore,  the  Directors  ordered  the  Chief  Engineer  to  pre- 
pare plans  and  specifications  covering  all  units  of  the  work  so  that  lump  sum  bids  could 
be  received  and  the  construction  cost  of  the  project  ascertained  in  advance  of  the  award- 
ing of  any  contracts.  Such  procedure,  of  course,  is  contrary  to  standard  practice  on 
major  jobs,  where  the  starting  of  certain  units  of  construction  must,  in  the  nature  of 


42 


Entrance  to  interior  of 
tower  and  service  elevator 


THE    GOLDEN    GATE  BRIDGE 


things,  be  postponed  until  other  units  have  been  finished.  Nevertheless  the  situation  in 
this  instance  required  the  adoption  of  this  program. 

To  the  end  that  construction  be  gotten  under  way  as  early  as  possible,  it  was  decided 
that  the  Bidding  Plans  should  be  so  drawn  as  to  enable  bidders  to  accurately  prepare 
their  lump  sum  bids,  but  at  the  same  time  allow  the  greatest  possible  flexibility  in  the 
subsequent  development  of  construction  plans  for  those  portions  of  the  work  which 
would  not  be  started  until  later.  It  was  realized  also  that  proper  provisions  should 
be  made  in  the  proposals  and  contracts,  whereby  adjustments  in  the  contractors' 
compensation  because  of  changes  in  plans  could  be  on  a  basis  agreed  upon  in  the 
contracts,  which  was  done. 

The  work  was  divided  into  ten  principal  contracts  including  for  completeness, 
provisional  plans  covering  the  Toll  Plaza,  although  this  unit  was  among  the  last  to  be 
built.  As  to  approaches,  the  plans  included  ( 1 )  a  lateral  to  Sausalito's  south  limits 
leading  from  a  braided  connection  with  the  Waldo  road,  and  (2)  the  so-called  Presidio 
Approach  Road  terminating  at  the  end  of  Marina  Boulevard  in  San  Francisco.  The 
remaining  outlets,  unfortunately,  but  through  no  fault  of  the  District,  were  not 
contracted  for  completion  synchronously  with  the  completion  of  the  bridge,  with  the 
result  that  when  the  bridge  was  completed,  it  lacked  adequate  and  properly  placed 
feeders  to  its  main  approaches. 

Bids  were  advertised  for  as  returnable  in  July,  1931.  The  following  tabulation 
summarizes  by  unit  numbers  and  character  of  work  covered,  the  low  bids  received  on 


that  date: 

I-A  Steel  Superstructure  $10,494,000.00 

I-B  Steel  Cables,  Suspenders  &  Accessories   6,25  5,767.65 

II  San  Francisco  Pier  and  Fender  &  Marin  Pier   2,260,000.00 

III  Anchorages  &  Piers  of  Approach  Spans   1,645,841.2  8 

IV  Steel  Superstructure,  San  Francisco  and  Marin  Approaches   996,000.00 

V  Presidio  Approach  Road   966,180.00 

VI  Sausalito  Approach  Road   67,5  86.00 

VII  Paving  of  Main  Span,  Side  &  Approach  Spans   345,000.00 

VIII  Electrical  Work   133,495.00 

IX  Toll  Houses  &  Service  Buildings   71,430.00 

X  Cement  (Estimated  500,000  bbls.)   1,220,000.00 


Total  $24,45  5,299.93 


In  addition  to  the  above,  there  were  certain  minor  miscellaneous  items  which  could 
of  necessity  only  be  covered  by  estimates.  The  Chief  Engineer's  estimate  of  construction 
cost,  as  contained  in  his  Report  of  1930  totaled  $27,165,000.  In  the  light  of  the  bona-fide 
bids  above  noted,  it  was  indisputably  evident  that  the  total  cost  would  not  exceed  the 
Chief  Engineer's  estimate. 

Since  the  project  cost,  including  interest  during  the  construction  period  and  all 
other  costs  and  allowances,  was  thus  established  at  a  figure  comfortably  under  the 


44 


GENERAL  HISTORY 


amount  of  the  bonds,  the  pledge  of  the  Directors  had  been  fulfilled.  However,  the 
District  was  still  not  in  position  to  award  the  contracts  and  begin  the  work  because 
of  the  new  litigation  referred  to  in  the  following  section.  Accordingly,  provisional 
agreements  were  entered  into  with  the  bidders  on  the  principal  contracts  in  the 
expectation  that  the  District  might  retain  the  benefits  of  the  bids  received.  On  certain 
other  contracts,  such  as  Contract  VI,  bids  were  rejected  because  of  the  decision  to  assign 
the  planning  of  this  lateral  to  the  California  State  Highway  Commission  as  already 
stated.  The  bid  on  the  paving  was  also  deferred. 

SECOND  STAGE  OF  LITIGATION 

As  the  reader  has  already  seen,  there  was  extended  litigation  in  connection  with 
the  formation  of  the  District  and  it  was  assumed  that  this  was  all  that  was  involved, 
but  it  developed  before  the  work  could  be  proceeded  with  that  it  was  necessary  that 
California's  Supreme  Court  first  clarify  certain  constitutional  questions  having  to 
do  with  the  District's  power  to  tax.  These  questions  had  been  raised  by  investment 
bankers— prospective  bidders  for  the  District's  bonds— and  one  of  the  contractors. 
Clarification  was  essential  before  the  bonds  could  be  marketed. 

In  view  of  its  urgency  the  Court  heard  the  matter  without  undue  delay,  and, 
although  the  opposition  through  counsel  intervened  in  the  proceeding,  the  Court's 
favorable  decision  was  soon  rendered,  only  one  Justice  dissenting. 

With  the  favorable  decision  of  the  Supreme  Court  behind  them,  officials  of  the 
District  hoped  that  the  project  had  taken  its  last  legal  hurdle  and  that  they  could  now 
sell  their  bonds,  award  contracts,  and  proceed  uninterruptedly  with  the  business  of 
building  the  bridge.  But  new  litigation  developed,  this  time  in  the  United  States  District 
Court,  the  plaintiffs  being  the  Del  Norte  Company  and  the  Garland  Company, — two 
tax-paying  corporations  from  the  North. 

The  District  thus  found  itself  defendant  in  an  action  which  might  conceivably 
continue  litigation  for  several  years.  Whether  the  District  in  these  circumstances  could 
be  held  together  that  long  was  by  no  means  certain.  But  the  Directors,  having  received 
the  people's  mandate  at  the  bond  election  to  build  the  bridge,  engaged  special  counsel 
to  carry  out  a  vigorous  defense. 

In  the  spring  of  1932  with  Orrick,  Palmer  and  Dahlquist  as  associate  counsel,  the 
District  won  in  the  trial  court.  At  that  time  men  walked  the  streets  looking  for 
employment  and  the  equipment  of  steel  mills  and  cement  plants  were  depreciating  in 
idleness.  Nevertheless,  the  opposition  decided  to  appeal,  and  carry  the  case  to  the 
Supreme  Court  if  necessary.  But  an  aroused  public  had  meantime  become  more  and 
more  vocal,  contending  that  the  electors  of  the  District  had  voted  the  bonds  by  a  huge 
majority  and  that  the  opposition  had  had  its  day  in  court.  To  the  cumulative  force  of 
this  pressure  the  opposition  at  last  gave  way  and  instructed  counsel  to  withdraw  the 
appeal,  and  accordingly  this  litigation  was  terminated  in  July,  1932. 


45 


GENERAL  HISTORY 


But  just  as  steps  were  being  taken  to  proceed  with  the  letting  of  the  contracts,  a  new 
source  of  delay  arose.  The  Bankamerica  Company,  heading  a  syndicate  to  finance  the 
District,  had  bid  92.3  for  the  first  offering  of  bonds,  making  the  effective  rate  of  interest 
5.2  5  per  cent.  In  the  opinion  of  the  District's  legal  advisors  in  New  York,  which,  by  the 
way,  conflicted  with  the  local  legal  opinion,  this  rate  exceeded  the  permissible  rate,  since 
the  Directors  had  asked  the  electors  of  the  District  for  approval  of  5  per  cent  bonds. 
Nevertheless  and  although  this  was  nothing  more  than  a  technicality,  it  was  decided  that 
only  a  court  trial  could  remove  the  doubt  as  to  the  legality  of  the  bonds.  The  District's 
funds  by  that  time  had  become  exhausted  and  the  District,  although  victorious  in  every 
legal  encounter,  feared  to  levy  a  new  tax  to  carry  on  in  the  face  of  this  new  and  unex- 
pected obstacle.  Furthermore,  litigation  would  consume  valuable  time  and  indefinitely 
postpone  the  starting  of  construction. 

Realizing  the  seriousness  of  this  situation,  the  Chief  Engineer  with  a  strong 
committee  of  Bridge  Directors  and  officials  presented  the  District's  problem  to  A.  P. 
Giannini,  chairman  of  the  Board  of  the  Bank  of  America.  Mr.  Giannini  pledged  his 
bank's  support,  and,  as  a  result  and  through  the  splendid  work  of  Will  F.  Moorish  (the 
bank's  president  at  that  time)  and  local  bond  houses,  a  new  bond  syndicate  headed  by 
the  Bank  of  America  was  formed.  Notwithstanding  an  unfavorable  bond  market, 
this  syndicate  agreed,  pending  a  test  of  the  legality  of  the  interest  rate,  to  purchase 
$3,000,000  of  the  District's  bonds  at  96.23,  making  the  effective  rate  of  interest  5  per 
cent,  in  accordance  with  the  interpretation  of  the  New  York  counsel.  In  addition,  the 
syndicate,  pending  determination  of  this  technical  question  that  had  been  raised, 
advanced  $184,600  against  $200,000  of  the  District's  unvalidated  bonds,  as  suggested 
by  the  Chief  Engineer,  as  a  result  of  which  the  District  was  provided  with  the  funds 
it  so  urgently  needed  for  current  expenses.  The  consummation  of  the  project  was 
thus  assured  and  the  District  was  in  a  position  to  proceed  with  construction. 

AWARD  OF  CONTRACTS 

Due  to  the  unexpected  prolongation  of  litigation,  so  much  time  had  elapsed  since 
the  receipt  of  bids  in  July,  1931,  that  the  low  bidders  had  been  released  from  their 
proposals  with  the  single  exception  of  Contract  I-A.  In  the  case  of  this  contract,  which 
covered  the  Steel  Superstructure  of  the  Main  Span,  the  proposal  was  continued  in  effect, 
but  it  was  decided  to  call-for  new  bids  on  other  units  of  the  work.  It  was  also  decided  to 
have  these  new  bids  include  the  cement  as  a  part  of  the  concrete  work  instead  of  calling 
for  separate  bids  as  had  been  done  in  the  former  bidding. 

It  was  also  decided  to  omit  from  the  bids  the  Toll  Terminal  and  the  final  painting, 
the  former  because  the  Toll  Terminal  grant  of  the  government  gave  an  inadequate 
area  and  the  new  area  contemplated  would  of  necessity  invalidate  the  original  layout, 
and  the  latter  because  it  was  a  minor  item,  the  performance  of  which  was  at  least  four 
years  off. 


47 


THE     GOLDEN     GATE  BRIDGE 


The  new  bids,  received  October  14,  1932,  therefore,  together  with  the  former  bid 


on  Contract  I- A,  covered  nine  contracts— I- A  to  VIII  inclusive— and  were  as  follows: 

I-A    Steel  Superstructure  (McClintic-Marshall  Corporation)  $10,494,000 

I-B    Steel  Cables,  Suspenders  &  Accessories  (John  A.  Roebling's  Sons 

Company)     5,8  5  5,000 

II        San  Francisco  Pier  and  Fender  &  Marin  Pier  (Pacific  Bridge  Company)     2,93  5,000 

III  Anchorages  &  Piers  of  Approach  Spans  (Barrett  &  Hilp)   1,8  59,85  5 

IV  Steel  Superstructure,  San  Francisco  and  Marin  Approaches  (J.  H. 

Pomeroy  &  Co.,  Inc.,  and  Raymond  Concrete  Pile  Company)   934,800 

V        Presidio  Approach  Road  (Eaton  &  Smith)   996,000 

VI        Sausalito  Approach  Road      — .  5  9,780 

VII        Paving  of  Main  Spans  (Barrett  &  Hilp  and  Pacific  Bridge  Company) ..  5  5  5,000 

VIII        Electrical  Work  (Alta  Electric  &  Mechanical  Company,  Inc.)   154,470 

Total  $23,843,905 


In  November,  1932,  contracts  were  accordingly  awarded  on  the  basis  of  these  bids 
for  I-B,  II,  III,  IV  and  VIII  and  tentatively  for  V.  Contract  VI  (the  Sausalito  Lateral) 
was  not  awarded  and  was  later  built  as  a  W.P.A.  project,  as  already  stated. 

BUILDING  THE  STRUCTURE 

Construction  was  officially  begun  January  5,  1933.  In  commemoration  of  this  event 
officials  of  the  District  on  February  26  staged  a  ground-breaking  ceremony  at  Crissy 
Field,  the  like  of  which  for  pageantry  and  enthusiastic  support  of  the  citizenry 
had  never  before  been  witnessed  in  the  bay  region.  Director  William  P.  Stanton  was 
chairman  of  the  committee  in  charge,  and  the  writer's  office  was  the  clearing  house 
through  which  the  committee  functioned.  Participation  of  the  United  States  fleet  had 
been  secured;  people  flocked  to  San  Francisco  from  distant  points,  and  the  mayor 
officially  proclaimed  the  day  a  holiday.  Work  on  the  San  Francisco  and  Marin  anchorages 
was  started  close  on  the  heels  of  the  ground-breaking  ceremony. 

We  shall  note  here  only  the  principal  events  of  interest  in  connection  with  the 
project's  building  and  leave  for  discussion  in  subsequent  chapters  such  other  matters  as 
the  details  of  its  construction  and  design  and  the  standards  set  up  for  the  testing  and 
inspection  of  materials.  But  first  we  should  record  that,  while  the  Chief  Engineer  was 
in  full  charge  of  all  work  relating  to  the  design  and  building  of  the  project,  the  Directors 
had  entered  into  an  agreement  with  the  California  State  Highway  Commission  for  the 
planning  of  the  Sausalito  Lateral  in  order  to  facilitate  the  tie-in  of  this  work  with  the 
Waldo  Point  Road  and  its  construction  in  accordance  with  State  Highway  standards. 

The  building  of  this  lateral,  a  two-lane  road,  was  begun  in  April,  1936,  by  the  State 
Division  of  Highways  and  carried  out  as  a  W.P.A.  project  sponsored  by  the  District. 


48 


GENERAL  HISTORY 


Certain  of  the  military  replacements  and  improvements  required  of  the  District  in  the 
Presidio  and  Fort  Baker  reservations  were  similarly  handled— as  W.P.A.  projects.  The 
Waldo  Point  and  Funston  Avenue  approaches,  as  we  have  seen,  were  to  be  financed  and 
built  by  the  State.  The  former  was  completed  as  a  four-lane  road  and  made  ready  for 
traffic  the  day  before  the  bridge  was  opened.  The  negotiations  for  the  latter,  at  this 
writing,  however,  are  still  in  process. 

No  especial  problems  had  to  be  met  in  the  building  of  the  Marin  pier.  It  was  neces- 
sary only  to  enclose  the  area  on  three  sides  by  a  cofferdam  of  steel  sheet  piling  buttressed 
within  by  rock-filled  timber  cribbing,  maintain  the  pumps  in  continuous  operation, 
and  proceed.  But  the  building  of  the  San  Francisco  pier  was  quite  a  different  story. 

We  have  previously  called  attention  to  the  exposed  storm-swept  location  of  the 
bridge  site— the  heavy  ground  swells,  prevailing  high-velocity  cross  winds  and  tidal 
currents  running  upwards  of  seven  knots.  The  San  Francisco  pier,  1125  feet  offshore, 
lies  virtually  in  the  open  sea  and  is  wholly  unprotected  from  the  elements.  The 
contractor's  first  move  toward  the  construction  of  this  unit  was  to  build  an  access 
trestle  22  feet  wide  and  1100  feet  long  from  the  San  Francisco  shore  to  the  pier  site, 
bombing  each  bent  shoe  into  the  solid  rock  of  the  ocean's  floor  as  construction  progressed. 

The  access  trestle  had  hardly  been  completed  when  a  vessel  off  its  course  in  a  thick 
fog  crashed  through  it,  not  without  considerable  damage  to  itself,  and  the  resulting 
breach  had  no  sooner  been  repaired  when  a  section  of  the  structure  800  feet  long  was 
carried  away  in  a  storm.  The  Chief  Engineer  then  ordered  the  trestle  raised  five  feet  and 
securely  guyed  at  intervals  to  the  bedrock  by  anchored,  steel  cables.  Thus  reinforced, 
it  stood  without  further  mishap  until  the  end  of  the  job,  serving  effectively  over  the 
four  year  construction  period  as  a  means  of 
access  for  the  contractors  not  only  for  the  San 
Francisco  pier  but  for  the  steel  superstructure 
as  well. 

The  fender,  an  original  conception  de- 
signed to  play  the  dual  role  of  a  cofferdam 
within  which  the  excavation  and  building  of 
the  pier  could  be  carried  on  and  a  permanent 
fender  to  protect  the  pier  from  the  impact  of 
passing  vessels,  will  be  described  in  detail  in 
following  sections.  The  pier  proper  was  to  be 
built  within  this  fender  by  means  of  a  pneu- 
matic caisson.  The  contractor  had  planned  to 
float  the  caisson  into  position  through  an  open- 
ing left  in  the  east  end  of  the  fender  for  that 
purpose,  the  opening  to  be  closed  as  soon  as 
possible  after  the  caisson  was  inside.  The  cais- 
son was  built  at  the  Oakland  yard  of  the  Moore 


THE     GOLDEN      GATE  BRIDGE 


Dry  Dock  Company  and  successfully  floated  into  place,  but  by  nightfall  of  that  same 
day,  under  the  influence  of  unexpected  heavy  swells  of  unknown  origin,  it  became  a 
battering  ram  which  threatened  to  demolish  the  fender  wall.  At  a  midnight  conference 
the  Chief  Engineer  gave  the  contractor  permission  to  remove  the  caisson,  a  hazardous 
job,  which  was,  however,  successfully  accomplished. 

The  fender  ring  was  then  closed,  the  inside  filled  with  tremie  concrete  up  to 
elevation  — 3  5 ;  using  the  fender  as  a  cofferdam,  the  water  was  pumped  out  and  the 
building  of  the  upper  portion  of  the  pier  was  completed  in  the  dry.  This  was  not  done 
without  hazard,  as  was  evidenced  in  December,  1934,  when  the  prow  of  a  great  ocean 
freighter  suddenly  loomed  out  of  the  fog  with  but  a  few  feet  to  spare.  Nevertheless 
after  20  months'  patient  labor,  including  11  months'  delay,  the  pier  was  completed. 

Subsequent  to  the  bond  election,  the  opponents'  criticism  of  the  south  pier 
foundation  persisted  and  in  order  to  quiet  this  the  Board  of  Directors  authorized  a 
further  and  separate  investigation  of  the  foundation  conditions  existing  at  the  pier  site 
and  upon  completion  of  this  investigation  accepted  the  conclusions  of  its  consulting 
geologists  Andrew  C.  Lawson  and  Allan  E.  Sedgwick,  which  confirmed  that  the  safety 
of  the  foundation  was  beyond  question.  Nevertheless,  after  the  pier  was  well  along 
towards  completion  a  new  attack  was  made  by  a  local  and  meddlesome  geologist  and 
this  was  given  such  widespread  publicity  that  the  whole  subject  was  again  given  a 
further  hearing  by  the  Board  of  Directors,  its  Engineering  Board  and  consulting 
geologists,  with  the  result  that  this  further  criticism  was  found  to  be  equally  fallacious. 
This  finally  ended  the  insistent  campaign  to  impeach  the  safety  of  the  San  Francisco  pier. 

Consideration  had  been  given  by  the  Board  of  Engineers  to  the  use  of  high-silica 
cement  in  the  construction  of  the  San  Francisco  pier  and  fender.  Their  investigation 
convinced  them  that  this  cement  would  produce  concrete  having  superior  qualities  in 
sea  water  exposure  and  they  therefore  recommended  its  use.  So  far  as  the  writer  knows 
this  is  the  first  major  work  to  employ  such  cement. 

During  the  progress  of  the  work  on  the  south  pier,  the  north  pier  and  tower  had 
been  completed  and  the  work  on  the  two  anchorages  and  pylon  groups  had  proceeded 
uninterruptedly.  Some  time  after  work  on  the  Presidio  Approach  road  had  begun, 
objection  was  raised  to  its  terminus  at  Marina  Boulevard,  on  the  ground  that  the  bridge 
traffic  would  increase  the  congestion  on  the  boulevard  intolerably.  The  District  was 
therefore  asked  to  abandon  this  terminus  and  divert  all  the  traffic  to  Lombard  Street. 
After  protracted  negotiation  between  the  City,  the  War  Department,  the  Park 
Commission  and  the  District,  an  agreement  was  reached  on  a  compromise  solution 
proposed  by  the  Chief  Engineer,  whereby  the  Marina  Terminus  was  retained  as  planned 
and  a  secondary  outlet,  for  truck  traffic  principally,  was  carried  behind  the  Palace  of 
Fine  Arts  joining  with  the  Presidio  Approach  by  means  of  a  braided  connection  and 
connecting  with  a  new  diagonal  street  now  called  Richardson  Avenue  and  thence  with 
Lombard  Street.  This  outlet  was  subsequently  built  as  a  W.P.A.  project  sponsored 
by  the  city. 


50 


GENERAL  HISTORY 


The  building  of  the  two  Presidio  viaducts  and  the  Marin  approaches  involved  the 
demolition  and  reconstruction  of  more  or  less  elaborate  systems  of  sometimes  outmoded 
military  structures  and  works,  under  the  supervision  of  the  army  engineers.  The  work 
performed  on  this  phase  of  the  project  includes  among  other  things  the  construction 
of  several  fire  control  stations,  a  $125,000  modern  powder  magazine,  a  rifle  range, 
extensive  machine  and  other  shops  and  gas  stations,  drainage  and  sewerage  systems, 
living  quarters  and  roads. 

The  District,  by  the  terms  of  its  permit  to  use  and  occupy  certain  reservation 
property,  agreed  to  replace  and  make  good  the  damage  to  military  structures  and 
facilities  wherever  there  was  any  interference.  This  was  an  equitable  and  proper  return 
for  the  valuable  concessions  given  the  District  in  rights  of  way,  but  due  to  governmental 
requirements  it  was  a  most  exacting  and  trying  phase  of  the  work,  and  for  the  same 
reason  its  cost  was  an  item  which  constantly  grew  larger. 

The  Toll  Terminal  site,  located  170  feet  south  of  the  south  abutment  of  the  bridge, 
had  been  agreed  to  by  the  Army  as  originally  determined  in  the  preliminary  lay-out 
plans,  but  in  making  the  grant,  the  War  Department  had  limited  the  area  to  200  feet 
by  300  feet.  The  Chief  Engineer  from  the  outset  protested  the  insufficiency  of  this  area 
and  finally  prevailed  upon  the  War  Department  to  reconsider  the  matter.  Accordingly 
in  addition  to  a  liaison  officer  appointed  by  the  War  Department  to  deal  with  the 
District,  a  local  Board  of  Army  Engineers  was  set  up  for  the  specific  purpose  of 
reviewing  this  matter  as  well  as  the  reconstruction  of  various  batteries,  the  planning  of 


Work  progressed 
simultaneously  on 
the  Anchorages, 
Pylons,  Marin 
Tower  and 
San  Francisco  Pier 


THE     GOLDEN      GATE  BRIDGE 


the  powder  magazine  and  other  matters  relating  to  the  work  in  the  Presidio  and  Fort 
Baker.  This  Board  held  formal  hearings  and  after  many  months  of  negotiations  a 
satisfactory  agreement  was  reached  on  all  major  matters  involved,  including  the 
expansion  of  the  Toll  Terminal  area  from  200  by  300  feet  to  3  50  by  500  feet.  Although 
the  latter  dimensions  were  somewhat  less  than  those  urged  by  the  Chief  Engineer,  it  was 
decided  to  accept  them  and  a  revised  permit  was  issued  on  this  basis. 

It  was  necessary  to  divert  Lincoln  Boulevard  just  south  of  the  Toll  Plaza  and 
reconstruct  approximately  a  quarter-mile  length  thereof,  depress  it  and  construct  an 
over-pass  across  it  to  connect  the  Presidio  Approach  road  with  the  Toll  Terminal. 

CONSTRUCTION  PROCEEDS:  The  completion  of  the  south  pier  was  followed  in 
quick  succession  by  the  erection  of  the  south  tower,  the  installation  of  the  cable  catwalks 
and  the  spinning  of  the  cables,  the  placing  of  the  suspended  structure,  and  the  paving  of 
the  bridge  approaches  and  floor— and  the  contractors  for  these  units  of  construction  in 
most  cases  established  new  records  for  speed. 

A  highlight  of  the  work  was  the  concern  given,  throughout  the  construction  period, 
to  the  protection  of  the  workmen.  Most  conspicuous  among  these  precautions  was  the 
safety  net,  suspended  beneath  the  floor  system  from  end  to  end.  This  was  a  costly 
expedient,  and  because  it  was  new  and  unusual  it  met  with  resistance.  But  the  Chief 
Engineer's  plea  to  the  Board  of  Directors  that  if  one  life  were  saved  the  expenditure 
was  justified,  prevailed  and  the  net  was  installed  and  was  the  means  of  saving  nineteen 
lives. 

As  a  result  of  these  measures  there  had  been  but  a  single  fatality  up  to  February  17, 
1937,  since  the  beginning  of  the  work,  establishing  a  new  all-time  record  in  a  field  of 
activity  where  one  man  killed  per  each  million  dollars  expended  has  been  axiomatic. 
Notwithstanding  these  precautions,  the  unexpected  happened  when  on  February  17, 
1937,  one  of  the  stripping  scaffolds  installed  by  the  paving  contractor  fell,  carrying 
with  it  twelve  men  and  2100  feet  of  the  safety  net.  This  deplorable  accident  cost  the 
lives  of  ten  men.  The  work  was  seriously  delayed.  Order  was  ultimately  restored;  new 
stripping  scaffolds  were  put  in  operation,  but  this  time  only  after  they  had  been  checked 
and  approved  by  the  Chief  Engineer;  the  destroyed  net  was  replaced  and  the  work 
proceeded  without  further  fatalities.  The  record  of  life  lost  on  this  structure,  therefore, 
stands  at  eleven,  which  is  unusually  low. 

The  last  unit  of  construction  to  be  completed  was  the  Toll  Terminal,  located  in  the 
Presidio  just  south  of  the  San  Francisco  abutment.  The  preferred  plans  called  for  a 
reinforced  concrete  unit  of  imposing  appearance  in  two  wings  separated  by  steel  and 
glass  toll  booths  surmounted  by  a  concrete  canopy  which  served  as  a  connecting  walk 
between  the  two  wings.  This  design  was  too  costly,  and  after  two  revisions  the  present 
simpler  layout  was  adopted,  and  although  belatedly  begun,  was  nevertheless  finished  in 
time  for  the  bridge  opening.  While  not  in  strict  conformance  with  the  architectural 
requirements  of  the  structure  proper,  the  Toll  Terminal  is  a  compact  and  efficient  unit 

5 2"  The  meeting  of  the  trav- 

elers at  the  center  of  the 
Main  Span  completed  the 
"first-pass"  of  steel  erec- 
tion 


THE      GOLDEN      GATE  BRIDGE 


which  contains,  in  addition  to  administrative  offices,  quarters  for  the  operating  personnel 
and  the  California  Highway  patrol,  and  a  complete  maintenance  section,  including 
machine  shops,  garages,  and  a  power  house.  The  latter  is  a  modern  power  station  in 
every  respect,  serving  the  entire  project,  and  will  be  described  hereinafter. 

It  was  decided  after  careful  consideration  to  equip  the  bridge  throughout  with 
sodium  vapor  lights.  Originally  these  lights  were  to  be  limited  to  the  Presidio  Approach 
and  the  bridge  proper,  but  later  they  were  extended  to  the  Sausalito  Lateral  and  it  is  the 
expectation  that  ultimately  the  Waldo  Point  road  will  be  similarly  lighted. 

Located  on  the  fender  of  the  south  pier  is  a  modernistic  concrete  shaft,  3  5  feet  high, 
on  which  is  mounted  an  aid  to  navigation  light  maintained  by  the  District  under  the 
requirements  of  the  United  States  Lighthouse  Department. 

Electrically-powered  elevators  operate  in  the  east  leg  of  both  towers  for  purposes 
of  inspection  and  maintenance. 

The  two  10-foot  sidewalks  are  limited  to  the  bridge  proper.  On  the  Presidio 
Approach  there  is  a  3  l/z -foot  sidewalk  on  the  east  side  only.  There  are  no  sidewalks  on 
the  Waldo  Point  road  and  the  Sausalito  Lateral,  but  a  steel  underpass  at  the  north  pylon 
connects  the  two  sidewalks  of  the  bridge  and  permits  foot  passengers  to  go  from  one  side 
to  the  other  without  crossing  the  roadway.  Provision  has  been  made  by  the  United  States 
The  closing  top  chord      government  for  parking  areas  near  the  Toll  Terminal  and  also  at  the  Marin  terminus 

member  is  being  .  .  -  1-t  I'll       xur   1  1  •  1  1*1 

placed      near  the  junction  of  the  Sausalito  Lateral  with  the  Waldo  Point  road,  which  gives 


GENERAL  HISTORY 


opportunity  for  pedestrians  to  park  their  cars  and  walk  across  the  span.  No  provision 
has  as  yet  been  made  for  commuter  traffic  or  rapid  transit,  mass  transportation  being 
served  by  existing  facilities. 

COMPLETION:  The  Golden  Gate  Bridge  was  completed  ready  for  traffic  on  May  28, 
1937.  However,  on  the  preceding  day  the  bridge  was  thrown  open  to  pedestrians  only. 
It  was  a  gala  occasion  marking  the  beginning  of  the  Golden  Gate  Bridge  Fiesta  and  from 
morning  until  night  the  bridge  was  packed  with  200,000  joyful  celebrants. 

On  the  following  day,  May  28,  the  Chief  Engineer  in  a  brief  ceremony  turned  the 
bridge  over  to  President  Filmer,  who  accepted  it  on  behalf  of  the  District.  This  was 
followed  by  a  most  impressive  program  at  which  former  Director  Francis  V.  Keesling 
delivered  the  principal  address.  Then  came  a  week  of  gayety  and  carnival,  including  a 
magnificent  pageant  held  at  Crissy  Field.  The  occasion  brought  to  San  Francisco  many 
dignitaries  from  other  states  and  from  Canada  and  Mexico,  the  entire  United  States 
fleet  and  thousands  of  visitors.  A  striking  feature  of  this  celebration  was  the  illumination 
of  the  bridge  by  means  of  flood-lights  playing  on  the  towers.  A  remarkably  beautiful 
effect  was  obtained  which  gave  the  bridge  the  title  "The  Span  of  Gold."  The  celebration 
of  the  opening  of  the  bridge  was  handled  by  a  Citizens'  Committee,  of  which  Supervisor  Directors  of  the 
Arthur  M.  Brown,  Jr.  was  chairman,  Mr.  Eric  Cullenward,  manager,  and  Mr.  Tames  D,s"ict ■ and  engineers 

'  ->  '  '  «->     '  J  gathered  to  witness 

Adam,  publicity  director.  The  results  achieved  were  extraordinarily  successful  and    the  dosing  of  the 

_  |.  11  I  Main  Span  on 

reflect  great  credit  on  all  concerned.  November  is,  me 


THE      GOLDEN      GATE  BRIDGE 


CONSTRUCTION  COST 

The  following  statement  shows  the  cost  of  the  completed  structure  broken  down 
by  principal  items  of  expenditure. 

STATEMENT  OF  CONSTRUCTION  COST 


Marin  Pier   __$  436,000 

San  Francisco  Pier  and  Fender     2,93  5,000 

Shore-end  Pylons       295,000 

Cable  Anchorages  and  Housings   2,32  8,000 

Main  Towers — Steel     6,970,000 

Suspended  Structure — Steel    3,2  50,000 

Cables,  Suspenders  and  Accessories      5,910,000 

Approach  Piers  and  Structural  Steel   1,08  5,000 

Paving  Suspended  Structure  and  Approaches   800,000 

Presidio  Road.__._-  _____      1,314,000 

Sausalito  Lateral  Road   3  3  0,000 

Toll  Plaza       450,000 

Toll  Collection  and  Recording  Equipment   72,000 

Roadway  Lighting  and  Electrical       ____  270,000 

Tower  Elevators       60,000 

Military  Replacements  and  Improvements       575,000 

Miscellaneous  and  Equipment      45,000 


$27,125,000 

Engineering  and  Inspection        2,0  5  0,000 

Administrative  and  Preliminary  Expenses  less  Taxes  Collected   423,000 

Financing — Net     4,068,000 

Surplus       _    1,334,000 


Authorized  Bond  Issue     $3  5,000,000 


In  comparing  the  total  of  the  construction  items  above,  namely,  $27,12  5,000,  with 
the  $27,165,000  estimated  by  the  Chief  Engineer  in  1930,  it  should  be  borne  in  mind 
that  the  above  figure  includes  many  expenditures  not  originally  contemplated.  The 
actual  cost  of  military  re- 
placements, for  example, 
which  was  originally  esti- 
mated by  the  military  author- 
ities at  not  to  exceed  $  100,000, 
actually  ran  into  the  substan- 
tial total  of  $575,000. 

Aerial  view  of  the 
Toll  Plaza  on 
opening  day 


GENERAL  HISTORY 


W 
►J 
M 
< 


y 
2 

H 

CO 

h-H 

Q 

!* 

O 
Q 


W 

H 

< 

w 
Q 

O 

o 


e  q 


o 

Ph 


K     K  K 


■4" 


!  00 

00 

:  vo 

vo 

(N 

:  Tt- 

1-H 

K 

Kr\ 

! 
! 

0 

CM 

00 
0 

VO 

!  ts. 

0 

vo 

CM 

:  0 

O 

1  0 

0 

0 

VO 

1-H 

CM 

vo 

vo 

ON 

•t 

cm 

VO 

so 

vo 

»^\ 

K 

vo 

K 

ON 

vo 

o'N 

r*N 

VO 

VO 

CM 

© 

0 

O 

0 

0 

© 

© 

© 

© 
© 


OO 

K 

00 

vo 

VO 

1 — 1 

vo 

OO 

OO 

CM 

l\ 

«N 

>ys 

■<J- 

'  V 

K 

K 

OO 

■<1- 

© 

00 

OO 

1^ 

CM 

CN 

CM 

© 

cm 

CM 

<*"> 

cm 

© 

vo 

vo 

© 

K 

© 

vo 

vo 

VO 

VO 

K 

ON 

cm 

ON 

© 

ON 

ON 

ON 

ON 

ON 

ON 

ON 

© 

ON 

© 

© 

© 

1— 1 

1— < 

f-H 

© 

© 

© 

© 

K 

VO 

fl 

!  ^ 

ON 

CM* 

1  **** 

© 

VO 

© 

:  ® 

©^ 

© 

I — s 

!  <N 

1— < 

1-H 

OO 

!  cm 

»— H 

© 

© 

© 

© 

1^ 

© 

© 

© 

© 

© 

vo 

OO 

ON 

© 

© 

' — . 

00 

VO 

© 

© 

OO 

© 

00 

VO 

1-H 

© 

©^ 

vo 

l\ 

n~1 

©^ 

ly\ 

ON 

©~ 

ON 

f*N 

©' 

ON 

OO 

ON 

© 

1—1 

CM 

ON 

1-H 

VO 

© 

© 

© 

© 

iy\ 

© 

Is*, 

© 

© 

© 

© 

© 

© 

00 

^H 

1— 1 

© 

© 

VO 

ON 

© 

© 

VO 

«N 

r*N 

ON 

r\ 

© 

© 

VO 

ON 

f*N 

VO 

r*N 

© 

VO 

CM 

© 

© 

CM 

VO 

ON 

© 

OO 

© 

© 

© 

vo 

K 

K 

© 

ON 

© 

VO 

ON 

1  V 

© 

CM 

1-H 

c*"\ 

CM 

OO 

00 

© 

ON 

CM 

00 

00 

K 

CM 

1^ 

OO 

00 

OO 

ON 

ON 

ON 

CM 

ON 

© 

1—1 

r^N 

VO 

<N 

CM 

CM 

CM 

•<1- 

© 

© 

© 

© 

© 

© 

© 

O 

© 

© 

© 

© 

O 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

©^ 

© 

©^ 

© 

©^ 

©_ 

© 

©^ 

c© 

© 

©_ 

© 

©" 

© 

©" 

© 

©" 

©" 

© 

©" 

© 

© 

©" 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

© 

CM 

© 

© 

© 

© 

WN 

r— 1 

CM 

■bO- 

CM 

«1 

Tf" 

1 — \ 

VO 

vo 

1 

K 

i 

1 

1 

1 

i-H 

1 

CM 

1 

CM 

1 

1 

VO 

© 

1 

OO 

CM 

1 

CM 

1 

1 

1 

1 

1 

1 

1 

1 

1 

1 

vo 

m  C 


VO  K. 


ON  © 


59 


1 


1 


GENERAL  HISTORY 


THE  COMPLETED  STRUCTURE 

It  is  a  truism  that  every  great  bridge  project  in  its  consummation  has  contributed 
notably  to  the  science  of  structural  design  and  the  technique  of  the  builder;  and  in  these 
respects  the  Golden  Gate  Bridge  has  been  no  exception.  Nevertheless,  its  outstanding 
contribution  has  not  been  to  these  alone,  but  to  architectonics  as  well,  for  the  structure 
since  its  completion  has  received  notable  recognition  because  of  its  majestic  beauty 
and  size. 

The  reader  has  seen  that  the  project  proper  was  successfully  financed  during  the 
darkest  days  of  the  depression  without  aid  of  government  subsidy  or  loan  and  despite 
the  persistent  opposition  of  influential  vested  interests.  And  he  will  have  noted  among 
its  contributions  to  the  arts  and  sciences  the  south  pier  fender,  constructed  first  as  a 
defense  against  the  elements  while  the  pier  was  being  built,  and  then  serving  as  a 
defense  for  the  completed  pier,  and  that  safety  measures  of  unusual  effectiveness  were 
instituted  and  carried  out  all  through  the  period  of  construction,  among  them  a  net 
suspended  from  the  floor  system,  already  noted,  which  was  the  novel  means  of  saving 
nineteen  lives.  Other  contributions  will  now  be  recorded,  and  the  first  of  these,  quite 
appropriately,  is  the  complete  answer  of  the  finished  job  itself  to  the  fears  of  alarmed 
nature  lovers,  who  insisted  that  a  man-made  bridge  in  such  a  setting  would  mar  the 
beauty  of  the  Golden  Gate. 

We  have  seen  that  the  design  adopted  was  one  in  which  the  essential  beauty  and 
elemental  simplicity  of  a  conventional  suspension  design  was  obtained,  a  design  with 
symmetrical  shore  spans  supported  by  the  cables.  To  this  simplicity  of  line  was  added 
the  dignity  of  the  well-proportioned  portal-braced  towers,  all  in  accordance  with 
the  original  studies.  A  happily-selected  color  scheme  dominated  by  orange-vermilion 
completes  the  picture,  blending  perfectly  with  the  changing  seasonal  tints  of  the  natural 
setting  of  the  bridge  and  the  surrounding  land  masses,  sea  and  sky.  The  effect  is  as  highly 
pleasing  as  it  is  unusual  in  the  realm  of  engineering  structures. 

The  qualities  of  reserve  power  and  serene  dignity  have  been  imparted  to  the  towers 
by  forming  their  two  main  unitary  posts  of  built-up  non-encased  steel  cells.  The  vertical 
lines  of  the  tower  silhouettes  have  been  emphasized  by  the  successive  stopping-off  of 
cells  at  varying  heights.  The  vertical  set-backs  resulting  from  a  rational  disposition  of 
metal  give  the  towers  extremely  graceful  lines.  Four  horizontal  portal  struts  above  the 
floor  line— instead  of  the  conventional  system  of  diagonal  bracing— give  the  towers 
lateral  stiffness;  and  each  strut  has  been  enclosed  by  facia  plates,  so  fashioned  as  to 
coordinate  and  blend  with  the  stepped-off  lines  of  the  towers.  The  strut  spacing,  which 
diminishes  progressively  from  floor  line  to  tower  top,  accentuates  the  height  of  the 
towers;  and  while  this  design  is  unique  and  a  radical  departure  from  traditional  design, 
it  was  nevertheless  accomplished  without  material  increase  in  cost. 

The  vertical  set-back  motive  has  been  carried  out  as  well  in  the  design  of  the  pylons 
which  are  grouped  symmetrically  in  pairs  at  the  two  anchorages,  and  the  lines  of  the 


61 


THE      GOLDEN      GATE  BRIDGE 


approach  structures,  hand  railings  and  sodium  vapor  light  standards  along  the  four-mile 
stretch  of  bridge  and  approach  structure.  Even  the  unsymmetrical  grouping  of  the 
administration  buildings  at  the  Toll  Plaza,  offset  to  some  extent  by  the  graceful  toll 
booths,  does  not  materially  detract  from  the  general  effect. 

Old  Fort  Scott,  dating  back  to  the  late  fifties  as  we  have  seen,  and  still  in  a  good 
state  of  preservation,  now  nestles  between  two  pylons  and  beneath  the  319-foot  steel 
arch  which  at  this  point  supports  the  bridge  floor.  While  the  old  fort  has  no  military 
value  now,  it  remains  nevertheless  a  fine  example  of  the  mason's  art.  Many  had  urged 
the  razing  of  this  venerable  structure  in  order  to  make  way  for  modern  progress  and 
provide  an  uninterrupted  working  area  for  the  bridge  during  construction.  In  the 
writer's  view  it  should  be  preserved  and  restored  as  a  national  monument,  and  that  was 
the  primary  reason  for  the  arch.  Mayor  Rossi,  in  entire  sympathy  with  this  program, 
has  appointed  a  Citizens'  Committee  which  is  now  planning  to  carry  that  program 
into  effect. 

The  southerly  pylon  of  the  group  at  this  point  displays  two  bronze  commemorative 
plaques,  one  on  each  side  facing  the  bridge  roadway  where  they  may  be  read  by 
pedestrians  passing  by.  The  plaque  west  of  the  roadway  is  a  memorial  to  those  heroic 
workers  who  lost  their  lives  while  construction  was  in  progress.  That  on  the  east  exhibits 
joint  dedications,  one  contributed  by  the  District  itself,  and  the  other  by  the  Native 
Sons  of  the  Golden  West. 

Set  into  the  roadway  on  the  center  line  of  the  bridge  at  a  distance  of  180  feet 
southward  from  the  south  abutment  is  a  starred  disk  of  bronze  marking  the  center  of 
the  old  fire  control  station  at  Battery  Lancaster  which  once  occupied  that  site.  In  this 
manner  is  marked  the  point  where  the  first  reconnaissance  of  the  Golden  Gate  Bridge 
was  initiated  by  the  Chief  Engineer.  It  is  interesting  to  note  that  the  present  center 
line  of  the  bridge  passes  through  this  point  and  that  the  present  alignment  of  the 
approach  roads,  terminals  and  the  Toll  Area  site  of  the  bridge  coincides  with  the 
tentative  alignment  established  in  the  first  reconnaissance. 

FORECASTS,  TRENDS  AND  INFLUENCES 

The  traffic  engineer's  revenue  forecasts  of  1930  included  definite  though  relatively 
small  amounts  from  ( 1 )  the  patronage  of  an  expected  interurban  rapid  transit  service 
between  San  Francisco  and  Marin,  and  (2)  public  utility  concessions  such  as  pipe- 
line, conduits  and  the  like,  neither  of  which  had  materialized  when  the  bridge  was 
opened  for  traffic.  Pedestrians,  however,  began  at  once  to  contribute  liberally,  and 
revenue  from  this  source— the  potentialities  of  which  were  not  canvassed  by  the 
estimator— has  gone  beyond  all  expectations  since  the  opening  of  the  bridge.  The  project, 
however,  must  always  rely  upon  the  motoring  public  as  its  chief  source  of  revenue.  In 
bringing  these  historical  notes  to  a  close  the  effect  of  certain  factors  which  have  operated 
since  1929  to  influence  traffic  trends  will  now  be  discussed. 


62 


The  toll-booths  am 
District  administra 
tion  building 


THE      GOLDEN      GATE  BRIDGE 


APPROACHES:  The  Golden  Gate  Bridge  is,  as  stated,  a  project  conceived  and 
justified  as  a  toll  bridge.  For  this  reason  the  studies  underlying  the  conclusion  presented 
in  the  Chief  Engineer's  report  of  1930  were  limited  to  the  examination  of  those  factors 
only  which  would  more  immediately  affect  the  financial  success  of  the  bridge,  and  the 
carrying  out  of  the  origin-destination  surveys  necessary  for  the  purpose  of  determining 
approach  road  locations  and  capacities  was  postponed  pending  the  approval  of  the 
bonds.  Nevertheless,  the  traffic  and  revenue  forecasts  were  very  definitely  predicated 
upon  the  assumption  that  adequate  and  properly  placed  approaches  would  be  provided 
by  the  time  the  bridge  was  opened  to  traffic. 

We  have  noted  that  the  original  plans  called  for  three  primary  approach  stems: 
one  in  Marin  County  connecting  through  a  braided  connection  with  the  Redwood 
Highway  at  Waldo  Point  just  beyond  the  city  limits  of  Sausalito— and  two  in  San 
Francisco  extending  through  the  Presidio  and  connecting  the  toll  plaza  ( 1 )  with 
Funston  Avenue  on  the  south  and  (2)  with  Marina  Boulevard  on  the  east.  In  addition, 
Sausalito  local  travel  was  to  be  routed  over  a  secondary  stem  or  lateral  leading  from 
a  braided  connection  with  the  Waldo  road  to  the  town's  south  limits. 

In  compliance  with  regulations  prescribed  by  the  War  Department,  grade- 
separation  was  to  be  provided  within  the  Fort  Baker  and  Presidio  reservations  wherever 
bridge  roads  crossed  the  military  network.  The  controlling  grades  contemplated  were  6 
per  cent  for  the  Sausalito  Lateral  and  4  per  cent  for  the  remaining  roads.  All  approaches 
were  originally  planned  as  four-lane  roads.  Later  developments  made  it  desirable  to 
change  the  width  of  the  Marina  Approach  to  six  lanes  and  it  was  so  built. 

We  have  noted,  too,  that  the  District  had  budgeted  funds  for  building  the  Marina 
Approach  and  Sausalito  Lateral,  and  that  the  other  feeders  came  within  the  province 
of  the  City  of  San  Francisco  and  the  State  of  California. 

It  is  well  known  that  two  processes  are  involved  in  the  building  of  a  successful  toll 
bridge— once  the  preliminary  studies  have  made  clear  the  project's  engineering  and 
economic  feasibility.  These  are  (1)  the  building  of  the  structure  proper,  and  (2)  the 
linking  of  its  portals  with  the  established  beaten  tracks.  At  the  time  when  the  work  of 
organizing  to  build  the  structure  proper  was  well  in  hand  and  funds  for  the  Marina 
Approach  and  Sausalito  Lateral  had  been  budgeted,  data  were  still  lacking  on  which 
to  base  the  planning  of  effective  highway  feeders. 

Immediately  following  the  bond  election,  the  Chief  Engineer  recommended  that 
a  comprehensive  origin-destination  check  be  authorized  at  an  early  date  in  order  that 
the  District's  negotiators  might  be  properly  informed  when  they  appeared  in  conference 
with  officials  of  the  City  and  State.  But  litigation  intervened— litigation  and  the  other 
delays  recorded— and  more  than  two  years  elapsed  before  the  subject  could  be  broached 
again. 

This  traffic  check  and  study  was  authorized  on  February  20,  193  5,  and  the  results, 
with  supporting  data,  were  made  available  in  the  traffic  engineer's  "Report  on  Condi- 
tions Affecting  Traffic  Which  Will  Use  or  May  Be  Encouraged  To  Use  the 


64 


At  Waldo  Point  in  the  1 
foreground  Route  1 
from  the  north  divi< 
into  two  branches — one 
the  right  leads  tc 
Golden  Gate  Bridge  3 
one  to  the  left  leads 
Sausalito 


THE     GOLDEN     GATE  BRIDGE 


Golden  Gate  Bridge"  transmitted  to  the  Directors  in  September,  1935.  Meantime  the 
City,  with  State  and  Federal  aid,  was  planning  to  improve  Lombard  Street  as  the 
principal  bridge  approach  artery  in  San  Francisco,  a  route  dead-ending  at  Van  Ness 
Avenue  and  even  then  heavily  trafficked  and  serving  as  the  City's  main  approach  to  the 
Presidio,  while  the  Waldo  Approach  road  was  planned  as  a  three-lane  road  with  5.8  per 
cent  grade  and  no  braided  connection  at  Waldo  junction. 

The  State,  ultimately,  agreed  to  build  the  Waldo  Approach  as  a  four-lane  road  and 
the  project  was  later  completed  with  its  5.8  per  cent  grade  and  without  a  braided 
connection  at  Waldo,  in  time  for  the  opening  of  the  bridge— nearly  four  miles  of  heavy, 
difficult  construction  and  a  magnificent  tribute  to  the  energy  and  resourcefulness  of 
California's  Division  of  Highways  and  the  contractors  who  carried  out  the  work.  The 
Lombard-Lyon  Street  Outlet,  at  this  writing,  is  nearing  completion,  but  after  that 
Lombard  Street  has  still  to  be  widened  to  Van  Ness  Avenue,  a  job  involving  property 
damage  and  the  appropriation  of  additional  funds.  As  yet,  the  City  has  no  plans  for 
tapping  the  prolific  traffic  resources  east  of  the  Russian-Nob  Hill  ridge,  and  the  District, 
having  completed  the  Sausalito  Lateral  as  a  W.P. A.  project  as  far  as  the  Fort  Baker  gate, 
has  still  to  negotiate  a  suitable  roadway  into  Sausalito  from  its  southern  limits. 

The  origin-destination  survey  brought  to  light  many  aspects  of  the  proper  function 
of  the  bridge  as  a  traffic  carrier  not  previously  fully  sensed.  The  flow  diagram,  Fig.  1, 
reproduced  from  the  traffic  report  of  193  5  indicates  the  principal  and  lesser  sources  of 
traffic  of  the  bridge  and  shows  the  relative  importance  of  each  source.  We  have  noted 
that  two  of  these  sources,  the  Sacramento  Valley  and  the  western  section  of  San 
Francisco  tributary  to  the  Funston  Avenue  Approach,  have  not  yet  been  provided 
with  feeders.  Each  of  these  two  sources,  according  to  the  flow  diagram,  is  a  potential 
contributor  of  a  seventh  of  the  total  traffic  of  the  bridge.  The  seventh  from  the 
Sacramento  Valley  will  be  shared,  of  course^  with  the  San  Francisco-Oakland  Bay 
Bridge.  But  the  other  is  the  exclusive  feeder  of  the  Golden  Gate  Bridge,  and  until  the 
Funston  Avenue  Approach  has  been  completed,  bridge  patrons  from  the  western  section 
of  the  city  will  be  compelled  to  use  the  Marina  Approach  at  the  expense  of  more  than 
three  additional  miles  of  travel  per  trip,  for,  as  we  have  seen,  the  roadways  within  the 
Presidio  are  permitted  to  have  no  connection  with  the  roadways  of  the  Bridge  District. 

THE  TRAFFIC  RESERVOIR:  We  have  noted  the  instant  response  on  the  part  of 
the  motoring  public  in  the  past  to  every  expansion  of  vehicular  ferry  service  or  reduction 
of  tolls.  This  characteristic  of  San  Francisco's  bay  crossing  traffic  is  brought  out  in  a 
striking  way  by  the  chart,  Fig.  2,  which  was  reproduced  from  material  presented  in 
Volume  II  of  the  Chief  Engineer's  Report  of  August  27,  1930,  and  subsequent  records 
of  ferry  travel  since  1929.  The  record  is  one  of  rapid,  persistent  growth  with  only 
temporary  recessions  when  the  depression  had  set  in,  to  be  followed  by  sharp  upturns 
again  beginning  in  1933.  Traffic  over  the  Marin  lines  during  the  single  month  of  July, 
1931,  for  example,  was  higher  by  nearly  sixty  per  cent  than  that  for  the  entire  year  1919, 


66 


GENERAL  HISTORY 


THE      GOLDEN      GATE  BRIDGE 


when,  as  we  have  noted,  the  motor  vehicle  began  to  be  a  factor  to  be  reckoned  with  as 
a  means  of  transportation. 

The  forecasts  of  1930  were  predicated  upon  the  assumption  that  the  bridge  would 
be  opened  for  traffic  January  1,  1936,  and  that  the  District  would  pay  five  per  cent 
interest  on  its  bonds.  A  definite  program  of  bond  redemptions  was  worked  out,  and  the 
traffic  and  revenue  estimates  were  based  on  vehicular  toll  levels  beginning  with  84.3 
cents  per  average  unit  and  diminishing  each  five-year  period  thereafter  as  the  chart 
shows.  Due  to  litigation  and  the  other  unavoidable  delays  we  have  noted,  the  structure 
was  not  completed  and  opened  for  vehicular  traffic  until  May  28,  1937.  Meanwhile 
the  District  had  been  able  to  place  its  bonds  at  the  average  rate  of  4.34  per  cent,  and  the 
Directors,  adhering  to  the  original  program  of  redemptions,  had  set  the  bridge's 
vehicular  toll  level  at  approximately  50.9  cents  per  average  unit,  since  the  San  Francisco- 
Oakland  Bay  Bridge,  opened  for  traffic  November  12,  1936,  had  already  reduced  its 
tolls  approximately  to  that  level  the  following  February.  . 

For  the  sake  of  completeness,  the  chart  shows,  also,  the  indicated  traffic  and 
revenue  for  the  first  operating  year  of  the  bridge,  together  with  the  total  for  bond 
interest  and  estimated  operating  expenses.  Bond  redemption,  under  the  program,  does 
not  begin  until  1942.  It  should  be  pointed  out,  however,  that  these  traffic  and  revenue 


Fig.  2 — Forecast  of  Golden  Gate  Bridge  vehicular  traffic  and  revenue 


68 


GENERAL  HISTORY 


estimates  are  based  on  but  two  months'  experience,  and,  although  the  amounts  recorded 
therefor  have  been  liberally  adjusted  to  eliminate  the  curiosity  travel  of  these  first  two 
months,  many  influences  can  operate  before  next  August  to  reduce  the  bridge's  share 
of  the  total  travel  between  San  Francisco  and  Marin.  As  an  example,  the  California 
Railroad  Commission  authorized  a  drastic  reduction  in  automobile  rates  applicable 
to  the  competing  lines  of  the  Southern  Pacific  Golden  Gate  Ferries,  Ltd.,  and  effective 
the  11th  of  August,  1937.  Since  then,  both  the  Golden  Gate  and  the  San  Francisco- 
Oakland  Bay  Bridge  have  sustained  severe  traffic  losses. 

It  is  of  interest  to  record  that  truck  traffic  over  all  bay  crossings  (not  segregated  on 
the  chart)  persistently  increased  throughout  the  lean  years  of  the  depression,  notwith- 
standing the  setbacks  sustained  by  the  automobile;  and  that  the  Marin  ferry  lines,  due 
in  large  part  to  their  preeminence  as  carriers  of  week-end  and  holiday  travel,  and 
notwithstanding  a  toll  level  2  5  per  cent  higher  than  the  prevailing  level  in  effect  over 
the  main  bay,  were  the  last  to  succumb  to  economic  pressure  and  the  first  to  respond 
to  the  stimulus  of  better  times.  And  when  the  Golden  Gate  Bridge  opened  for  traffic, 
the  Marin  lines  having  reduced  their  tolls  on  automobiles  the  previous  March,  were 
handling  traffic  at  the  estimated  rate  of  2,280,000  vehicles  annually,  or  47.5  per  cent 
more  than  their  previous  all-time  high  of  1931. 


 TABLE.  2.  

GOLDEN  GATE  BRIDGE  AND  HIGHWAY  DISTRICT 
Schedule  of  Interest  and  Redemption,  July  1,  1S37  to  July  1,  1971 


Tear 

Series  "A" 

Series  "B" 

Series  "C" 

Total 

Total 

Total 

Total 

Tear 

Ending 

Principal 

Principal 

Interest  at 

Principal 

Interest  at 

Principal 

Interest 

Principal 

Interest  & 

Ending 

July  1 

Outstanding 

Outstanding 

4-3/45? 

Outstanding 

3-3/4$ 

Out stand  ing 

Payable 

Maturing 

Redemption 

July  1 

1938 

?    6  200  000 

?14  500  000 

983  250  00 

514  300  000 

$     536  250  00 

535  000  000 

$    1  519  500 

$ 

t  1  519  500 

1938 

1939 

6  200  000 

14  500  000 

983  250  00 

14  300  000 

536  250  00 

35  000  000 

1  519  500 

1  519  500 

1939 

1940 

6  200  000 

14  500  000 

983  250  00 

14  300  000 

536  250  00 

•35  000  000 

1  519  500 

1  519  500 

1940 

1941 

6  200  000 

14  500  000 

983  250  00 

14  300  300 

536  250  00 

35  000  000 

1  519  500 

1  519  500 

1941 

1942 

6  200  000 

14  500  000 

983  250  00 

14  300  000 

536  250  00 

35  000  000 

1  519  500 

200  000 

1  719  500 

1942 

1943 

6  140  000 

14  425  000 

976  837  50 

14  235  000 

533  812  50 

34  800  000 

1  510  650 

200  000 

1  710  650 

1943 

1944 

6  080  000 

14  350  000 

970  425  00 

14  170  000 

531  375  00 

34  600  000 

1  501  800 

200  000 

1  701  800 

1944 

1945 

6  020  000 

14  275  000 

964  012  50 

14  105  000 

528  937  50 

34  400  000 

1  492  950 

200  000 

1  692  950 

1945 

1946 

5  960  000 

14  200  000 

957  600  00 

14  040  000 

526  500  00 

34  200  000 

1  484  100 

200  000 

1  661,  100 

1946 

1947 

5  900  000 

14  125  000 

951  187  50 

13  975  000 

524  062  50 

34  000  000 

1  475  250 

400  000 

1  875  250 

1947 

194S 

5  790  000 

13  980  000 

939  075  00 

13  830  000 

B18  625  00 

33  600  000 

1  457  700 

400  000 

1  857  700 

1948 

1949 

5  730  000 

13  835  000 

929  337  50 

13  635  000 

511  312  50 

33  200  000 

1  440  650 

400  000 

1  940  650 

1949 

1950 

5  670  000 

13  690  000 

919  600  00 

13  440  000 

504  000  00 

32  800  000 

1  423  600 

400  000 

1  823  600 

1950 

1951 

5  610  000 

13  545  000 

909  862  50 

13  245  000 

496  687  50 

32  400  000 

1  406  550 

400  000 

1  806  550 

1951 

1952 

5  550  000 

13  400  000 

900  125  00 

13  050  000 

489  375  00 

32  000  000 

1  389  500 

800  000 

2  189  500 

1952 

1953 

5  400  000 

13  040  000 

875  900  00 

12  760  000 

478  500  00 

31  200  000 

1  354  400 

800  000 

2  154  400 

1953 

1954 

5  250  000 

12  680  000 

851  675  00 

12  470  000 

467  625  00 

30  400  000 

1  319  300 

800  000 

2  119  300 

1954 

1955 

5  100  000 

12  320  000 

827  450  00 

12  180  000 

456  750  00 

29  600  000 

1  284  200 

800  000 

2  084  200 

1955 

1956 

4  950  000 

11  960  000 

803  225  00 

11  890  000 

445  875  00 

28  800  000 

1  249  100 

8O0  000 

2  049  100 

1956 

1957 

4  800  000 

11  600  000 

779  000  00 

11  600  000 

435  000  00 

28  000  000 

1  214  000 

1  200  000 

2  414  000 

1937 

1958 

4  590  000 

11  080  000 

744  325  00 

11  130  000 

417  375  00 

26  800  000 

1  161  700 

1  200  000 

2  361  700 

1958 

1959 

4  380  000 

10  560  000 

709  650  00 

10  660  000 

399  750  00 

25  600  000 

1  109  400 

1  200  000 

2  309  400 

1959 

1960 

4  170  000 

10  040  000 

674  975  00 

10  190  000 

382  125  00 

24  400  000 

1  057  100 

1  200  000 

2  257  100 

1960 

1961 

3  960  000 

9  520  000 

640  300  00 

9  720  000 

364  500  00 

23  200  000 

1  004  800 

1  200  000 

2  204  800 

1961 

1962 

3  750  000 

9  000  000 

605  625  00 

9  250  000 

346  875  00 

22  000  000 

952  500 

1  600  000 

2  552  500 

1962 

1963 

3  480  000 

8  360  000 

562  400  00 

8  560  000 

321  000  00 

20  400  000 

883  400 

1  600  000 

2  483  400 

1963 

1964 

3  210  000 

7  720  000 

519  175  00 

7  870  000 

295  1  25  00 

18  800  000 

814  300 

1  600  000 

2  414  300 

1964 

1965 

2  940  000 

7  080  000 

475  950  00 

7  180  000 

269  250  00 

17  200  000 

745  200 

1  600  000 

2  345  200 

1965 

1966 

2  6  70  000 

6  440  000 

432  725  00 

6  490  000 

243  375  00 

15  600  000 

676  100 

1  600  000 

2  276  100 

1966 

1967 

2  400  000 

5  800  000 

389  500  00 

5  800  000 

217  500  00 

14  000  000 

607  000 

2  800  000 

3  407  000 

1967 

1968 

1  920  000 

4  640  000 

311  600  00 

4  640  000 

174  000  00 

11  200  000 

485  600 

2  800  000 

3  285  600 

1968 

1969 

1  440  000 

3  480  000 

233  700  00 

3  480  000 

130  500  00 

8  400  000 

364  200 

2  800  000 

3  164  200 

1969 

1970 

960  000 

2  320  000 

155  800  00 

2  320  000 

87  000  00 

5  600  000 

242  800 

2  800  000 

3  042  800 

1970 

1971 

480  000 

1  160  000 

77  900  00 

1  160  000 

43  500  00 

2  800  000 

121  400 

2  800  000 

2  921  400 

1971 

$25  005  187  50 

$13  821  562  50 

}38  826  760 

♦35  000  000 

)7i  act  750  1 

69 


THE     GOLDEN     GATE  BRIDGE 


To  the  student  of  trends,  the  persistence  of  bay-crossing  traffic,  its  instant  response 
to  favorable  influences,  will  come  as  no  surprise.  San  Francisco  is  a  traffic  reservoir  of 
considerable  potentiality.  Prior  to  the  opening  of  the  two  bay  bridges,  the  city's  north 
and  eastern  gateways  faced  water  barriers  crossed  by  out-moded  ferries  charging 
excessive  tolls.  Its  southern  gateway  on  the  other  hand  was  served  by  four  modern, 
high-speed  highways,  available  day  and  night  leading  down  the  beautiful  peninsula  of 
San  Mateo.  Result:  out  of  the  more  than  twenty-two  million  vehicles  which  were 
entering  or  leaving  the  city  each  year,  only  a  fifth  used  the  ferries,  and  of  this  fifth,  less 
than  a  third  part  crossed  between  San  Francisco  and  Marin. 

Bear  in  mind  that  motor  vehicle  registration  is  just  as  high  in  the  East  Bay  Cities  as 
it  is  in  San  Francisco,  and  that  the  recreational  advantages  of  Marin  County  and  the 
Redwood  Empire  are  no  less  varied  and  attractive  than  are  those  of  San  Mateo  and 
the  South.  Why,  then,  was  San  Mateo  travel  compared  with  that  through  the  north 
and  eastern  gateways  so  disproportionately  large?  The  answer  lies  in  the  inherent 
inadequacy  and  high  cost  of  a  ferry  service  contrasted  with  the  time-saving  and  freedom 
of  an  open  road. 

And  this,  too,  explains  the  past  response  by  the  automobilist  to  better  ferry  service 
and  lower  tolls  whenever  the  ferry  operators  have  vouchsafed  such  concessions  to  the 
growing  demands  of  their  patronage;  for  the  record  over  the  years  since  1929  clearly 
shows  that  the  ratio  of  ferry  travel  to  south  gateway  travel  has  invariably  increased 
following  each  improvement  in  ferry  service.  This  ratio  may  be  taken  as  a  sort  of 
indicator  of  the  potentiality  of  San  Francisco's  traffic  reservoir.  We  have  seen  that 
the  ratio  stood  at  twenty/ eighty  at  the  time  of  the  opening  of  the  bridges.  Since  their 
opening  it  has  increased  approximately  to  forty/ sixty.  The  bridges  drastically  reduced 
all  bay-crossing  toll  rates  (See  Chart)  and  cut  the  travel  time  enormously  between  San 
Francisco  and  the  north  and  east. 

If  we  measure  the  circuit  distance  from  Waldo  Point  southward  over  the  route  of 
the  Sausalito-Hyde  Street  ferry,  thence  by  way  of  the  Marina  Approach  and  back  over 
the  bridge  to  Waldo  Point  again,  the  middle  point  of  the  circuit  will  fall  at  Buchanan 
Street  in  San  Francisco.  Similarly,  the  middle  point  of  the  circuit  measured  by  way  of 
the  proposed  but  uncompleted  Funston  Avenue  Approach  instead  of  the  Marina 
Approach  will  fall  at  Steiner  Street  three  blocks  west.  This  narrow  strip  in  San  Francisco 
between  Buchanan  and  Steiner,  extending  southward  between  Dolores  and  Sanchez 
constitutes  the  median  zone  with  respect  to  travel  distance  between  San  Francisco  and 
Marin;  for  from  all  points  within  this  zone  the  distance  is  approximately  the  same 
whether  we  travel  by  way  of  the  ferry  or  over  the  bridge.  But  the  time  advantage  to  the 
automobilist  from  points  within  the  zone  is  27  minutes  in  favor  of  the  bridge.  Even 
a  horse-and-buggy-owning  citizen  residing  within  the  limits  of  this  median  strip— if 
there  be  such— could  give  his  Lincoln-owning  neighbor  who  preferred  the  ferry  a  five- 
minutes'  start,  and  Old  Dobbin  would  beat  the  Lincoln  by  two  minutes  to  Sausalito 
via  the  bridge. 


70 


GENERAL  HISTORY 


GENERAL  ASPECTS 


The  Golden  Gate  Bridge  is  fortunate  in  having  a  scenic  setting  which  is  world 
famous  and  which  provides  entry  to  the  structure  through  the  orderliness  of  a  residen- 
tial section  of  the  city  and  through  the  landscaped  areas  of  one  of  the  nation's  finest 
military  reservations.  The  approach  to  the  bridge  from  either  side  leaves  a  pleasing 
impression  upon  the  visitor,  which  is  heightened  by  the  magnificence  of  the  view  from 
the  bridge  proper. 

The  two  wide  sidewalks  and  the  open  type  of  handrailing  with  off -set  bays  at 
intervals,  fulfill  the  expectation  of  the  designer  in  providing  a  promenade  of  unusual 
and  appealing  character.  The  popularity  and  inspiring  character  of  these  footwalks  is 
evidenced  by  the  tremendous  number  of  pedestrians  who  daily,  and  particularly  on 
week-ends,  view  the  Golden  Gate  from  these  lofty  vantage  points. 

The  Golden  Gate  Bridge  was  the  first  bridge  to  be  built  under  a  district  plan.  This 
alone  made  it  possible  and  brought  about  the  present  bridge-minded  attitude  of  the 
people  of  San  Francisco  and  the  Bay  Area.  Bearing  in  mind  the  agitation  for  "free 
bridges"  it  should  be  remembered  that  there  are  no  free  bridges,  that  all  bridges  must 
be  paid  for  in  taxes  of  some  sort.  In  the  case  of  the  Golden  Gate  Bridge  a  toll  or  users' 
tax  was  the  only  method  by  which  the  age-old  isolation  of  San  Francisco  could  be  ended. 

The  toll  rate  fixed  by  the  Bridge  District  was  modest  and  fair,  and  although  lower 
than  that  upon  which  the  Chief  Engineer  based  his  conclusions  as  to  financing,  will 
nevertheless  make  the  bridge  a  self -liquidating  project  when  all  present  handicaps  are 
removed.  But  even  were  it  not  a  self -liqui- 
dating project,  the  bridge  would  be  worth 
all  its  cost  and  more  in  the  tremendous  im- 
petus it  has  given  to  the  physical  unifica- 
tion of  the  bay  area;  to  the  establishment 
of  the  beginnings  of  a  genuine  metropoli- 
tan area;  and  to  the  growth  and  prosperity 
of  San  Francisco  and  its  environs.  The 
Golden  Gate  Bridge,  aside  from  its  revenue 
producing  capacity  is  an  asset  of  incalcul- 
able value  to  San  Francisco,  California  and 
the  nation. 

Standing  at  the  portals  of  the  Redwood  mmm  HJ 
Empire,  and  constituting  as  it  does  the  last 
link  of  the  great  highway  from  Canada  to 
Mexico,  the  Golden  Gate  Bridge,  aside 
from  its  physical  attributes,  is  California's 
outstanding  contribution  to  progress  and 
international  amity. 


Bronze  name-plate  on 
San  Francisco  Tower 


JJ-jJJJJXJ-iJ: 

fill  t  PiJJJP 


m<»m**m*amm  *•****»».»».** 


I  I.I  HllitU 

JWUiMUlSill*- 

Uai:IJ.-WlK.| 

t.)!ti).i:[<m.^ 


Bronze  memorial  panel 
for  those  who  lost  their 
lives  in  the  building  of 
the  bridge 


Bronze 

dedication  panel 


5g& 

and  \1jD0f 

GOLDEN  ^jJKU 


M»1 


tNMMMBIr 

11— y—  IHUfflWMH 

•  r*  IWIMI 


imttummmwmumimwxiim 
RMunrrwin  Mi  mm  awooMCf  mm 
w-wnmiu  am  tw  ruu 


"""if  i 


th*  gouhnoati  smog* 

T!K  WNlltt  W.IO(M  «3\N  IN  fid  WO&U 

sri-tn*  rivfiv*  «ow  0*  mil  cxxjmn  wis 

MAX*  THIS  OtOKtflQN 
IN  &*0O<iNmON<# 

™*  MAWY  AND  -rm  frarrv 


lift 


W\4 


IN1TI 


Ml 


NEHAL  HISTORY 


PRINCIPAL  DIMENSIONS  AND  QUANTITIES 


Total  Length  of  Bridge  Including  Approach  Structure  8,98 1  ft. 

Length  of  Suspended  Structure  6,450  ft. 

Length  of  Main  Span  4,200  ft. 

Length  of  Each  Side  Span  1,125ft. 

Width  of  Bridge  90  ft. 

Width  of  Roadway  Between  Curbs  60  ft. 

Height  of  Towers  746  ft. 

Clearance  Above  Mean  Lower  Low  Water  220  ft. 

Weight  of  Main  Span  Per  Lineal  Foot  21,300  lbs. 

Live  Load  Capacity  Per  Lineal  Foot  4,000  lbs. 

Total  Weight  on  Marin  Pier  Foundation  264,000,000  lbs. 

Total  Weight  on  San  Francisco  Pier  Foundation  726,000,000  lbs. 

Weight  of  Cable  Anchorage  at  Each  End  of  Bridge  240,000,000  lbs. 

Deepest  Foundation  Below  Mean  Lower  Low  Water  1 10  ft. 

Maximum  Transverse  Deflection,  Center  Span  27.7  ft. 

Maximum  Downward  Deflection,  Center  Span  10.8  ft. 

Maximum  Upward  Deflection,  Center  Span  5.8  ft. 

TOWERS 

Height  Above  Water  746  ft. 

Weight  of  Two  Towers  88,800,000  lbs. 

Number  of  Cells  at  Base,  Per  Leg  (3'-6"x3'-6")  103 

Number  of  Cells  at  Top,  Per  Leg  21 

Base  Dimensions  (Each  Leg)  33  ft.  x  54  ft. 

Load  on  Tower  from  Cables  123,000,000  lbs. 

Transverse  Deflection  \2V2\n. 

Longitudinal  Deflection  j  Shoreward— 22  in.;  Channelward— 1 8  in. 

CABLES 

Diameter  of  Cables  Over  Wrapping  }63/g  in. 

Length  of  One  Cable  7,650  ft. 

Number  of  Wires  in  Each  Cable  27,572 

Number  of  Strands  in  Each  Cable  61 

Size  of  Wire  (No.  6)  Diameter  0.196  in. 

Total  Length  of  Wire  Used  80,000  miles 

Weight  of  Cables,  Suspenders  and  Accessories  24,5  00  tons 


73 


THE     GOLDEN     GATE  BRIDGE 


CONCRETE  QUANTITIES 


San  Francisco  Pier  and  Fender  130,000  cu.  yds. 

Marin  Pier   23,500  cu.  yds. 

Anchorages,  Pylons  and  Cable  Housings  182,000  cu.  yds. 

Approaches   28,500  cu.  yds. 

Paving   25,000  cu.  yds. 


Total   389,000  cu.  yds. 


STRUCTURAL  STEEL  QUANTITIES 


Main  Towers  44,400  tons 

Suspended  Structure  24,000  tons 

Anchorages   4,400  tons 

Approaches  10,200  tons 


Total   83,000  tons 


LIST  OF  CONTRACTORS 

Main  Piers  Pacific  Bridge  Company 

Anchorages  &  Approach  Piers  Barrett  &  Hilp 

Structural  Steel  of  Suspension  Spans  Bethlehem  Steel  Company 

Cables  of  Suspension  Spans  John  A.  Roebling's  Sons  Company 

Structural  Steel  of  San  Francisco  and  Marin  Approaches  

J.  H.  Pomeroy  &  Co.,  Inc.,  and  Raymond  Concrete  Pile  Company 

Presidio  Approach  Road  Eaton  &  Smith 

Pavement  for  Suspension  Spans  and  San  Francisco  and  Marin 

Approaches  Pacific  Bridge  Company  and  Barrett  &  Hilp 

Electrical  Work  Alta  Electric  &  Mechanical  Company,  Inc. 

Elevators  in  Towers  Otis  Elevator  Company 

Toll  Plaza  Barrett  &  Hilp 

Final  Paint  Coat  Pacific  Bridge  Painting  Co. 


74 


BOOK  TWO 


75 


PLANNING  AND  DESIGNING  A 
BRIDGE  WITH  4200-FOOT  SPAN. 
750-FOOT  TOWERS  AND  A  DEEP- 
WATER  PIER  IN  OCEAN  EXPOSURE 


the  left  is  seen  the  Presidio  Ap- 
oach  Road  which  connects  the 
idge  with  Marina  Boulevard.  Its 
aided  connection  with  the  Rich- 
Json  Avenue  approach  is  also  shown 
in  the  foreground 


THE     GOLDEN     GATE  BRIDGE 


The  development  of  plans  for  large  engineering  projects  begins  with  investigations 
and  studies  to  determine  which  one  of  several  possible  developments  would  prove 
most  desirable.  Based  upon  these  studies,  usually  extensive  in  scope,  the  major 
features  of  the  general  plan  are  established  and  the  project  assumes  definite  form.  In  the 
case  of  large  bridges  the  studies  normally  include  consideration  of  crossings  at  several 
different  feasible  sites  from  which  a  choice  can  be  made  only  after  a  careful  weighing 
of  the  merits  of  each.  The  procedure  in  the  Golden  Gate  Bridge  project  was  much 
simpler  because  physical  conditions  at  the  entrance  to  San  Francisco  Bay  are  such  that 
a  bridge  joining  the  two  peninsulas  should  unquestionably  be  located  at  the  Golden 
Gate,  extending  from  Fort  Point  on  the  South  to  Lime  Point  on  the  North.  Obviously, 
any  other  location  would  involve  a  much  longer  structure  and  would  introduce  addi- 
tional construction  difficulties  with  no  compensating  reduction  in  those  present  at  the 
site  favored. 

From  the  south  shoreline,  the  floor  of  the  strait  slopes  gently  toward  the  channel  for 
some  1300  feet  but  beyond  that  point  the  water  depth  increases  rapidly.  The  founda- 
tion for  the  South  Pier,  desired  to  be  not  less  than  20  feet  into  the  rock,  could  be  prepared 
under  air  pressure  at  a  depth  of  100  feet  below  the  surface  of  the  water.  Meeting  the 
above  prerequisites  placed  the  pier  1 100  feet  out  from  shore  where  the  maximum  water 
depth  at  the  channel  face  of  the  pier  is  about  80  feet. 

On  the  north  shore,  the  steep  slope  of  the  rock  bottom  prohibited  the  placing  of  piers 
any  appreciable  distance  off-shore.  The  length  of  the  main  span  was  thus  fixed  at  4200 
feet  since  water  depth  would  make  the  construction  cost  of  piers  between  these  points 
prohibitive.  The  natural  location  of  the  South  Shore-end  Pylon  at  the  Fort  Point  shore- 
line fixed  the  length  of  the  side  spans  at  1125  feet.  The  narrow  point  of  land  which 
served  so  well  to  reduce  the  length  of  the  structure  left  little  leeway  as  to  the  location  of 
the  bridge  in  the  east-west  direction,  but  fortunately  it  was  possible  to  keep  the  south 
cable-anchorage  on  land  along  the  west  shore  of  the  Point  where  a  setting  in  serpentine 
rock  could  be  prepared  for  it.  On  the  Marin  side  the  1125  foot  sidespan  had  to  skirt  the 
high  cliff  and  terminate  in  a  Pylon  just  in  front  of  the  north  cable-anchorage.  The 
topography  at  this  point  is  well  suited  for  the  gravity  type  anchorage  finally  adopted 
since  the  natural  slope  of  the  rock's  surface  follows  the  slope  which  the  cables  take  and 
it  was  only  necessary  to  cut  a  suitable  niche  in  the  side  of  the  hill  to  receive  the  mass  of 
anchorage  concrete. 

The  bridge  terminates  within  military  reservations  on  both  sides  of  the  Gate  and 
from  these  terminals,  roadways  had  to  be  constructed  through  the  reservations  joining 
the  bridge  with  existing  streets  and  highways.  The  location  of  these  roads  so  as  to 
minimize  interference  with  military  facilities  was  a  major  task.  On  the  San  Francisco 
side  a  route  was  worked  out  which  anticipated  a  future  branch  extending  southward 


78 


PLANNING 


across  the  Presidio  to  connect  with  Funston  Avenue.  On  the  Marin  side  the  extremely 
rugged  terrain  added  to  the  difficulty  of  locating  a  suitable  connecting  road.  The  align- 
ment finally  selected  passed  to  the  westward  of  Sausalito  joining  Route  101  at  Waldo 
Point,  a  distance  of  3  x/z  miles.  This  carries  traffic  around  Sausalito  which  is  desirable.  A 
lateral,  branching  off  to  the  eastward,  connects  with  Water  Street  in  Sausalito  and 
serves  the  needs  of  local  traffic.  The  road  to  Waldo  Point  became  the  obligation  of  the 
California  State  Highway  Commission  as  an  extension  of  State  Route  101.  The  proposed 
branch  road  through  the  Presidio  connecting  with  Funston  Avenue  became  the  obliga- 


tion of  the  City  of  San  Francisco  and  the  State  who,  at  the  time  this  report  is  written, 
are  working  out  its  final  alignment  with  the  War  Department. 

The  War  Department  by  its  permit  of  August  11,  1930  established  the  minimum 
clear  height  above  mean  higher  high  water,  of  210  feet  at  the  piers  and  220  feet  at  the 
center  of  the  main  span.  This  requirement  of  the  permit,  of  course,  determined  the 
height  of  the  bridge.  Low-steel  at  mid-span  under  normal  temperature  of  70°  F.  and 
dead  load  only  would  have  to  be  at  least  236  feet  above  mean  lower  low  water  in  order 


79 


THE      GOLDEN      GATE  BRIDGE 


to  give  220  feet  clearance  above  mean  higher  high  water  at  110°  F.  with  a  live  load  on 
the  main  span  averaging  4000  pounds  per  lineal  foot.  The  sixteen  feet  difference  allows 
for  10  feet  increased  sag  in  the  main  span  due  to  a  40°  F.  rise  in  temperature  plus  live 
load  and  6  feet  for  the  difference  between  mean  higher  high  water  and  mean  lower  low 
water.  (The  latter  is  used  as  datum  throughout  the  work).  With  low  steel  fixed  at 
elevation  236,  the  elevation  of  the  roadway  and  cable  at  mid-span  was  readily  established 
at  266.70  and  276  respectively.  Choosing  a  cable  sag  of  470  feet  then  fixed  the  height 
of  towers  at  746  feet  above  datum. 

As  a  matter  of  proper  proportioning  it  was  felt  that  the  width  of  the  bridge  having 
a  4200  foot  span  should  be  not  less  than  90  feet;  therefore  this  was  established  as  the 
width  center  to  center  of  cables  and  stiffening  trusses.  With  tower-shafts  centered 
under  the  cables  there  would  be  room  for  a  60-foot  roadway  to  pass  through  the  towers. 
It  was  evident  that  full  advantage  should  be  taken  of  the  possibility  of  having  at  once  a 
six-lane  road  at  a  relatively  small  added  cost.  This  would  be  more  than  offset  by  the 
relief  it  would  offer  during  periods  of  extraordinary  traffic  which  would  occur  even 
during  the  early  days  of  service;  however,  it  seemed  desirable  to  occupy  with  curbs, 
sidewalk  and  balustrade  the  fifteen  foot  strip  remaining  outside  the  roadway  on  each 
side  of  the  bridge.  This  provided  sidewalks  having  a  clear  width  of  10  feet.  Balconies 
around  the  outsides  of  the  towers  serve  there  as  continuations  of  the  sidewalks. 

The  lateral  system  is  placed  in  the  plane  of  the  top  chords  of  the  stiffening  trusses, 
and  at  each  floorbeam,  knee-braces  are  provided  to  give  lateral  support  to  the  bottom 
chords.  Panel  lengths  are  2  5  feet  and  at  every  second  panel  point  the  stiffening  trusses 
are  connected  with  the  cables  by  double  suspenders  ( four  parts)  of  wire  rope.  The  latter 
are  looped  over  cast  steel  cable-bands  on  the  cables  and  their  free  ends,  fitted  with  forged 
steel  sockets,  are  attached  to  the  webs  of  vertical  truss  members  where  suitable  stiffened 
seats  are  provided  to  receive  them.  Underneath  each  sidewalk  there  is  provided  a  hori- 
zontal truss  designed  to  support  the  curb  at  six-foot  intervals  against  side  thrusts  that 
may  be  delivered  to  it  by  traffic. 

BASIS  OF  DESIGN 

Since  stresses  in  the  principal  parts  of  the  suspension  spans  depend  upon  loads  applied 
over  great  lengths,  a  proper  proportioning  of  the  structure  would  be  obtained  only  if 
the  basis  of  design  made  due  allowance  for  this  fact.  A  single,  solid  line  of  vehicles  with 
high  percentage  of  trucks  will  average  in  weight  about  500  pounds  per  lineal  foot.  Such 
a  load  in  each  of  the  six  traffic  lanes,  making  a  roadway  load  of  3000  pounds  per  foot  of 
bridge,  obviously  is  a  congested  loading  not  apt  to  occur,  but  one  which  may  be  ap- 
proached should  traffic  for  any  reason  be  blocked  from  leaving  the  bridge.  In  such  event 
cars  will  not  stand  in  contact  end  to  end  but  will  be  separated  by  short  open  spaces  which 
will,  of  course,  materially  reduce  the  load  per  foot.  The  two  ten  foot  sidewalks  may 
receive  loads  of  100  pounds  per  square  foot  over  small  areas  but  an  average  of  50  pounds 


8o 


PLANNING 


per  square  foot  is  ample  when  applied  throughout  the  structure.  Accordingly  it  was 
recognized  that  1000  pounds  per  lineal  foot  would  suffice  for  the  sidewalks.  The  basic 
live  load  for  the  suspended  spans  was  therefore  taken  at  4000  pounds  per  lineal  foot  of 
bridge.  All  loads  used  for  design  of  the  Main  Structure  are  as  follows: 

LIVE  LOAD:  The  basic  live  load  for  towers,  cables  and  stiffening  trusses  is  4000 
pounds  per  lineal  foot  of  bridge  and  of  the  length  and  position  to  produce  maximum 
stress.  Live  load  stresses  for  combination  with  wind  stresses  from  a  wind  load  of  30 
pounds  per  square  foot  were  computed  for  the  above  live  loading  except  that  in  the  case 
of  the  center  span  stiffening  trusses  the  live  load  was  taken  at  2000  pounds  per  lineal 
foot  uniformly  distributed  over  the  entire  center  span  plus  2000  pounds  per  lineal  foot 
of  any  length  and  position  in  the  span  to  produce  maximum  stress. 

The  roadway  slab  and  stringers  were  designed  to  carry  24  ton  trucks  having  wheels 
spaced  six  feet  gauge  and  axles  nine  feet  center  to  center.  Two  thirds  of  the  load  was 
assumed  to  be  on  the  rear  axle.  Impact  was  assumed  to  equal  50%  of  the  live  load.  The 
sidewalk  slab  and  stringers  were  designed  for  a  live  load  of  100  pounds  per  square  foot. 

Floorbeams  were  designed  for  roadway  load  of  six  24-ton  trucks  abreast  with  a 
reduction  factor  of  75%  to  allow  for  the  large  number  of  loaded  lanes.  Impact  was 
assumed  to  equal  25  %  of  the  live  load.  In  addition  to  the  roadway  load  a  uniform  live 
load-on  the  sidewalks  amounting  to  100  pounds  per  square  foot  was  included. 

WIND  LOAD:  Wind  pressures  used  in  design  were  30  pounds  per  square  foot  on  the 
cables  and  suspended  structure  and  50  pounds  per  square  foot  on  the  towers.  The 
exposed  area  used  for  computing  transverse  wind  pressure  was  taken  as  twice  the 
vertical  projection  of  the  structure  as  seen  in  side  elevation.  The  exposed  area  used  for 
computing  longitudinal  wind  pressure  for  the  suspended  structure  was  taken  as  one 
half  the  vertical  projection  of  each  web  member  of  the  stiffening  trusses  and  of  each 
floor  beam  and  knee  brace. 

TEMPERATURE:  The  range  of  temperature  has  been  assumed  to  extend  from  30° 
to  110°  F.  Normal  temperature  has  been  taken  at  70°  F. 

DEAD  LOAD:  The  dead  load  of  the  center  span  if  uniformly  distributed  would  be 


as  follows:  Pound!  per 

lineal  foot 

Cables,  suspenders  and  accessories   6,670 

Stiffening  trusses   3,3  3  0 

Floor  system,  curbs  and  railings   _   3,830 

Bracing      600 

Concrete  paving    6,470 

Conduits  and  miscellaneous     _   400 


Total  as  built      21,300 


The  dead  load  in  the  sidespans  as  built  is  21,500  pounds  per  lineal  foot.  For  purpose 
of  design  an  assumed  uniform  dead  load  of  21,000  pounds  per  lineal  foot  was  used  for 
all  spans. 


8i 


THE      GOLDEN      GATE  BRIDGE 


UNIT  STRESSES:  Permissible  unit  stresses  used  in  the  design  are  as  follows: 


TOWERS 

Direct  stress  in  shafts  from  dead  load,  live  load  and  temperature  changes  Lbs.  per  sq.  in. 

Carbon  steel   .       14,000 

Silicon  steel       18,000 

Combined  direct  and  bending  stresses  in  shafts — 

Carbon  steel      18,000 

Silicon  steel  7/%  in.  plates   20,000 

15/16  in.  plates   23,000 

Maximum    24,000 

Bearing,  carbon  steel     24,000 

Bearing,  silicon  steel   30,000 

Bearing,  power  driven  rivets   24,000 

Bearing,  carbon  steel  pins,  heat  treated   27,000 

Shear,  carbon  steel   10,000 

Shear,  silicon  steel    13,000 

Shear,  power  driven  rivets    12,000 

Shear,  carbon  steel  pins,  heat  treated   13,5  00 

Tension,  power  driven  rivets     5,000 

SUSPENDED  STRUCTURE 

Stiffening  truss  chords,  silicon  steel 

Tension   32,000 

Compression    2  5,000 

Stiffening  truss  web  members,  carbon  steel 

Tension     21,000 

Compression    21,000 — 90-1 

Where  lrrlength  in  inches  of  the  unsupported  length  of  the  member,  and  r=the  radius  of  gyration  in  inches. 

Lateral  Bracing,  silicon  steel 

Tension,  including  participation   32,000 

Compression,  including  participation     25,000 

Rivets  for  stiffening  trusses  and  bracing 

Bearing,  power  driven   27,000 

Shear,  power  driven     15,000 

Floorbeams  and  Stringers 

Tension,  carbon  steel   16,000 

Tension,  silicon  steel     22,000 

Compression,  carbon  steel   16,000 — 150-£- 

Compression,  silicon  steel   22,000 — 200^- 

Where  1— the  length  in  inches  of  the  unsupported  flange,  and  b=the  flange  width  in  inches. 

Shear,  carbon  steel   10,000 

Shear,  silicon  steel   13,000 

Bearing,  power  driven  rivets....    24,000 

Shear,  power  driven  rivets     12,000 


82 


PLANNING 


All  Other  Structural  Members  Lbs.  per  sq.  in. 

Tension,  carbon  steel   16,000 

Tension,  silicon  steel   24,000 

Tension,  heat  treated  eyebars   27,000 

Compression,  carbon  steel   16,000 — 70 -j- 

(14,000  Max.) 

Compression,  silicon  steel   24,000 — 100  — 

(18,000  Max.) 

Bearing,  carbon  steel   24,000 

Bearing,  silicon  steel   30,000 

Bearing,  power  driven  rivets   24,000 

Bearing,  carbon  steel  pins,  heat  treated   27,000 

Shear,  carbon  steel   10,000 

Shear,  silicon  steel   13,000 

Shear,  power  driven  rivets   12,000 

Shear,  carbon  steel  pins   13,500 

Tension,  power  driven  rivets   5,000 

Bending  on  extreme  fibres  carbon  steel  pins,  heat  treated   27,000 

Steel  Castings 

Bending  on  extreme  fibres  .   15,000 

Bearing    24,000 

Direct  compression   20,000 

Cable  Wire,  tension   82,000 

Heat  Treated  Bolts,  tension   22,000 

Bronze,  bearing   3,000 

The  materials  used  were  required  to  have  yield  points  and  ultimate  strengths  not 
less  than  the  following,  in  pounds  per  square  inch: 

Minimum  Minimum 

Yield  Ultimate 

Point  Strength 

Rolled  carbon  steel   36,000  60,000 

Rolled  silicon  steel   45,000  80,000 

Rivet  Steel   30,000  52,000 

Heat-treated  pins  and  bolts     60,000  95,000 

Forged  steel  roller^.   40,000  80,000 

Cast  steel   35,000  65,000 

Heat-treated  eyebars   50,000  80,000 

Cable  wire    160,000  220,000 

The  Preliminary  Plans  which  formed  a  part  of  the  Chief  Engineer's  Report  of 
August  27,  1930  were  tentative  in  character  and  were  developed  only  to  the  extent 
required  to  insure  the  sufficiency  of  the  cost  estimate  and  to  present  one  feasible  layout 
which  would  meet  the  requirements  of  the  War  Department  as  well  as  the  needs  of  the 
District.  The  major  dimensions  of  the  main  structure  were  necessarily  determined,  as 
were  also,  definite  locations  for  the  main  piers.  Many  features  of  the  design  shown  were 


83 


PLANNING 


of  course  subject  to  whatever  modifications  a  thorough  and  comprehensive  engineer- 
ing study  would  develop.  For  example,  tunnel  type  anchorages  for  the  cables  were 
shown  on  the  Preliminary  Plans  but  subsequent  study  led  to  the  adoption  of  gravity 
type  anchorages. 


MAIN  PIERS 

Preliminary  foundation  studies  completed  in  1930  and  covered  by  the  Chief  Engi- 
neer's Report  of  August,  1930,  were  based  upon  core  borings  taken  on  each  shore  and 
at  the  proposed  pier  sites.  These  borings,  eighteen  in  all,  showed  that  the  North  Pier  at 
Lime  Point  would  be  founded  on  basalt  containing  inclusions,  large  and  small,  of  radio- 
larian  chert,  an  adjoining  formation  into  which  it  was  intruded.  The  rock  is  very  strong 
and  the  cores  showed  it  to  be  uniform  in  character  except  for  the  occasional  inclusions 
of  chert  which  do  not  in  any  way  detract  from  its  strength. 

Borings  at  the  site  of  the  South  Pier  showed  the  rock  to  be  of  serpentine  identical 
with  that  exposed  on  the  shore  at  Fort  Point  and  having  a  bearing  strength  not  less  than 
that  of  the  rock  upon  which  the  previously  described  bearing  test  was  made.  Subsequent 
to  the  1930  borings  fourteen  additional  core  borings  were  taken  at  this  pier  site.  In  most 
instances  the  borings  penetrated  the  rock  for  60  or  100  feet  and  in  one  case  for  160  feet 
to  elevation  —251.6.  The  borings  showed  conclusively  that  the  serpentine  rock  founda- 
tion for  the  South  Pier  was  uniform  in  character  for  a  minimum  depth  of  160  feet 
which  corresponds  to  an  elevation  of  2  5  0  feet  below  sea  level. 

The  design  of  the  Marin  Pier,  located  on  the  shoreline  as  it  was,  involved  no  note- 
worthy engineering  problem.  A  U-shaped  cofferdam  built  out  from  shore  about  the 
pier  site  would  permit  the  excavation  of  the  rock  and  preparation  of  the  pier  founda- 
tion at  elevation  —20  and  the  subsequent  construction  of  the  pier,  to  be  carried  on  as  a 
land  operation.  The  pier  base  was  made  80  feet  wide  and  160  feet  long,  the  length  being 
determined  as  the  minimum  which  would  accommodate  the  base  dimensions  of  the 
tower  and  the  width  as  the  minmum  required  for  stability.  The  maximum  pressure  on 
the  base  with  full  live  load  on  all  spans  is  132,000  tons  of  which  48,000  tons  is  due  to 
the  weight  of  the  pier  itself.  The  resulting  average  unit  pressure  is  10.7  tons  per  square 
foot.  With  full  live  load  on  the  center  span  and  the  far  side  span,  at  highest  temperature, 
and  with  transverse  wind,  the  maximum  unit  pressure  on  the  base  of  the  pier  is  17.1  tons 
per  square  foot  and  the  minimum  is  4.0  tons  per  square  foot. 

The  development  of  plans  for  the  San  Francisco  Pier  involved  consideration  of 
extraordinary  conditions  at  the  site.  Attention  has  already  been  called  to  the  severe 
exposure  to  ocean  storms  and  tidal  currents  and  bare-rock  bottom.  The  pier  must  be 
built  at  a  site  exposed  to  the  full  force  of  ocean  storms  where  the  bare-rock  bottom  in 
65  feet  of  water  is  swept  by  tidal  currents  of  6.5  knots  per  hour.  Early  in  the  study  of 
the  problem  the  Chief  Engineer  concluded  that  the  permanent  protective  fender  which 
would  be  required  around  the  pier  in  the  completed  structure  should  be  designed  so 


snder  construction  has  completely  85 
icircled  the  pier  site.  The  wall  has 
:en  carried  up  to  within  40  feet  of 
the  surface  of  the  water 


THE     GOLDEN      GATE  BRIDGE 


Cut-away  section 
showing  construction 
of  San  Francisco 
Pier  and  Tower 


that  it  could  be  built  prior  to  the  pier.  Construction  of  the  pier  might  then  proceed  in 
quiet  water  within  the  fender.  This  novel  procedure  had  been  developed  sufficiently 
during  the  preparation  of  the  Preliminary  Plans  so  that  those  plans  showed  a  complete 
fender  ring  comprising  two  steel  plate  walls  10  feet  apart  carried  on  structural  steel 
frame  work  somewhat  like  a  floating  drydock.  The  plan  contemplated  that  this  would 
be  built  at  a  shipyard,  launched  and  floated  to  the  site  where  it  would  be  lowered  on  to 
the  rock  bottom  and  the  10-foot  space  filled  with  concrete.  As  the  problem  was  further 
studied  in  the  preparation  of  the  Bidding  Plans  it  became  more  and  more  evident  that 
the  general  scheme  of  building  the  fender  first  and  using  it  to  facilitate  the  building  of 
the  pier,  was  sound.  There  were,  however,  many  objections  to  the  plan  as  then  developed. 
The  big  steel,  hull-like  structure  would  be  costly  to  build;  difficult  to  handle;  uncertain 
as  to  shape  of  bottom  to  fit  contours  of  the  rock  surface  upon  which  it  would  be  sunk; 
the  necessary  bracing  spanning  the  space  enclosed,  would  interfere  with  the  sinking  of 
a  pneumatic  caisson;  the  10  foot  wall  thickness  would  probably  need  to  be  increased. 
These  very  objections  pointed  out  the  way  to  the  solution.  The  fender  construction 
should  not  begin  with  the  placing  of  a  large  fabricated  unit  but  should  be  built  up  in 
place  starting  with  a  small  initial  unit  to  which  other  units  would  be  added  successively. 


PLANNING 


In  order  to  minimize  the  interference  of  tide  and  waves  the  initial  unit  would  start  with 
a  skeleton  steel  frame  about  3  0  feet  square  in  plan,  with  columns  at  each  of  the  four 
corners.  This  frame  would  be  securely  anchored  into  previously  drilled  anchorage  holes. 
Sheet  piling  or  forms  would  then  be  placed  around  the  lower  section  and  it  would  be 
filled  with  concrete.  With  the  added  stability  thus  obtained  the  next  section  above  could 
be  formed  and  it  filled  with  concrete.  After  the  initial  unit  was  completed  adjacent 
units  could  be  built  in  much  the  same  manner.  Thus  as  the  building  of  the  fender 
progressed  its  stability  would  be  ever  increasing  at  a  rate  equal  to  or  greater  than  the 
rate  of  increase  of  area  exposed  to  current  and  wave.  It  was  conceived  that  work  could 
thus  go  forward  in  both  directions  from  the  initial  unit  until  the  enclosure  was  com- 
pleted. When  completed  there  would  be  a  concrete  wall  30  feet  thick  all  around  the  pier 
site.  A  pneumatic  caisson  could  then  be  constructed  within  the  walls  of  the  fender  and 
sunk  to  the  desired  depth  into  the  rock. 

In  accordance  with  this  conception  the  San  Francisco  Pier  and  Fender  design  was 
developed  and  shown  on  the  Bidding  Plans.  In  order  to  give  the  greatest  possible  latitude 
to  the  contractor  the  plans  for  the  fender  showed  its  design  as  a  completed  unit  in  all 
essentials  with  no  limitations  as  to  methods  of  construction  except  that  under-water 
concrete  must  be  placed  by  the  tremie  method  and  in  sections  not  Over  40  feet  in  length. 
For  the  pier  these  plans  showed  a  base  90  feet  wide  and  185  feet  long  with  its  bottom 
surface  at  elevation  —100.  As  construction  progressed  modifications  were  made  in  the 
plans  to  meet  difficult  situations  as  they  arose.  These  are  described  in  Book  Three  but 
it  will  be  noted  here  that  as  finally  built  the  fender  and  pier  proper  are  combined  as  a 
single  structure  below  elevation  —35.  The  total  area  of  the  base  thus  formed  is  37,800 
square  feet.  Pressure  on  this  base  is  363,000  tons,  of  which  279,000  tons  is  in  the  weight 
of  the  pier  and  fender.  Live  load  on  the  bridge  contributes  only  1.9  per  cent  of  the  total 
pressure.  The  average  unit  pressure  is  9.6  tons  per  square  foot  and  under  the  most  severe 
combination  of  load,  temperature  and  wind  the  maximum  unit  pressure  is  10.8  tons 
per  square  foot. 

An  earthquake  acceleration  equal  to  10  per  cent  of  the  acceleration  of  gravity, 
which  is  greater  than  can  reasonably  be  anticipated,  would  increase  the  maximum  bear- 
ing pressure  on  the  Marin  Pier  by  not  more  than  four  tons  per  square  foot  and  that  on 
the  San  Francisco  Pier  by  not  more  than  three  tons  per  square  foot. 

ANCHORAGES 

Although  the  Preliminary  Plans  showed  tunnel  type  anchorages  on  both  sides  of 
the  Gate,  subsequent  study  showed  that  it  would  be  unwise  to  subject  the  rock  on  either 
side  to  the  character  of  stress  which  would  result  from  the  use  of  that  type  of  anchor- 
age. Accordingly  gravity  anchorages  were  developed  and  shown  on  the  Bidding  Plans. 
These  anchorages  comprise,  at  each  cable-end,  a  mass  of  concrete,  weighing  approxi- 
mately 60,000  tons  set  well  down  into  the  rock  foundation.  They  are  about  150  feet 


87 


THE      GOLDEN      GATE  BRIDGE 


long  and  have  embedded  within  them  heavy  eye-  bar  chains  which  terminate  in  a  series 
of  upright  girders  at  the  rear  ends  of  the  anchorages.  At  the  forward  end  of  each 
anchorage  the  eye-bar  chains  protrude  from  the  concrete  as  61  pairs  of  bars  arranged 
to  receive  the  61  strands  which  make  up  the  cable.  At  each  cable-end  the  total  cable 
pull  of  62,000,000  pounds  is  delivered  to  the  anchorage  through  these  61  strands.  On 
the  San  Francisco  side,  at  the  anchorage,  the  cable  curve  has  an  inclination  of  16°  31' 
with  the  horizontal.  On  the  Marin  side  the  corresponding  inclination  is  17°  40'.  These 
angles  therefore  give  the  direction  of  application  of  the  cable-pull.  The  60,000  ton 
weight  of  the  anchorage  mass  is  sufficient  to  turn  this  pull  into  a  resultant  thrust  down- 
ward against  the  rock  foundation  with  an  inclination  from  the  vertical  of  about  30°. 
The  unit  bearing  pressure  over  any  portion  of  any  anchorage  foundation  does  not  exceed 
10  tons  per  square  foot.  The  disposition  of  the  anchorage  mass  is  such  that  it  would  be 
stable  even  though  the  cable  pull  were  increased  to  twice  the  design  load. 

The  anchorages  are  enclosed  in  reinforced  concrete  housings,  one  for  the  San  Fran- 
cisco side  and  one  for  the  Marin  side.  The  roof  of  the  housing  on  the  Marin  side  serves 
also  as  the  floor  of  the  bridge. 

The  eye-bar  chains  which  transmit  the  loads  from  the  cables  to  the  anchorages  are 
arranged  in  three  tiers  of  122  bars  each.  Those  of  the  first  tier  are  pin-connected  to  the 
nine  upright  girders  at  the  rear  of  the  anchorage.  Each  girder  except  the  center  one 
receives  14  eye-bars,  in  three  groups,  4  at  each  end  and  6  at  the  center.  The  eye-bars  are 
heat  treated.  Those  of  the  first  tier  are  10  in.  by  2  in.  and  33  ft.  4  in.  long.  Those  of  the 
second  tier  are  1 0  in.  by  2  in.  and  66  ft.  7  in.  long.  Those  of  the  third  tier  (except  for  two 
pairs)  are  1 0  in.  by  2 1/%  in.  and  33  ft.  4  in.  long. 

Since  the  aim  was  to  deliver  the  cable-pull  to  the  girders  at  the  rear  end  of  the 
anchorage,  precautions  were  taken  to  minimize  the  tendency  of  the  embedded  eye-bars 
to  unload  through  bond  with  concrete  as  well  as  by  direct  bearing  of  eye-bar  heads 
against  the  concrete  at  connections  of  adjoining  bars.  Edges  of  such  eye-bar  heads  were 
wrapped  with  mastic  1  /4-in.  in  thickness.  While  it  was  felt  that  painting  the  eye-bars 
with  some  covering  which  would  prevent  bond  with  concrete  was  highly  desirable,  a 
suitable  material,  known  to  be  free  of  possible  injurious  effect  over  a  long  period  of  time, 
was  not  available.  The  bars  were  given  two  coats  of  heavy  red  lead  paint. 


88 


Erecting  th 
San  Francisc 
Tower 


THE      GOLDEN      GATE  BRIDGE 


MAIN  TOWERS 


From  a  paper  by  Clifford  E.  Paine  published  in 
Engineering  News-Record  October  8,  19)6. 

The  steel  towers  supporting  the  cables,  obviously  notable  because  of  their  size,  also 
command  attention  because  of  the  unusually  close  correlation  of  architectural  and 
structural  requirements  that  characterized  their  design.  Developed  as  rigid  frames  made 
up  of  two  shafts  and  cross  bracing  without  diagonals  in  the  panels  that  comprise  the 
upper  500  ft.  of  their  700-ft.  height,  the  towers  each  contain  22,200  tons  of  steel,  about 


a 

o 


Woolujorth  Building 

Neui  York 
<JYez\  tonnage  24,100 


4,200- ft  ./pan 
Golden  Gare 
2?,200  tons  per  tower 


JE 


W 


■*-  31-6— 
SECTION  A 


3.500- ft-  /pan 
George  Wa-rhington 
20,550  tons  per  tower. 

dt;  -A— 

'  J 1  L  ■  ■  J I L  1 

■  J  '  L  ■  '  J  |  L  ■  - 

■  1 1  r  .  .  1 1  r  . 
^£L  47- 6"-3^ 
djt  -■#:- 

1  J  I  L  1  ■  J  |  L  ' 

SECTION  B 


2,310-fr.  /pan 
Jim  Franci/co-Oakland 
5,500  tons  per  toiucr 


1,750  -  ft.  span 
Philadelphia-  Camden 
10,000  tons  per  rower 


-I7* 

SECTION  C 


EE::33 


—  22  — 
SECTION  D 


MAKE-UP   OF  TOWER  LEGS 


Comparison  of  Golden  Gate  Bridge  towers  with  the  towers  of  other  notable  suspension  bridges 

1 0  per  cent  more  than  was  used  in  the  George  Washington  Bridge  towers  at  New  York. 
The  main  section  at  the  base  of  each  shaft  or  leg  of  the  towers  has  an  area  of  12,391  sq. 
in.  as  compared  with  4500  sq.  in.  in  the  Philadelphia-Camden  bridge  towers  of  similar 
make-up  and  of  5000  sq.  in.  in  the  eight  columns  that  comprise  one  leg  of  the  George 
Washington  Bridge  towers.  The  Golden  Gate  tower  shafts  are  thus  by  far  the  largest 
structural  steel  members  ever  assembled. 

The  towers  are  690  ft.  4  in.  high  from  the  piers  to  the  base  of  the  saddle  castings,  and 
rise  746  ft.  above  the  water  to  the  intersection  of  the  main  and  the  side  span  cable 
tangents.  The  center  lines  of  the  tower  shafts  are  90  ft.  apart,  the  distance  selected  as 


90 


PLANNING 


the  desired  spacing  between  centers  of  cables.  This  spacing  and  the  necessary  width  of 
the  tower  shafts  is  just  sufficient  to  provide  clearance  for  the  60  ft.  roadway  through 
the  towers  at  deck  level. 

Supporting  a  4200-ft.  center  span  and  two  1125-ft.  side  spans  through  two 
3  6  Yg -in.  diameter  cables,  the  towers  are  designed  to  resist  forces  of  great  magnitude 
caused  by  dead  and  live  loads,  wind  and  earthquakes.  This  fact,  coupled  with  the  special 
indeterminate  nature  of  the  structures  made  the  design  problem  a  difficult  one.  Among 
the  contributions  to  structural  practice  that  came  out  of  the  design  is  a  novel  applica- 
tion of  the  Williot  diagram,  by  which  strain  equations  can  be  written  directly  without 
first  knowing  the  stresses  that  cause  the  strains. 

The  general  features  of  tower  design  were  developed  concurrently  with  the  archi- 
tectural treatment,  to  insure  a  satisfactory  architectural  effect  without  undue  cost  or 
structural  sacrifice.  The  architectural  treatment  is 
in  general  modernistic  and  involves  the  exclusion 
of  applied  decoration  and  unnecessary  elements. 
"Where  ornament  was  desirable,  either  to  enrich  cer- 
tain surfaces  or  to  diversify  surfaces  unlikely  to  be 
perfectly  executed  over  large  areas,  a  simple  vertical 
fluting  was  used  consisting  of  intersecting  plane 
facets  which  could  be  carried  out  readily  in  both 
concrete  and  steel.  Since  an  ornamental  elaboration 
of  minor  details  such  as  hand  rails,  lighting  units, 
etc.,  is  likely  to  be  inharmonious  in  a  structure  pre- 
dominantly engineering  and  industrial  in  character, 
these  features  were  handled  in  the  spirit  of  the  large 
design,  using  principally  structural  steel  shapes. 

Where  great  heights  are  involved,  the  common 
architectural  practice  of  enlarging  the  scale  of  details 
as  their  distance  from  the  ground  increases,  tends  to 
emphasize  the  detail  as  such  at  the  expense  of  the 
whole  mass.  The  opposite  principle  was  employed  on 
towers  of  the  Golden  Gate  Bridge;  the  scale  of  details 
on  the  towers  decreases  with  the  height. 

The  main  shafts  of  the  towers  are  built  up  of 
plates  and  angles  arranged  in  cellular  form  (Fig.  3 ) , 
using  sections  3J4  ft.  square.  At  the  base  in  the 
longitudinal  direction  of  the  bridge,  each  shaft  is  1 5 
cells  wide  and  in  the  transverse  direction,  9  cells  wide. 
The  base  slab  on  which  each  shaft  stands  is  a  33  x 
54-ft.  steel  plate  5  in.  thick,  made  up  of  19  separate     Fic-  ' — Cellular  makeup  of  tower  shafts  s«s  a 

...  .  -  new  record  for  steel  assemblages;  at  the  base  MCO 

pieces.  As  the  shafts  progress  from  the  base  toward  tower  shaft  contains  12.391  $q.  in. 


SHAFT  f 


Ir— iir— 1| 

1     II  1 
1— jIl^j 

ri 

L  a 

r— lir— i 

•     II  1 

r— ■» 
■ 

TOP 


TOWER  t 


r 

—  .a.  ji 


r  ir 


r  -i 


r  1 


r  -nr  m 
jIl  j 


JIMIJ 


1 


MID  HEIGHT 

•TOWER  <t 


r  1 


r  i 


r  ir  n 

L    jjt,  J 


r  1 


r  i 

L.  J 


r  1 


r  H 

L  . 


~/         BELOW  FLOOR 

L- — TOWER  <t 


r  n 


r  ilr  -% 

l.  J  L  J 


lir  tip  tJt  -\y-  -nr 

-   Ji.  JL  JL  gjh  jj 

r  ir  thr  iu-  ir  ir 

t.     JL  jllb  jU.  jjll-    JI  |L_ 

r  1  r  hit  iu-  TWr- ti  |r  . 

l    jJl  j|t  j|l  j.  J 


r    iir  ■HJF'tI 

L    jL     JL  J 


TOWER  <t 


26-3- 
BASE 


4-k 


91 


THE      GOLDEN      GATE  BRIDGE 


Footwalk  Ropes 


the  top,  the  section  is  decreased  by  successive  omissions  of  outside  cells,  until  at  the  top 
the  total  number  of  cells  is  only  21,  arranged  in  the  form  of  a  rectangle  composed  of  3 
cells  in  the  transverse  direction  and  7  cells  in  the  longitudinal  direction. 

Below  the  bridge  floor  level,  transverse  bracing  between  the  two  shafts  is  provided 
in  the  form  of  two  panels  of  diagonals.  Above  the  floor  level,  however,  transverse  bracing 
is  confined  to  four  portal  struts.  All  bracing  members  have  four  webs  which  are  spaced 
to  permit  gusset  connections  direct  to  web  plates  of  tower  shafts;  thus  the  width  of 
bracing  members  is  approximately  the  width  of  three  cells,  or  10  l/i-it.  The  portal  struts 
are  cased  in  steel  plate  enclosures,  detailed  to  carry  out  the  architectural  treatment. 

FACTORS  THAT  INFLUENCED  DESIGN:  The  principal  architectural  influence 
on  the  structural  make-up  of  the  towers  is  evident  in  the  portal  strut  bracing.  This  form 
of  bracing  was  found  to  be  efficient,  and  did  not  involve  any  structural  difficulties;  the 
spacing  of  the  portal  struts  was  arbitrarily  chosen  to  give  the  best  appearance. 

The  dead  load  of  the  towers  is  22,260,000  lb.  per  shaft.  The  dead  load  concentration 
from  the  cables  on  the  saddles  amounts  to  52,000,000  lb.  and  the  live  load  and  tempera- 
ture concentration  to  9,438,000  lb.  per  shaft.  The  towers,  cables  and  stiffening  trusses 
were  designed  for  a  live  load  of  4000  lb.  per  lineal  foot  of  any  length  and  position. 

Transverse  wind  forces  applied  to  the  tower  were  computed  on  the  basis  of  30  lb. 
per  sq.  ft.  on  twice  the  vertical  projection  of  trusses  and  cables  plus  50  lb.  per  sq.  ft.  on 
twice  the  vertical  projection  of  the  tower.  For  longitudinal  wind  forces  computations 
in  place     were  on  the  basis  of  50  lb.  per  sq.  ft.  on  the  vertical  projection  of  the  tower  plus  30  lb. 


PLANNING 


per  sq.  ft.  on  one-half  the  vertical  projection  of  each  web  member  of  stiffening  trusses 
and  of  each  floorbeam  and  knee  brace.  Temperature  stresses  were  figured  for  an  assumed 
rise  or  fall  in  temperature  of  40°  F. 

At  the  outset  it  was  decided  that  the  tower  shafts  were  to  be  of  cellular  construction 
formed  of  42 x% -in.  web  plates  and  8x8x% -in.  angles.  Silicon  steel  is  used  from  the 
base  up  to  the  roadway  and  in  the  top  two  panels;  the  two  center  panels  utilize  carbon 
steel.  Whenever  unit  stresses  in  silicon  steel  were  found  to  be  in  excess  of  20,000  lb.  per 
sq.  in.,  the  thickness  of  the  plates  was  increased  to  15/16  in.  This  occurs,  for  the  most 
part,  in  the  outer  cells  where  bending  stresses  are  of  more  consequence.  Also  it  was 
decided  at  the  outset  that  the  1/r  ratio  of  the  tower  shafts  should  not  exceed  60.  The 
establishment  of  these  proportions  pretty  well  determined  the  number  and  arrangement 
of  cells. 

The  carbon  steel  specifications  required  tensile  strength  of  60,000  to  70,000  lb.  per 
sq.  in.  and  a  minimum  yield  point  of  36,000  lb.  per  sq.  in.;  for  the  silicon  steel  a  tensile 
strength  of  80,000  to  9  5,000  lb.  per  sq.  in.  and  a  minimum  yield  point  of  45,000  lb.  per 
sq.  in.  were  specified. 

The  allowable  unit  stresses  adopted  were  as  follows: 

Direct  stress  in  shafts  from  dead  and  live  loads  and  temperature  changes: 

Carbon  steel  14,000  lb.  per  sq.  in. 

Silicon  steel   18,000  lb.  per  sq.  in. 

Combined  direct  and  bending  stresses  in  shafts: 

Carbon  steel   18,000  lb.  per  sq.  in. 

Silicon  steel  %-in.  plates— 20,000  lb.  per  sq.  in. 

"   15/16-in.  plates-23,000  lb.  per  sq.  in. 

 maximum— 24,000  lb.  per  sq.  ft. 

LONGITUDINAL  STRESSES:  The  towers  are  deflected  6  in.  toward  the  shore  in 
their  dead  load,  normal  temperature,  position.  From  changes  in  the  sags  of  the  side  span 
cables  and  from  changes  in  length  of  the  side  span  cables  due  to  temperature  and 
loading,  the  tower  tops  may  move  to  positions  18  in.  channelward  or  22  in.  shoreward 
from  vertical  lines  through  the  centers  of  the  tower  bases.  These  movements,  determined 
by  the  most  unfavorable  positions  of  the  full  live  load  of  4000  lb.  per  lineal  foot  of 
bridge  and  a  maximum  temperature  change  of  40°  F.  up  or  down  from  normal, 
are  smaller  than  on  some  shorter  spans  because  of  the  favorable  ratio  of  side  span  to 
main  span,  the  low  proportion  of  live  load  to  dead  load,  and  the  moderate  temperature 
change.  Despite  the  limitation  of  the  longitudinal  radius  of  gyration  to  1/60  of  the 
height  of  the  tower,  the  maximum  unit  bending  stress  from  a  deflection  of  22  in.  is  only 
6000  lb.  per  sq.  in.  Under  such  deflection  the  bending  moment  in  the  shaft  at  the  base 
is  slightly  over  3  billion  in. -lb. 

The  analysis  of  stresses  is  simple  and  conventional  but  the  important  effect  of  the 
eccentricity  of  the  direct  loads  in  reducing,  by  more  than  one-half,  the  amount  of 


93 


THE     GOLDEN     GATE  BRIDGE 


horizontal  force  from  the  cables  required  to  produce  the  desired  deflection  necessitated 
several  sets  of  computations  before  the  assumed  deflection  curve  agreed  with  the 
computed  curve. 

Several  cases  of  longitudinal  wind  combined  with  longitudinal  tower  deflection 
were  also  studied.  However,  except  for  a  short  distance  near  the  middle  of  the  tower, 
the  longitudinal  wind  forces  did  not  affect  the  design  of  the  tower. 

TRANSVERSE  WIND  STRESSES:  The  transverse  wind  load  per  shaft  amounts  to 
3,149,000  lb.,  of  which  30  per  cent  is  from  the  cable,  26  per  cent  from  the  laterals  of 
the  suspended  spans,  and  44  per  cent  is  the  wind  on  the  tower  itself.  Since  the  history  of 
the  design  of  the  towers  is  practically  the  history  of  the  determination  of  the  transverse 
wind  stresses,  some  description  of  the  various  methods  used  to  analyze  the  wind  stresses 
is  pertinent. 

Determination  of  the  superimposed  loads,  the  longitudinal  tower  deflections,  the 
maximum  slenderness  ratio,  the  unit  working  stresses  and  an  outline  of  the  structure 
completed  the  preparatory  steps.  The  direct  stresses  from  dead  load  and  live  load  were 
then  tabulated  and  a  guess  made  at  the  amount  of  unit  bending  stresses  from  longi- 
tudinal movements.  The  wind  stresses  were  computed  on  the  basis  of  a  point  of 
contraflexure  at  the  center  of  each  unbraced  panel.  This  information  was  sufficient  to 
permit  an  approximate  determination  of  the  various  sections  of  the  shafts,  struts  and 
other  web  members. 

Using  the  tentative  sections  selected,  the  longitudinal  bending  moments  were 
computed  and  the  sections  revised  to  correct  the  errors  made  in  guessing  the  amount  of 
the  unit  stresses  from  longitudinal  bending. 

To  facilitate  investigation  of  the  tentative  design  under  transverse  forces,  the  tower 
was  cut  at  the  floor,  and  the  upper  part  of  the  tower  figured  as  an  independent  structure, 
consisting  of  a  multiple-story  portal  frame.  The  solution  assumed  identical  deflections 
and  changes  in  slope  for  the  two  tower  shafts.  The  fully-braced  lower  section  of  the 
tower  was  considered  as  a  simple  truss.  This  analysis  gave  somewhat  different  results 
than  the  first  determination  of  wind  stresses,  and  the  sections  were  again  revised. 

The  methods  used  so  far  were  very  crude  in  their  determination  of  the  stresses.  For 
a  more  accurate  analysis  conventional  slope  deflection  methods  were  next  employed. 
It  was  assumed  that  the  direct  wind  stresses  previously  found  were  correct;  that  the 
struts  had  no  depth  (Fig.  4) ;  and  that  the  base  of  the  tower  was  free  to  rotate.  A 
conventional  Williot  diagram  was  drawn  and  the  usual  slope  deflection  equations  were 
set  up  and  solved  to  determine  the  moments  in  the  towers.  Direct  wind  stresses  resulting 
from  this  solution  were  substituted  for  those  assumed  and  a  new  solution  carried  out. 
After  several  attempts  the  calculated  direct  stresses  agreed  fairly  well  with  those 
assumed.  Sections  were  revised,  longitudinal  moments  recalculated,  sections  again 
revised  and  the  transverse  wind  stresses  again  computed.  This  completed  what  may  well 
be  termed  the  "Preliminary  Design"  which  was  shown  on  the  Bidding  Plans. 


94 


PLANNING 


REFINEMENT  OF  PRELIMINARY  DESIGN: 

At  this  stage  a  critical  study  of  the  tower  design 
was  made.  Some  objectionable  features  were  em- 
bodied in  the  preliminary  design.  Webs,  for  ex- 
ample, in  the  longitudinal  and  transverse  faces  of 
the  shafts  varied  in  thickness  from  7/%  to  3  in.  The 
splices  for  webs  of  3  in.  thickness  were  long  and 
the  riveting  burdensome.  The  gussets  for  the  web 
members  below  the  floor  were  very  long  and  the 
bending  stresses  in  the  gussets  became  large  when 
the  intersections  of  the  working  lines  of  the  hori- 
zontal and  diagonal  web  members  were  placed  on 
the  center  of  the  shaft.  Some  of  the  portal  struts 
had  short  heavy  members  and  the  secondary 
stresses  in  these  members  certainly  would  be  high. 

The  basic  assumptions  used  thus  far  in  the 
stress  determination  were  far  from  satisfactory. 
Obviously  an  assumption  of  fixity  for  the  bases  of 
the  shafts  was  more  nearly  correct  than  the  previ- 
ous assumption  of  a  free  base.  The  vertical  dimen- 
sion of  the  struts  would  have  a  considerable  effect 
and  must  be  considered.  Also  the  shear  carried  by 
the  shafts  would  have  to  be  considered,  to  make 
any  accurate  determination  of  the  direct  stresses 
in  the  diagonals  below  the  floor. 

A  survey  of  the  preliminary  design  indicated 
that  if  proper  consideration  were  given  to  the 
depth  of  the  struts  the  main  web  plates  in  the 
shafts  could  be  kept  at  7/g-in.  thickness,  although 
in  certain  places  they  would  have  to  be  made  of  silicon  steel,  and  in  a  few  instances 
reinforcing  plates  between  the  angles  would  have  to  be  added.  This  would  produce  a 
much  cleaner  design.  There  was  no  reason  why  the  intersection  of  the  working  lines  of 
the  web  members  needed  to  be  on  the  centerlines  of  the  shafts  if  account  were  taken  of 
the  resulting  stresses  from  the  eccentricity.  Also,  the  strut  sections  and  their  panel 
lengths  were  revised  in  an  attempt  to  keep  the  anticipated  combination  of  primary  and 
secondary  unit  stresses  within  permissible  limits. 

The  errors  of  assumptions  and  analysis  used  in  the  determination  of  the  stresses 
in  the  preliminary  design  were  next  to  be  eliminated.  A  correction  of  the  previous 
calculations  showed  that  the  assumption  of  fixed  bases  gave  moments  of  considerable 
magnitude  in  the  shafts  below  the  floor.  The  shears  accompanying  these  moments  were 
of  such  magnitude  as  to  affect  considerably  the  stresses  in  the  web  members.  Also  the 

95 


PRELIMINARY  FINAL 

Fig.  4 — Tower  diagrams  used  for 
preliminary  and  final  calculations. 


THE      GOLDEN      GATE  BRIDGE 


appreciable  moments  resulting  from  eccentric  connections  of  the  web  members  below 
the  floor  had  to  be  included  in  the  calculations.  Thus  the  part  of  the  structure  below  the 
floor  changed  from  a  very  simple  truss  to  a  statically  indeterminate  structure.  Study  of 
this  perplexing  problem  led  to  a  clear-cut  analysis. 

Unique  Use  of  Williot  Diagram:  In  all  previous  work  with  slope  deflections  the  primary 
stresses  had  been  obtained  first  without  regard  to  the  bending  stresses,  and  then  a  Williot 
diagram  was  drawn  using  the  strains  derived  from  the  primary  stresses  to  obtain  the 
deflection  angles  of  these  web  members.  It  was  now  realized  that  the  Williot  diagram 
was  the  missing  key  to  a  satisfactory,  direct  solution.  A  Williot  diagram  was  sketched 
without  knowing  the  stresses  but  from  which  it  would  be  possible  to  evaluate  the 
deflections  in  terms  of  the  various  unknown  stresses.  The  unknown  stresses  could  be 
readily  expressed  algebraically  in  terms  of  the  known  loads  and  the  unknowns  of  the 
slope  deflection  formulas.  This  procedure  took  care  of  the  major  difficulties.  Placing 
the  angle  of  rotation  of  the  shaft  at  the  base  equal  to  zero  provided  the  necessary  fixity 
of  the  base  of  the  shaft,  and  the  inclusion  of  the  eccentric  moment  from  the  diagonals 
below  the  floor  in  the  summation  of  moments  at  the  various  points  took  care  of  those 
stray  moments.  Thus  the  lower  part  of  the  structure  was  adequately  analyzed  although 
the  solution  had  to  await  the  necessary  equations  for  the  portal-braced,  upper  portion 


|Dcd+T, 
LEEWARD  "END   POST"  be 

Fig.  5 — Shaft  Deflection  Angle  between  chords  of  struts  was  expressed  in  terms  of  the  strut  deflection  from  a 
vertical  upward  load  equal  to  the  shear  Ti  and  the  relative  change  in  length  of  the  two  shafts,  2A91.  The 
sketches  portray  the  movements  of  the  members  involved. 

Taking  Account  of  Strut  Depth:  Transferring  attention  now  to  the  upper  portion  of 
the  tower,  a  possibility  of  treating  the  struts  in  a  manner  similar  to  that  developed  for 
the  part  below  the  floor  was  considered.  However,  it  was  soon  evident  that  the  number 
of  equations  would  become  unwieldy.  Also  it  was  noted  that  the  secondary  moments  in 


96 


PLANNING 


the  strut  members  were  far  too  small  to  affect  the  moments  in  the  shafts  more  than  a 
fraction  of  one  per  cent.  Apparently  the  effect  of  secondary  stresses  in  the  struts  could 
be  handled  adequately  without  combining  this  study  with  the  stresses  in  the  structure 
as  a  whole. 

This  decision  left  the  introduction  of  strut-depth  into  the  analysis  as  the  major 
remaining  problem  in  this  part  of  the  structure.  It  was  found  that  by  using  a  special 
equation  for  the  deflection  angle  of  the  shaft  between  the  chords  of  a  strut,  a  satisfactory 
analysis  could  be  made.  This  method,  described  below,  is  believed  to  be  unique. 

First,  assume  that  the  end  posts  of  a  strut— the  shafts  between  the  chords  of  the 
strut— are  restrained  so  that  their  axes  remain  vertical  while  the  leeward  end  of  the  strut 
is  permitted  to  deflect  upward  under  the  action  of  an  upward  force  equal  to  the  shear 
in  the  strut  (Fig.  5 ) .  If  now  the  strut,  including  its  end  posts,  is  rotated  until  the 
leeward  end  is  again  at  its  initial  elevation,  the  end  posts  will  have  rotated  through  an 
angle  equal  to  the  deflection  of  the  strut  divided  by  the  distance  between  the  posts.  The 
deflection  angle,  due  to  the  distortions  within  the  strut  as  above  determined,  is  increased 
by  the  change  due  to  the  shortening  of  the  leeward  post  and  the  lengthening  of  the 
windward  post.  This  added  deflection  angle  is  equal  to  the  difference  in  elevation  of  the 
two  ends  of  the  struts  divided  by  the  distance  between  the  posts. 

The  shear  in  the  struts  was  expressed  in  terms  of  the  known  loads  and  the  unknown 
deflection  angles  and  rotation  angles  of  the  shafts.  To  eliminate  the  necessity  for  repeated 
solutions  the  elongations  and  shortenings  of  the  shafts  from  direct  wind  loads  were  also 
expressed  in  terms  of  the  known  loads  and  unknown  angles. 

This  method  contains  an  approximation  in  the  assumption  that  the  end  post  of  the 
strut  does  not  change  length.  It  was  assumed,  in  computing  that  part  of  the  deflection 
angle  of  the  shaft  between  strut  chords  due  to  changes  in  length  of  the  shafts,  that  the 
shaft  changes  in  length  were  from  the  base  of  the  shaft  to  the  center  of  the  strut.  This 
assumption  produced  only  a  small  error  in  the  structure  as  a  whole.  Account  was  taken 
of  the  changes  in  length  of  the  shaft  between  chords  when  studying  the  secondary 
stresses  in  the  struts. 

The  analysis  of  the  towers  was  finally  concluded  with  a  set  of  33  simultaneous 
equations.  Since  most  of  these  equations  did  not  contain  more  than  half  a  dozen  un- 
knowns, the  solution  was  not  difficult.  Having  the  necessary  distortion  angles  it  was  possi- 
ble to  compute  in  the  customary  manner  all  of  the  required  stresses  from  transverse  wind. 

The  moments  in  the  shafts  were,  of  course,  appreciably  smaller  than  in  the  previous 
calculations.  This  resulted  in  the  anticipated  savings  in  material,  and,  together  with  a 
few  changes  to  silicon  steel  permitted  the  web  plates  to  be  of  uniform  thickness  except 
in  a  few  places  where  the  stresses  were  sufficiently  high  to  require  1 5/16-in.  plates  as  a 
precaution  against  web  buckling.  At  the  base  of  the  shafts  the  plates  were  thickened  to 
1 5/16-in.  to  resist  corrosion.  The  transverse  deflection  of  the  tower  by  this  analysis  was 
shown  to  be  12^2  in.  instead  of  16  in.  as  obtained  by  the  analysis  used  in  the  preliminary 
design. 


97 


THE     GOLDEN      GATE  BRIDGE 


The  33  Equations  in  Detail:  The  development  of  the  equations  is  outlined  to  illustrate 
the  procedure.  There  are  5  equations  of  the  "bent"  type  such  as: 

M„  +  M,q  =  —3S0W  +  D  (3&0R„) 

where  W  is  the  external  wind  shear  and  D  the  direct  dead  and  live  load  stress  in  the  shaft. 

There  are  1 3  equations  of  the  usual  kind  equating  the  summation  of  the  moments  at 
a  point  to  zero.  The  summation  of  the  moments  at  points  k,  o,  and  q,  (Fig.  4) ,  include 
the  moments  due  to  eccentric  web  connections. 

There  are  3  equations  for  the  strains  in  members  kt,  ot,  and  qt.  The  development  of 
these  equations  will  be  outlined  later. 

There  are  4  equations  for  the  deflection  angles  of  shaft  members  between  the  chords 
of  the  4  struts.  These  take  the  form 


Rhc  =  — 


+ 


0.000,000,724,034  7,-1 


L  540  1080 

in  which  An  is  the  change  in  length  of  the  shaft  from  the  center  of  strut  1  to  the  base 
of  the  tower;  the  factor  0.000,000,724,034  is  the  vertical  deflection,  from  a  unit  load, 
of  the  strut  as  a  beam  fixed  at  each  end;  and  Ti  is  the  vertical  shear  carried  by  the  strut. 
See  Fig.  5 . 

There  are  8  equations  for  the  deflection  angles  of  the  two  shaft  sections,  the  two 
effective  horizontal  struts  and  the  four  diagonals  in  the  fully  braced  section  below  the 
floor.  The  development  of  these  equations  is  the  most  interesting  feature  of  the  study. 


^(Aoq+Aqtt  |5^77  Ao'z  +  II360) 


8.7S 


13.2877 


Ao'z 


\\58q_l 


8.75 


132877 


Aq'r 


Fig.  6 — Williot  Diagram  for  bottom  panel  of  bracing,  typical  of  those  used  to 
obtain  the  deflection  angle  equations  for  the  eight  members  below  the  floor. 

First  Williot  diagrams  were  drawn  for  the  movement  with  respect  to  the  base  of  all 
points  below  the  floor.  One  of  these  diagrams  is  shown  in  Fig.  6.  From  these  Williot 
diagrams  the  deflection  angles  of  these  8  members  were  expressed  in  terms  of  the  strains 
in  the  members  and  the  angles  of  rotation  at  points  k,  o  and  q. 


98 


PLANNING 


A  typical  expression  for  the  diagonals  is 
Eq.  1  below.  Eq.  2  gives  a  typical  expression 
for  the  shaft  members,  while  a  typical  ex- 
pression for  the  horizontal  struts  is: 


952. 
23- 

61- 


-JhafI  <l 


1 

 Ac 

540 


63- 
64- 


99- 
126- 


4 


T 


I  rTaurer  ^ 


This  gives  the  set-up  of  the  33  equations 
finally  used.  However,  equations  for  the 
stresses  and  strains  in  the  members  had  to  be 
developed  and  introduced  in  these  equations 
before  they  could  be  solved. 

The  two  horizontal  struts  at  k  and  o  were 
assumed  to  have  no  direct  stress  from  wind. 
The  typical  expression  for  the  stress  in  a  diag- 
onal is  illustrated  by  Eq.  3 . 

The  expressions  for  the  stresses  in  the 
shaft  members  were  first  obtained  in  the  form 
of  the  stress  added  at  each  point.  A  typical 
expression  for  a  point  below  the  floor  is  shown 
in  Eq.  4. 

Eq.  5  shows  a  typical  expression  for  the 
load  added  to  the  shaft  at  a  portal  strut  above 
the  floor  or  the  reaction  from  the  strut  (say 
strut  2 ) . 

The  summation  of  these  expressions  for  LOADS  PER  SHAFT 
the  load  added  at  various  points  gave  the  total         IN  1000  LB 
wind  stress  in  the  shaft  members. 


1055- 


196" 


153 


209.6 


616.5 


404.4 


335.0 


MOMENTS  IN  SHAFT 
IN  1,000,000  IN.LB. 


13.2877 


R, 


8.75 


10 


10 

8.75 


L  13.2877 
10 


A«'«  +  A«(  +  1130, 


13.2877 
.  8.75 


X  427 


Fig.  7 — Shaft  Moments  from  transverse  wind. 


=  —  (0.7525757  A,'.  +  A,<  +  1130,)  427 


8.75  \  20 

+   ( A.'.  +  A,'0  +  A,<  + 

7/ 


10  10  10 

 A.,  +  X  1130,  +  X  1130, 

8.75  8.75 


13.2877       13.2877/  8.75  8.75 

=  [1.32877(A»'z  +  A.'O  +  2A««  +  A»,  +  1130-  +  1130,]  854 
8.75  Mu,  +  M„k        10    /M/„  4-  Mu.„ 


+976 


13.2877 


2778000-77413000/?* 


+  + 


Stress  added  at  0 


10 


13.2877 


■S.',  + 


976 

8.75   /M0\  +  Mwar 


13.2877  V  648.439 
10 


Reaction  from  strut  2  =  ■ 


13.2877V.  648.439 
—  Mir  —  M„  +  1104000  X  264 


Moo 

+  +  

540  13.2877 


So':  + 


8.75  /M,'.  +  M.: 


13.2877  V.  648.439 


64365000  X  264 A',,, 


540 


(1) 


(2) 


(3) 


(4) 


(5) 


99 


THE      GOLDEN      GATE  BRIDGE 


The  strains  were  computed  from  these  stresses  and  introduced  into  the  33  basic 
equations  after  the  moments  were  expressed  in  terms  of  the  slope  deflection  unknowns 
and  the  rotation  and  deflection  angles  of  the  various  members.  The  33  unknowns  con- 
sisted of  3  0  angles  and  the  strains  in  members  ko,  oq  and  qt  which  were  kept  as  part  of 
the  final  equations  since  they  entered  into  several  of  the  equations. 

This  method  of  analysis  was  so  satisfactory  that  the  time  spent  in  earlier  approxima- 
tions was  regretted.  In  any  future  design  of  this  type  this  method  of  analysis  would  be 
used  immediately  after  the  first  rough  approximation  by  assuming  a  point  of  contra- 
flexure  midway  between  struts.  The  transverse  wind  loads  and  moments  on  each  shaft 
as  designed  are  shown  in  Fig.  7. 

Other  Stresses:  Following  the  determination  of  the  sections  from  dead  and  live  loads, 
wind  loads  and  longitudinal  bending  stresses,  the  towers  were  investigated  for  other 
stresses.  In  addition  to  the  effect  of  the  changes  in  temperature  on  the  distribution  of 
the  suspended  loads  between  the  cables  and  the  stiffening  trusses  and  on  the  longitudinal 
position  of  the  tower  tops,  consideration  was  given  to  the  effect  of  a  difference  in  expan- 
sion or  contraction  between  the  pier  and  the  tower  corresponding  to  a  difference  of  40  ° 
F.  in  temperature.  The  method  of  analysis  was  similar  to  that  for  the  determination  of 

stresses  from  transverse  wind.  ,  . 

As  a  result  of  these  studies  it 

was  decided  that  strut  7  should 
be  made  ineffective  for  carrying 
stress.  The  final  stresses  in  the 
diagonals  in  the  lower  panel 
amounted  to  1,300,000  lb.  The 
maximum  bending  moment  in 
the  tower  shaft  was  found  to  be 
750,000,000  in.-lb.  at  the  base  of 
the  tower. 

The  effect  of  the  participa- 
tion of  the  bracing  below  the 
floor  in  carrying  the  direct  dead 
and  live  loads  on  the  shafts  was 
determined  in  a  manner  similar 
to  that  for  the  determination  of 
temperature  stresses,  and  the 
equations  were  nearly  identical. 
The  participation  stresses  in  the 
diagonals  averaged  about  3,500,- 
000  lb.  The  maximum  bending 
moment  in  the  tower  shaft 
amounted  to  72  5,000,000  in.-lb. 


PLANNING 


A  study  was  made  to  determine  the  effect  of  unequal  longitudinal  deflection 
resulting  from  live  load  on  one  half  the  roadway.  The  primary  purpose  of  this  study 
was  to  determine  the  effect  of  such  a  condition  on  the  lacing  of  the  chords  of  the  struts. 
The  maximum  difference  in  the  deflection  of  the  two  shafts  was  found  to  be  8  in.  Since 
there  was  uncertainty  as  to  the  torsional  resistance  of  the  cellular  shafts  stiffened  by 
horizontal  diaphragms,  it  was  decided  that  the  study  should  be  made  on  the  assumption 
that  the  shaft  was  as  effective  as  a  circular  section  of  equal  polar  moment  of  inertia. 
Subsequent  model  studies  indicated  that  the  cellular  shafts  were  about  half  as  effective 
as  was  thus  assumed. 

It  was  found  that  twelve  simultaneous  equations  could  be  written,  the  solution  of 
which  would  give  the  loads  on  the  shaft  from  the  web  members  and  the  cable  directly. 

The  longitudinal  tower  deflections  at  each  of  the  twelve  panel  points  for  an 
unknown  load  at  each  panel  point  were  determined.  From  these  deflections  were  written 
simple  expressions  in  terms  of  the  unknown  loads,  for  the  deflection  angles  of  the  web 
members  acting  as  horizontal  beams. 

The  angles  through  which  the  shafts  twisted  at  each  panel  point  were  found  for 
a  couple  applied  at  each  point.  The  couple  at  each  panel  point  was  equal  to  half  the 
tower  width  times  the  unknown  load  except  at  the  top  where  the  couple  was  equal  to 
the  restraint  of  the  cable  or  the  horizontal  component  of  the  cable  stress  times  the 
horizontal  length  of  the  effective  part  of  the  saddle  multiplied  by  the  unknown  angle 
of  twist.  By  equating  this  unknown  angle  to  its  value  computed  by  applying  the  couples 
to  the  shaft,  it  was  possible  to  eliminate  this  unknown  angle  of  twist  leaving  only  the 
twelve  loads  as  unknowns.  These  torsional  angles  are  also  the  angles  of  rotation  of  the 
horizontal  beams  comprising  the  web  members. 

From  the  expression  for  the  deflection  angles  and  rotation  angles  were  written  the 
expressions  for  the  shears  or  end  reactions  of  the  horizontal  beams  which  were  equated 
to  the  unknown  loads  giving  1 1  of  the  12  necessary  simultaneous  equations.  The  twelfth 
equation  was  found  by  equating  the  desired  deflection  at  the  top  of  the  shaft  less  the 
deflection  due  to  change  in  cable  stress  to  the  expression  previously  found  for  the  tower 
deflection  from  loads  at  the  panel  points.  A  solution  of  these  twelve  simultaneous  equa- 
tions gave  directly  the  shears  in  the  struts  due  to  the  differences  in  the  shaft  deflections. 

Although  the  process  of  determining  the  stresses  appears  somewhat  elaborate  for 
the  determination  of  stresses  that  were  realized  to  be  subject  to  a  considerable  but 
probably  fairly  constant  percentage  of  error,  the  investigation  seemed  justified  since 
it  revealed,  quite  accurately,  the  maximum  possible  stresses  and  the  distribution  of 
the  stresses. 

As  a  result  of  the  investigation  the  three  top  struts  were  laced  together  in  pairs 
reducing  the  resistance  to  torsion  greatly.  The  lacing  of  the  web  members  was  increased 
as  indicated  by  the  results  of  these  calculations. 

It  was  realized  that  the  secondary  stresses  in  the  members  of  the  portal  struts  above 
the  floor  (Nos.  1,  2,  3,  and  4)  were  relatively  high  and  that  the  resistance  of  the 

IOI 


S.F.  PUBLIC  LIBRARY 


THE      GOLDEN      GATE  BRIDGE 


individual  members  to  bending  would  contribute  appreciably  to  the  stiffness  of  the 
struts;  that  changes  in  length  of  the  shaft  between  the  chords  of  a  strut  would  produce 
stresses  in  the  strut  members;  and  that  there  were  other  small  stresses  due  to  the  change 
in  slope  of  the  deflected  shafts  in  the  distance  between  the  chords  of  the  struts. 

It  was  desirable  to  keep  the  same  rigidity  of  the  struts  that  had  been  assumed  when 
the  transverse  wind  stresses  were  computed  so  as  to  avoid  a  recalculation  of  these 
stresses.  At  the  same  time,  it  was  not  wanted  to  waste  material  or  permit  excessive  unit 
stresses  in  any  member.  Previous  approximate  calculations  had  indicated  the  probable 
amount  of  these  stresses,  and  the  sections  in  general  were  thought  to  be  satisfactory. 

Starting  with  the  assumed  sections,  the  secondary  stresses  were  computed  by 
moment  distribution  in  the  conventional  manner.  The  stresses  due  to  changes  in  length 
of  the  shaft  were  found  by  the  ratio  of  the  shaft  strains  to  the  deflection  of  the  strut 
from  equal  and  opposite  vertical  loads  applied  to  the  strut  at  the  tower  connections. 
The  effect  of  the  angular  changes  in  the  shaft  was  computed.  The  total  unit  stresses 
were  computed.  The  summation  of  unit  stresses  indicated  a  few  desirable  changes  in 
section  and  in  the  number  of  panels  in  the  struts,  and  the  calculations  were  revised 
to  take  care  of  these  changes. 

Following  this  part  of  the  work  which  resulted  in  sections  stressed  under  these 
assumptions  to  a  reasonably  uniform  unit  stress,  the  effect  of  the  shears  from  secondary 
moments  on  the  direct  stresses  was  determined.  This  study  indicated  that  the  struts 
were  slightly  stiff er  than  had  been  assumed  when  making  the  calculations  for  transverse 
wind  and  the  sections  were  slightly  decreased  to  keep  close  to  the  original  assumption 
for  the  rigidity  of  the  struts.  All  the  previous  strut  calculations  were  then  revised  for 
the  new  sections  and  the  procedure  continued  until  the  assumed  sections  gave  the 
proper  rigidity. 

The  effect  of  the  gusset  plates  on  the  stiffness  of  the  members  of  the  struts  was 
included  in  the  determination  of  the  moments  of  inertia  and  areas  of  the  various 
members.  Since  their  effect  was  appreciable,  it  was  realized  that  the  rigidity  of  the 
struts  as  a  whole  could  not  be  determined  exactly.  The  procedure  adopted  gave  accurate 
results  within  the  limitations  of  the  assumptions  made.  Previous  studies  indicated  that 
a  small  variation  in  the  stiffness  of  the  struts  had  little  influence  on  the  stresses  in  the 
structure  as  a  whole. 

Earthquake  Considerations:  While  the  determination  of  stresses  due  to  dead  load,  live 
load,  wind  and  temperature  presented  a  well  defined  problem  subject  to  entirely  satis- 
factory solution,  it  must  be  admitted  that  stresses  due  to  seismic  forces  could  not  be 
evaluated  with  equal  certainty.  The  towers,  homogeneous,  flexible  shafts  of  steel,  are 
anchored  to  massive  concrete  piers  which  are  founded  on  rock.  Although  no  one  can 
predict  just  how  a  flexible  shaft  of  this  character  will  respond  to  an  earthquake,  some 
conclusions  can  be  drawn  as  to  its  stability  under  these  forces.  In  the  judgment  of 
engineers  who  have  investigated  destructive  effects  of  earthquakes,  these  towers  may 

I02  Between  the  shafts  of  Pylon  Si  the 

Main  Towers  are  seen  in  readiness  to 
receive  the  cables.  Footwalk  ropes  are 
being  erected 


THE      GOLDEN      GATE  BRIDGE 


be  subjected  to  earthquake  vibrations  of  very  small  amplitude  (a  fraction  of  an  inch) 
and  accelerating  forces  amounting  possibly  to  5  per  cent  of  gravity.  In  the  completed 
structure  the  transverse  deflection  of  the  towers  under  the  design  wind  load  is  more 
than  ten  times  any  expected  movement  of  the  pier  tops,  and  the  stresses  from  transverse 
wind  will  be  more  than  double  the  stresses  due  to  transverse  earthquake  forces.  Due  to 
the  great  flexibility  of  the  towers  in  the  longitudinal  direction,  stresses  from  longitudinal 
earthquake  forces  (5  per  cent  gravity)  will  not  exceed  50  per  cent  of  the  longitudinal 
wind  stresses. 

The  influence  of  earthquake  forces  on  the  design  of  the  towers  was  a  determining 
factor  only  in  proportioning  the  anchorage  to  the  piers  so  as  to  provide  against  earth- 
quake while  the  towers  were  standing  alone  on  the  piers  without  the  stabilizing  effect 
of  the  cables  and  the  suspended  structure. 

SOME  DETAILS  OF  DESIGN:  The  gross  area  of  each  tower  shaft  at  the  base  is 
12,391  sq.  in.  and  at  the  top  3,659  sq.  in.  As  shown  in  Fig.  3,  despite  the  fact  that  the  four 
central  transverse  webs,  to  which  the  transverse  bracing  is  directly  connected,  are  made 
up  of  three  widths  of  plates,  they  are,  by  splicing  made  as  effective  as  single  plates  having 
a  width  equal  to  the  full  width  of  the  shaft.  Filler  plates  l/z  in.  in  thickness  are  used 
back  of  angles  in  locations  where  vertical  joints  occur  in  web  plates.  This  makes  it 
possible  for  tension  plates  to  be  inserted  where  it  is  desirable  to  carry  tension  across  the 
joints  without  an  offset  or  break  in  the  main  angles. 

The  tower  shafts  were  fabricated  in  units  which  comprise  "cell  groups"  of  from 
three  to  six  cells  each  in  cross-section  and  generally  about  40  ft.  long.  This  grouping 
gave  units  within  the  working  limits  of  major  bridge  shop  facilities  and  also  gave 
shipping  pieces  which  were  satisfactory  in  dimensions,  weight  and  rigidity  for  handling. 
The  largest  units  were  about  7x10^  ft.  in  section,  45  ft.  long  and  weighed  80  tons. 

At  horizontal  splices  the  principal  elements  of  the  sections  spliced,  with  few 
exceptions,  are  in  direct  bearing,  and  the  splices  are  designed  to  develop  50  per  cent 
of  the  compression  strength  in  the  sections  spliced.  An  exception  is  that  splices  on 
extreme  outer  faces,  both  transverse  and  longitudinal,  are  designed  to  develop  60  per 
cent  of  the  value  of  the  section  in  compression. 

Wherever  the  section  of  the  tower  shaft  was  reduced  by  omitting  outer  cells,  a 
gradual  transition  from  the  larger  to  the  smaller  section  was  accomplished  by  lessening 
or  tapering  off,  over  a  length  of  about  21  ft.,  the  cross-sectional  area  of  the  cells 
omitted.  This  was  considered  necessary  to  avoid  undesirable  "hard  spots"  at  these  points 
and  also  to  avoid  overstress  in  the  rivets  at  a  point  of  abrupt  change  of  cross-section. 

Inasmuch  as  the  transverse  bracing  connections  are  made  directly  to  the  four  central 
transverse  webs  of  the  tower  shafts,  it  is  necessary  to  provide  means  for  distributing  to 
the  other  transverse  webs  their  proportional  part  of  the  loads  transferred  at  these 
connections.  This  was  done  through  three  planes  of  horizontal  diaphragms  placed  in 
the  tower  shafts  opposite  each  bracing  connection.  The  diaphragms  are  tied  together 


104 


PLANNING 


by  means  of  tension  plates  so  that  collectively  they  form  an  effective  horizontal  girder 
which  is  designed  to  carry  to  each  transverse  web  of  the  shaft  its  share  of  the  transferred 
load. 

Manholes  provided  in  the  cell  webs,  to  give  access  to  all  cells,  are  about  70  ft.  apart 
and  are  staggered  for  safety.  Those  in  the  exterior  faces  of  the  shafts  are  completely 
covered,  while  those  in  the  interior  webs  are  left  open  and  are  fully  reinforced  to  make 
good  the  section  cut  away.  At  frequent  intervals,  openings  &l/z  in.  in  diameter  were 
made  in  the  web  plates  to  facilitate  delivery  of  field  rivets  to  the  interior  cells. 

Except  for  one  cell  in  the  center  of  each  shaft,  all  cells  are  provided  with  horizontal 
diaphragms  at  intervals  of  from  12  to  15  ft.  Each  of  these  diaphragms  is  made  up  of 
one  plate  and  four  angles  and  is  riveted  to  web  plates  on  all  four  sides.  The  diaphragm 
plates  were  milled  accurately  to  bear  against  the  web  plates  so  as  to  serve  as  spacers; 
the  angles  were  set  back  1/16  in.  A  1/16-in.  filler  was  used  between  the  angles  and  the 
web  plates  wherever  these  were  joined  by  field  rivets,  as  it  was  found  that  tight  field 
rivets  could  not  be  obtained  otherwise.  These  diaphragms  were  effective  in  obtaining 
accurate  spacing  of  the  webs  and  in  maintaining  the  rectangular  form  of  the  cells. 

Each  tower  is  effectively  anchored  to  the  pier  by  riveted  connections  with  pairs  of 
angles  imbedded  for  a  depth  of  52  ft.  in  the  pier  concrete.  Also  there  are  78  dowels 
6l/2  in.  in  diameter  imbedded  in  the  pier  concrete  and  projecting  through  the  5 -in.  base 
slabs,  to  form  a  positive  shear  connection  between  tower  base  and  pier.  The  angle 
anchorage  was  arranged  so  that  it  could  be  riveted  directly  to  the  longitudinal  web  plates 
of  the  tower  shafts  while  an  initial  tension  was  maintained  in  the  angles  by  means 
of  jacks. 

In  the  completed  structure  the  cable  saddles  are  permanently  centered  in  both 
longitudinal  and  transverse  directions  on  the  tops  of  the  tower  shafts.  During  erection, 
however,  they  were  set  slightly  to  shoreward  so  that,  as  load  was  applied  to  the  cables, 
the  saddles  could  be  moved  channelward  (with  respect  to  the  tower-tops)  and  thus 
brought  to  final  position  by  progressive  stages.  To  facilitate  this  movement  a  nest  of 
rollers  8  in.  in  diameter  was  placed  under  each  saddle.  As  originally  set  the  saddles  were 
shoreward,  on  the  San  Francisco  tower  5  ft.  6  in.,  and  on  the  Marin  tower  3  ft.  7  in. 
Temporary  structural  supports  for  the  saddles  in  their  "off  center"  position  were 
arranged  so  that  their  movement  could  be  controlled  by  means  of  hydraulic  jacks. 
When  the  cables  were  strung  and  loaded  and  the  saddles  took  their  final  position,  they 
were  bolted  permanently  to  the  towers  and  the  spaces  between  the  rollers  filled  with 
grout. 

Owing  to  the  magnitude  of  the  towers  and  the  unusual  character  of  the  design, 
it  was  thought  desirable  to  have  a  model  built  for  the  purpose  of  checking  its  general 
behavior  under  the  different  conditions  of  load  to  which  it  would  be  subjected.  The 
model  was  built  of  stainless  steel  on  a  scale  of  1  to  56.  Proportionate  loads  were  applied 
to  the  model  and  unit  stresses  were  measured  by  strain  gauges.  The  results  obtained  from 
the  model  checked  closely  with  the  analytical  results. 


105 


THE      GOLDEN      GATE  BRIDGE 


CABLES 


The  Bidding  Plans  and  Specifications  called  for  cables  each  composed  of  27,572, 
No.  6,  galvanized  bridge  wires,  grouped  in  61  strands  of  452  wires  each.  The  strands 
were  to  be  arranged  in  the  conventional  manner  which,  when  all  in  place  and  before 
compacting,  would  result  in  a  hexagonal  cross-section  with  sides  at  top  and  bottom. 
In  the  construction  of  other  large  bridge-cables,  difficulty  had  been  experienced  in 
compacting  the  cables  to  a  circular  cross-section.  Generally  the  horizontal  diameter  of 
the  completed  cable  was  longer  than  the  vertical  diameter  and  often  this  difference 
proved  sufficient  to  give  some  concern  in  the  fitting  of  cable  bands.  The  contractor 
made  a  thorough  analysis  of  the  effect  of  strand  arrangement  on  the  shape  of  the  cable 
and  concluded  that  an  arrangement  which  placed  a  vertex  of  the  hexagon  at  the 
bottom  instead  of  a  side,  would  require  a  minimum  vertical  displacement  of  wires 
during  compaction  and  result  in  a  final  cross-section  conforming  more  closely  to  the 
ideal  circular  section  desired. 

This  new  arrangement  of  the  strands  which  was  adopted,  carried  with  it  some 
variation  in  the  number  of  wires  per  strand  with  a  view  of  getting  them  in  the  most 
advantageous  position  for  compacting.  While  in  the  former  arrangement,  strands  were 

placed  in  the  saddles  in  horizon- 
tal layers,  in  the  new  arrange- 
ment they  were  placed  in  vertical 
tiers.  Fillers  placed  in  the  spaces 
between  strands  at  the  saddles 
were  designed  to  hold  the  strands 
accurately  in  position  at  these 
control  points. 

The  circular  cross-section 
into  which  the  cables  are  com- 
pacted obtains  up  to  within  1 5 
feet  of  the  saddles  at  which 
points  the  spiral  wrapping  stops 
and  retaining  collars  are  placed. 
Between  the  retaining  collars 
and  the  saddles  the  cross-section 
of  the  cables  undergoes  a  transi- 
tion from  a  circular  shape  at  the 
former  to  the  hexagonal  shape 
which  it  takes  throughout  the 
length  of  the  saddles.  This  length 
of  cable  in  each  instance  is  pro- 
tected by  means  of  a  removable, 

The  vertical  separators  in  a 
substantial  frame  kept  the 
strands  in  proper  relation  with 
one  another 


PLANNING 


weatherproof,  cylindrical  enclosure  supported  by  the  retaining  collar  at  one  end  and 
by  a  shroud  casting  bolted  to  the  end  face  of  the  saddle,  at  the  other  end.  The  end  con- 
nections of  this  cylindrical  enclosure  are  provided  with  packing  glands  and  are  so  de- 
tailed as  to  allow  for  all  changes  in  direction  of  the  cable  due  to  changes  in  temperature 
and  loads. 

The  cable  groove  throughout  the  length  of  the  saddle  has  a  weatherproof  steel  cover 
plate  except  through  the  central  portion  where  it  is  surmounted  by  a  small  penthouse 
made  of  steel  plates  and  angles.  Manholes  with  weatherproof  covers  in  the  north  and 
south  faces  of  this  penthouse,  provide  access  for  inspection  of  the  cable  within  the 
saddle.  Mounted  on  pedestals  above  the  house  of  the  two  easterly  saddles  are  the  rotating 
airway-beacons  required  by  the  Department  of  Commerce. 

At  the  shore  ends  of  the  sidespans,  the  cables  are  "tied  down"  to  the  Pylons 
by  means  of  a  group  of  short  suspenders— six  at  each  point.  These,  looping  over  an 
articulated  cable-band,  are  adjusted  to  apply  to  the  cable  a  load  of  1,300,000  pounds 
under  normal  temperature  and  with  no  live  load  on  the  bridge.  This  load  will  increase 
to  a  maximum  of  2,360,000  pounds  under  highest  temperature  and  with  full  live  load 
on  center  and  far  side  spans  only.  By  this  means,  the  cable  at  that  point  is  maintained 
at  the  proper  elevation.  Means  are  also  provided  at  these  "tie-down"  points  whereby 
the  cables  are  there  held  against  lateral  movement. 


The  articulated  cable 
band  at  one  of  the 
"tie-down"  points 


THE      GOLDEN      GATE  BRIDGE 


THE  SUSPENDED  STRUCTURE 


Roadway  grating  at 
expansion  joint 
between  tower  and 
center  span 


The  roadway  and  sidewalks  of  the  bridge  are  directly  carried  by  rolled-beam 
stringers  which  are  seated  on  the  top  flanges  of  floorbeams.  The  latter  occur  at  every 
panel  point  of  the  stiffening  trusses  which  spaces  them  25  feet  apart.  At  every  second 
panel  point,  the  stiffening  trusses  are  connected  with  the  cables  by  double  suspenders 
(4  parts)  of  wire  rope  2  1 1/16  in.  in  diameter.  The  floor  system  and  lateral  bracing  is 
in  the  plane  of  the  top  chords  of  the  stiffening  trusses.  The  stiffening  trusses  are  2  5  feet 
deep  and  their  bottom  chords,  as  explained  elsewhere,  are  supported  laterally  by  means 
of  kneebraces  at  each  floorbeam. 

The  floorbeams  are  8  ft.  6^2  in.  deep,  87  ft.  2^2  in.  long  and  weigh  23  tons  each. 
Webs  are  of  carbon  steel  l/z  in.  thick  and  are  spliced  at  two  points.  Flanges  are  of  silicon 
steel  and  each  consists  of  two  angles  8x8x%  in.  and  two  cover  plates.  The  top-flange 
cover  plates  are  both  20x^/2  in.  The  bottom-flange  cover  plates  are  one  20x^2  in.  and  one 
20x7/16  in.  The  floorbeams  were  cambered  %  in.  and  the  ends  were  milled  so  that  the 
end  connection  angles  lie  in  vertical  planes  under  full  dead  load. 

The  stiffening  truss  chords  are  of  silicon  steel.  The  diagonals  and  verticals  are  of 
carbon  steel.  Top  chord  sections  have  a  maximum  gross  cross-sectional  area  of  145.51 
sq.  in.  made  up  of  two  web  plates  36x1  ]/%  in.,  four  angles  8x8x%  in.  turned  in,  and  one 
top  cover  plate  30x%  in.  Bottom  chords  have  a  maximum  gross  cross-sectional  area  of 
132  sq.  in.  made  up  of  two  web  plates  36x1 5/16  in.,  four  angles  8x8x%  in.  turned  in, 
and  one  top  cover  plate  30x%.  In  the  side  span  stiffening  trusses,  the  heaviest  top  chord 
section  has  a  gross  cross-sectional  area  of  91.23  sq.  in.  made  up  of  two  web  plates 
24x1 3/ 1 6  in.,  two  top  angles  6x4x5/g  in.  turned  in,  two  bottom  angles  8x6x%  in.  turned 
in,  and  one  top  cover  plate  30x1 1/16  in.  The  heaviest  bottom  chord  section  has  a  gross 
cross -sectional  area  of  88.23  sq.  in.  made  up  the  same  as  the  heaviest  top  chord  section 
except  that  the  web  plates  are  reduced  to  %  in.  thickness. 

Riveted  connections  of  stiffening  truss  members  were  designed  to  develop  the  full 

strength  of  the  members  con- 
nected, at  the  allowable  unit 
stresses  used  for  their  design. 
Diaphragms  were  used  in  the 
chord  sections  at  every  panel 
point  and,  in  the  case  of  the 
center  span  chords,  at  mid- 
panel  points.  Diagonals  are 
box-sections  formed  of  two 
ship-channels  18  in.  x  51.9  lb. 
except  for  a  few  in  panels  near 
the  end  supports  which  are 


PLANNING 


Verticals  are  built  up  I-sections.  Those  at  suspender  connections  are  nominal 
members  and  consist  of  one  web  plate  32x%  m-  with  %  in.  reinforcing  plate,  and  four 
angles  7x3  V2X  l/z  in.  Those  at  points  intermediate  the  suspenders  have  to  carry  floorbeam 
loads  and  consist  of  one  web  plate  32x%  in.  and  four  angles  7x3  ^2x9/1 6  in. 

The  lateral  bracing  system  is  made  up  of  box-members  consisting  of  four  or  eight 
angles  laced  on  four  sides,  designed  to  act  either  as  tension  or  compression  members. 
Since  chord  increments  of  wind  stress  are  of  considerable  magnitude  care  was  taken  to 
apply  these  forces  as  near  as  possible  to  the  neutral  axes  of  the  chords  so  as  to  minimize 
local  bending. 

Calculation  of  stresses  in  stiffening  trusses  was  by  the  "deflection"  method  and  the 
effect  of  distortion  of  long  suspenders  was  included.  This  method  has  been  so  thoroughly 
described  in  connection  with  major  suspension  bridge  design  of  late  years  that  nothing 
need  be  added  here.  The  stiffening  trusses  are  exceedingly  flexible  and  it  will  be  of 
interest  to  note  that  unit  stresses  in  the  chords  due  to  live  load  and  temperature  depend 
principally  upon  the  chosen  depth  of  trusses  since  great  changes  in  the  cross-sectional 
area  of  chord  members  would  have  very  little  effect  on  the  cable  deformation.  The  wind 
truss  of  the  central  span  is  likewise  very  flexible.  Being  more  flexible  than  the  loaded 
cables,  there  is  a  considerable  transfer  of  wind  load  from  the  floor  to  the  cables  through 
the  suspenders.  At  any  suspender  point  the  ratio  of  the  transferred  load  to  the  suspender 
pull  is  equal  to  the  ratio  of  the  horizontal  projection  of  the  suspender  to  its  length.  Solu- 
tion of  simultaneous  equations  based  on  this  relationship,  gave  the  transferred  load  at 
each  point.  The  calculated  lateral  deflection  of  the  center  span  under  a  wind  pressure  of 
30  pounds  per  sq.  ft.  is  27.7  feet  and  this  is  not  much  affected  by  changes  in  the  cross- 
sectional  area  of  the  wind  chords.  The  maximum  downward  deflection  of  the  center 
span  is  10.8  feet  and  its  maximum  upward  deflection  is  5.8  feet. 

The  combined  unit  stress  in  stiffening  truss  chords  from  live  load,  temperature  and 
wind  was  therefore  determined  principally  by  the  depth  of  the  stiffening  trusses  and 
their  distance  apart.  The  use  of  silicon  steel  with  an  allowable  unit  stress  of  32,000 
pounds  per  sq.  in.  in  tension  and  25,000  pounds  per  sq.  in.  in  compression  for  the 
severe  combination  of  loads  used  in  the  design,  met  the  requirements.  The  maximum 
chord  stresses  occur  near  the  quarter  points  and  of  these  the  wind  stress  makes  up  about 
three-quarters  of  the  total. 

Wind  velocities  at  the  Golden  Gate  do  not  exceed  60  miles  per  hour  and  the  bridge 
is  not  likely  ever  to  experience  lateral  forces  as  high  as  those  assumed.  Unquestionably 
the  bridge  has  ample  stiffness  in  both  vertical  and  horizontal  directions.  It  is  believed 
that  the  depth  of  the  stiffening  trusses  could  have  been  reduced  considerably  without 
detriment. 

The  wind  truss  of  the  center  span  is  connected  with  the  tower  at  each  end  through 
a  hinged  and  sliding  joint  located  on  the  longitudinal  center  line  of  the  bridge.  This 
connection  is  designed  to  transfer  the  lateral  forces  to  the  tower  and  at  the  same  time 
permit  free  longitudinal  motion  as  well  as  angular  motion  in  both  horizontal  and 


109 


vertical  planes.  Stops  are  provided  in  this  connection  which  limit  the  longitudinal 
movement  towerward  to  1 8  inches,  and  channelward  to  2 1  inches,  thus  allowing  a  total 
range  of  movement  of  39  inches.  The  calculated  movements,  exclusive  of  displacements 
due  to  longitudinal  wind,  is  12.5  inches  and  16.5  inches  respectively.  At  the  curbs  there 
is  additional  longitudinal  motion  due  to  the  angular  deflection  which  increases  the 
movements  there  to  a  total  of  26.5  inches  towerward  and  30  inches  channelward.  The 
maximum  range  of  movement  at  the  curb  lines  is  therefore  56.5  inches  and  the  grating 
joint  in  the  roadway  is  accordingly  designed  for  a  closing  of  27  inches  from  normal  or 
an  opening  of  3  0  inches  from  normal. 

The  25  ft.  rocker  links  which  support  the  center  span  stiffening  trusses  at  the 
towers,  swing  through  a  considerable  angle  because  of  the  change  in  length  of  the 
suspended  structure.  The  upper  link  pin,  as  the  link  moves  from  its  normal  vertical 
position  to  one  extreme  or  the  other,  describes  the  arc  of  a  circle  and  causes  the  end  of 
the  suspended  structure  to  drop  appreciably.  To  accommodate  this  vertical  movement 
the  stringers  of  the  end  panel  have  one  end  hinged  to  those  of  the  second  panel  and  the 
other  supported  directly  on  the  tower  structure. 

The  wind  truss  of  each  side  span  is  connected  with  the  tower  so  as  to  permit  only 
angular  motion  in  horizontal  and  vertical  planes.  All  longitudinal  forces  applied  to 
the  side  span  are  delivered  through  these  connections  directly  to  the  tower.  The  floor 
joints  therefore  are  designed  only  to  accommodate  the  longitudinal  motion  which 
results  from  the  angular  deflection  of  the  side  spans. 

In  the  development  of  the  stiffening  truss  plans  it  was  necessary  to  consider  the 
conditions  which  would  obtain  during  various  stages  of  erection  since  the  geometric 


no 


PLANNING 


figure  of  the  truss  would  be  greatly  distorted  and  to  accommodate  this  there  would  be 
considerable  relative  displacement  of  members  at  field  connections.  Studies  were  made 
to  insure  that  a  sufficient  number  of  pins  and  bolts  could  be  placed  in  the  field 
connections,  under  such  conditions,  to  take  care  of  the  erection  and  wind  loads.  Also 
special  study  was  given  to  the  closing  of  the  stiffening  trusses  at  the  center  of  the  main 
span  where,  at  the  time  of  closing,  the  cable  would  be  1 3  l/z  feet  above  its  normal  dead 
load  position.  This  meant  that  the  stiffening  trusses  would  have  to  be  connected  up 
while  under  a  deflection  of  1 3  ^  feet  upward.  Because  of  this  deflection,  with  the 
closing  top  chord  member  pinned  in  place,  the  opening  left  for  the  closing  bottom 
chord  would  be  about  3  inches  less  than  the  normal  panel  length.  Accordingly  the 
milled  length  of  this  member  was  made  3%  inches  short  so  that  it  could  be  entered, 
after  which,  with  the  aid  of  a  3  50  ton  jack,  the  panel  length  would  be  increased  to 
normal  and  the  connection  made.  This  would  give  to  the  stiffening  truss  throughout 
its  length,  the  configuration  which  it  should  have.  It  will  be  noted  that,  except  for 
the  closing  bottom  chord  mentioned,  all  chord  members  were  milled  to  bear  and  the 
only  open  joint  is  in  the  closing  panel  at  the  center  of  the  main  span. 

The  center  span  rocker  links  are  subject  to  considerable  torsional  deflection  resulting 
from  angular  deflection  of  the  suspended  structure  under  transverse  wind  load.  In 
order  to  avoid  excessive  unit  stresses  from  this  torsion,  each  link  was  designed  as  a  pair 
of  built  up  I-sections  joined  together  by  diaphragms  at  top  and  bottom  only. 

The  roadway  slab,  carried  on  stringers  spaced  4  ft.  9  in.  apart,  is  seven  inches  deep. 
It  is  reinforced  with  fabricated  reinforcing  trusses  having  an  overall  depth  of  4%  in. 
and  spaced  six  inches  apart.  Top  and  bottom  chords  1 1/16  in.  diameter  are  arc-welded 
to  webs  7/1 6  in.  diameter  in  the  form  of 
a  Warren  truss.  The  bottom  of  the  truss 
was  spaced  1  in.  above  the  top  of  the 
stringer  by  means  of  short,  steel  lugs 
which  were  arc-welded  to  both  the 
stringer  and  the  truss.  One  inch  cover  of 
concrete  was  provided  for  the  bottom 
chords  which  allowed  1 3/&  in.  cover  for 
the  top  chords.  Longitudinal  rods  %  in. 
diameter  were  placed  in  the  bottom  of 
the  slab,  four  in  each  panel  between 
stringers.  Longitudinal  rods  l/z  in.  di- 
ameter were  placed  in  the  top  of  the  slab, 
one  over  each  stringer  and  four  in  be- 
tween. Concrete  was  specified  to  have  a 
strength  of  4000  lbs.  per  sq.  in.  in  28 
days. 

No  light-weight  concrete  was  used 


The  handrailing  at  the  ends  of  the  suspended  spans  is  joined  with  the  handrailing  around  the 
tower  by  means  of  a  telescoping,  hinged  section  of  railing  which  can  accommodate  itself  to 
the  5  l/z  ft.  range  of  movement  of  span  with  respect  to  tower.  The  walkway  around  the  tower 
is  one  step  above  the  walkway  on  the  span  so  that  the  latter  is  free  to  move  underneath 

the  former 


1 
1 

i 

y 

PLANNING 


except  for  the  west  sidewalk  where  encasement  of  conduits  increased  the  volume  of 
concrete  and  in  order  to  keep  the  weight  per  foot  the  same  as  that  on  the  east  side,  a 
concrete  weighing  approximately  100  lb.  per  cu.  ft.  was  specified. 

The  roadway  and  sidewalk  pavement  is  made  in  units  fifty  feet  long  with  a  %  in. 
transverse  opening  between  units.  These  openings  are  faced  with  steel  plates  which 
support  an  inverted  U-shaped,  copper  seal  and  a  shallow  pre-molded  bituminous  filler 
at  the  top  of  the  slab.  These  joints  prevent  the  pavement  from  participating  in  the 
strains  which  the  top  chords  of  the  stiffening  trusses  must  undergo.  For  construction 
purposes  two  longitudinal  construction  joints  were  provided  in  the  roadway  slab 
which  divided  it  into  three  strips  each  approximately  20  ft.  wide. 


APPROACHES 

The  Marin  approach  proper  comprises  a  series  of  five  17  5 -foot  deck  truss  spans 
supported  on  high,  steel  towers.  This  structure,  having  an  overall  length  of  1100  feet, 
carries  the  roadway  from  the  Marin  Anchorage  to  the  beginning  of  the  state  highway 
approach  road  which  links  the  bridge  with  Route  101  at  Waldo  Point.  With  a  curve 
of  102  5  feet  radius,  it  swings  over  a  deep  valley  requiring  towers  of  varying  height 
up  to  160  feet.  Because  of  their  height  the  towers  were  kept  rectangular  in  plan  and 
the  curvature  in  the  structure  was  effected  by  skewing  the  ends  of  the  spans.  This 
avoided  a  large  number  of  bent  plates  for  bracing  connection  of  towers. 

On  the  San  Francisco  side,  that  portion  of  the  structure  which  extends  from  the 
Shore-end  Pylon  at  Fort  Point  southward  over  the  fort  and  the  San  Francisco  Anchorage 
to  an  abutment  about  170  feet  north  of  the  Toll  Plaza  has  been  termed  the  "San 
Francisco  Approach"  and  has  an  overall  length  of  1072  feet.  The  major  structure  of 
the  approach  is  a  two-hinged  arch  span  over  the  fort  having  a  length  of  319  ft.  7  in. 
center  to  center  of  bearings.  The  arch  has  four  ribs.  The  two  inner  ribs  are  spaced 
42  ft.  6  in.  apart  and  the  two  outer  ribs  are  spaced  30  ft.  outside  the  inner  ribs.  The  arch 
rise  is  1 1 3  feet  and,  at  the  north  end,  the  roadway  is  1 8  5  feet  above  the  springing  line. 
The  outer  ribs  being  spaced  102  ft.  6  in.  apart  puts  them  6  ft.  3  in.  outside  the  cable 
backstays. 

At  the  south  end  of  the  arch  span  a  concrete  pylon  marks  the  north  end  of  the 
anchorage  housing  and  rises  above  the  roadway  with  an  architectural  treatment  similar 
to  that  of  the  Shore-end  Pylon.  Southward  of  this  pylon  are  two  12  5-foot  deck  truss 
spans  supported  on  two  steel  towers  which  rise  from  the  anchorage  housing.  From  the 
southernmost  tower  on  the  anchorage,  to  the  abutment,  the  structure  comprises  first 
a  175 -foot  deck  span  and  then  three  71 -foot  plate  girder  spans. 

The  deck  of  the  San  Francisco  Approach  is  similar  to  that  of  the  suspended  structure 
employing  steel  curbs  and  steel  handrailings.  In  the  case  of  the  Marin  Approach 
however,  the  concrete  curbs  and  balustrades  necessary  over  the  Marin  Anchorage,  are 
continued  for  the  full  length  of  that  approach. 


The  main  span  stiffening  trusses  and  floor  1 1 

were  extended  outward  in  both  directions 
from  each  tower.  On  November  18,  1936, 
the  two  main-span  travelers  met  at  mid- 
span  and  the  stiffening  trusses  were  joined 
together.  At  this  time  the  main  span  was 
deflected  upward  1  3  Yz  feet  above  normal 


THE      GOLDEN      GATE  BRIDGE 


The  Presidio  Approach  Road  which  joins  the  Toll  Plaza  with  Marina  Boulevard 
at  the  eastern  or  Lyon  Street  boundary  of  the  Presidio  has  two  structures  which  for 
convenience  have  been  named  the  High  Viaduct,  and  the  Low  Viaduct.  The  former  has 
an  overall  length  of  1  5 1 8  ft.  9  in.  and  comprises  eight  13  5  -foot  deck  truss  spans  flanked 
on  each  end  by  four  beam  spans.  The  Low  Viaduct  has  an  overall  length  of  3308  ft. 
and  consists  of  a  reinforced  concrete  viaduct  having  span  lengths  of  approximately 
30  feet.  Each  bent  comprises  two  columns  with  a  cross  girder  and  one  or  more  horizontal 
struts  depending  upon  its  height.  Bents  are  joined  together  in  groups  of  two,  to  form 
towers.  The  roadway  slab  and  stringers  for  each  tower  are  poured  monolithic  with  the 
upper  column  sections  and  cross  girders,  and  one  or  more  longitudinal  struts  are 
provided  depending  upon  the  height  of  the  bents.  The  spans  between  towers  are  fixed 
at  one  end,  and  at  the  other  end  are  provided  with  steel  bearing  plates  designed  to  slide 
on  bronze  bearing  plates  set  on  the  supporting  brackets. 

Both  viaduct  structures  carry  a  60  ft.  roadway  and  one  3  l/z  ft.  sidewalk.  Curbs 
and  balustrades  are  of  concrete  similar  to  those  on  the  Marin  Approach. 

The  approach  from  Richardson  Avenue  passing  southward  of  the  Palace  of  Fine 
Arts  joins  the  Low  Viaduct  by  means  of  two  ramps.  This  approach  provides  three  lanes 
for  off -going  traffic  and  three  lanes  for  on-coming  traffic.  The  latter  pass  under  the  Low 
Viaduct  and  thence  up  a  ramp  to  join  traffic  bound  toward  the  bridge  from  Marina 
Boulevard. 

Present  construction  anticipated  the  requirements  of  a  future  Funston  Avenue  link 
and  made  provision  for  a  braided  connection  whereby  on-coming  traffic  lanes  from 
Funston  Avenue  would  pass  underneath  the  Presidio  Approach  Road  before  joining  it 
just  westward  of  the  west  abutment  of  the  High  Viaduct. 

TOLL  PLAZA 

Obviously  the  toll  collection  facilities  should  be  located  on  the  San  Francisco  side, 
and  the  Board  of  Directors  of  the  District  decided  that  the  District's  Administration 
Building  should  adjoin  the  toll  plaza.  The  area  finally  granted  the  District  by  the 
Presidio  authorities  for  this  purpose  is  3  50  ft.  wide  and  500  ft.  long  and,  although  the 
500  ft.  length  is  less  than  that  requested  and  desired  to  permit  easy  approach  to  the 
outside  toll  lanes,  an  operative  layout  has  been  effected.  An  increase  of  1  50  ft.  in  length 
would  have  made  a  great  improvement. 

Fourteen  toll  lanes  were  deemed  necessary  to  adequately  handle  all  the  traffic  which 
the  bridge  could  accommodate.  In  view  of  the  long  approaches  to  the  Toll  Plaza,  which 
from  the  boundary  lines  of  the  Presidio  are  in  no  way  connected  with  other  Presidio 
roadways,  it  seemed  desirable  to  provide  an  underpass  below  the  plaza  by  which  cars, 
entering  the  plaza  by  mistake,  could  turn  back  without  crossing  bridge  traffic.  Other 
frequent  users  of  this  underpass  would  include  District  officials  and  employees  as  well 
as  tradesmen  and  others  who  would  have  occasion  to  turn  around  at  the  plaza.  Aside 


1 14 


THE      GOLDEN      GATE  BRIDGE 


from  toll  booths,  housing  was  required  for  administrative  offices,  shops,  garages,  store- 
room and  powerhouse,  as  well  as  quarters  for  the  State  Highway  Patrol  stationed  at 
the  bridge. 

Several  layouts  were  made,  each  meeting  the  above  requirements  but  differing 
principally  in  the  size,  arrangement  and  type  of  construction  of  the  administration 
building  and  shops.  The  plan  adopted  placed  the  administration  offices,  shops,  storage, 
and  power  house  all  in  one  building  on  the  west  side  of  the  plaza.  On  the  east  side,  in 
line  with  the  toll  booths,  the  quarters  for  Highway  patrolmen  were  placed.  This 
arrangement  was  the  least  costly  and  although  it  lacks  symmetry  that  objection  is 
not  prominent. 

Portions  of  the  plaza  site  required  a  deep  fill.  However,  all  structures  are  carried 
on  foundations  to  rock.  The  underpass  structure  itself  carries  the  roadway  above  it,  as 
well  as  the  toll  booths  and  scale  pits.  Anticipating  future  settlement  of  the  fill,  mud  jack 
sleeves  were  specified  to  be  included  in  the  pavement  slabs,  centered  5  ft.  6  in.  in  one 
direction  and  7  ft.  in  the  other  direction. 

Each  toll  booth  is  provided  with  a  key  box  which  has  a  separate  key  for  each 
classification  of  traffic.  When  the  toll  collector  presses  a  key  corresponding  to  the 
classification  of  the  vehicle  for  which  he  is  collecting  the  toll,  automatically  the  amount 
of  the  toll  is  indicated  to  the  driver;  the  classification  number  is  lighted  on  the  overhead 
indicator  above  the  lane;  and  the  transaction  is  registered  remotely.  Axle  counters  in 
each  lane  remotely  register  the  number  of  axles  passing  through  the  lane  and  this  gives 
a  check  against  the  number  computed  from  the  registration  made  by  the  toll  collector. 
Each  collector  is  provided  with  a  distinctive,  identification  key  which  he  inserts  in  the 
key  box  at  the  beginning  of  his  shift  and  removes  whenever  he  leaves  the  booth.  At 
each  insertion  and  removal  of  the  key  a  printed  registration  of  the  date  and  time  of 
day,  and  the  axle  count,  is  made  at  the  remote  register.  The  scales  are  equipped  to 
automatically  register  remotely  the  amount  of  the  toll  collected  from  trucks  according 
to  weight.  Receipts  at  the  same  time  are  automatically  printed  showing  the  amount 
collected  according  to  weight. 

POWER,  LIGHTING  AND  SIGNAL  FACILITIES 

To  meet  government  requirements  it  was  necessary  for  the  District  to  provide, 
maintain  and  operate  navigation  lights  and  signals  comprising:  special  aid  to  navigation 
light  for  regular  U.  S.  Lighthouse  service  on  the  San  Francisco  Pier;  revolving  airway 
beacons  on  each  main  tower;  pier  lamps  on  both  main  piers;  mid-channel  lights— 6  white 
and  2  green;  6  obstruction  lights  on  each  cable;  two  diaphones  at  the  center  of  the  main 
span;  and  two  typhons  at  the  San  Francisco  Pier.  These  navigation  lights  and  signals 
must  be  ready  to  function  at  all  times  and  therefore  it  was  necessary  to  provide  an 
emergency  power  source  to  supply  electric  energy  should  there  be  an  interruption 
in  the  normal  power  service.  Also  a  standby  air-compressor  unit  was  necessary  to 


n6 


PLANNING 


maintain  air  pressure  while  the  other  unit  might  be  shut  down  for  repairs.  These  were 
the  principal  needs  to  be  met  aside  from  roadway  lighting,  building  lighting,  inter- 
communicating telephones,  and  power  elevators. 

When  the  bidding  plans  of  1931  were  prepared,  the  conception  of  electrical  needs 
was  not  complete.  At  that  time  the  plans  provided  for  a  substation  below  the  bridge 
floor  at  the  San  Francisco  Tower  where  the  District  would  receive  power  on  the 
secondary  side  of  the  11,000/2300  volt  transformers  which  would  be  furnished  by 
the  power  company.  Here  also  would  be  located  the  motor  driven  air-compressors  and 
the  emergency  power  unit.  As  plans  for  the  project  matured,  it  became  obvious  that 
insofar  as  practicable,  all  electrical  and  mechanical  equipment  should  be  centralized 
in  one  building  at  the  Toll  Plaza.  Accordingly  new  plans  were  made  which  accomplished 
the  aforesaid  centralization  and  also  provided  for  the  sodium  vapor  roadway  lighting 
that  had  been  decided  upon  as  early  as  1933. 

The  electric  service,  in  the  form  of  alternating  current,  3  phase,  60  cycle,  11,000 
volts,  is  delivered  to  the  main  control  panel  in  the  Power  House  at  the  Toll  Plaza.  Here 
it  is  stepped  down  to  2300  volts  by  means  of  transformers  of  which  duplicate  sets  are 
installed.  One  set  is  to  furnish  "preferred"  service  and  the  other  "emergency."  By  means 
of  a  selector-switch  either  set  can  be  made  to  function  as  "preferred"  and  the  other  as 
"emergency."  Either  set  of  transformers  is  capable  of  taking  the  entire  load  and  if  for 
any  reason  the  selected  "preferred"  set  becomes  inoperative,  the  "emergency"  set  will 
automatically  take  the  load  after  a  short  time-interval. 

Should  the  11,000  volt  service  be  interrupted  for  any  reason,  a  gasoline  engine 
generator-set  will  be  automatically  brought  up  to  voltage  and  thrown  on  the  2300 
volt  bus.  The  arrangement  is  such  that  when  this  is  done  the  main  service  will  have  been 
disconnected  from  the  bus,  it  being  impossible  to  throw  the  gasoline  engine  generator-set 
on  the  bus  as  long  as  the  1 1,000  volt  service  is  connected  to  it. 

When  the  11,000  volt  service  is  restored,  the  gasoline  engine  generator-set  will  be 
automatically  disconnected  from  the  bus  after  a  time-delay,  and  the  1 1,000  volt  service 
will  be  automatically  thrown  on  the  bus. 

As  an  exception  to  the  above,  it  has  been  arranged  so  that  during  daylight  hours, 
when  no  lights  are  being  used,  the  automatic  starting  of  the  generator-set  will  not  take 
place  unless  the  air  pressure  is  low. 

When  the  gasoline  engine  generator-set  is  supplying  the  electric  energy,  no  current 
is  available  for  the  roadway  lighting  circuits,  but  current  is  available  for  the  balance 
of  the  equipment. 

The  series  lighting  circuits,  seven  in  number,  are  controlled  from  a  supervisory 
switchboard  where  each  circuit  can  be  independently  switched  on  or  off  at  the  will 
of  the  operator. 

Roadway  lights  on  the  Suspended  Structure  and  the  Marin  and  San  Francisco 
Approaches  are  spaced  150  feet  apart  on  each  side  of  the  roadway  and  are  set  opposite 
one  another.  The  lighting  circuits  are  2300  volts,  6.6  amperes,  constant  current 


117 


THE      GOLDEN      GATE  BRIDGE 


Lighting  units  are  General  Electric  Company  Sodium-Vapor  Luminaires,  each  pro- 
vided with  a  6.6  ampere  IL  transformer  for  a  10,000  lumen,  series  lamp. 

Two  motor-operated  air-compressors  have  been  provided.  Each  has  capacity  to  meet 
all  requirements.  Either  can  be  selected  as  the  "preferred"  unit,  and  the  other  as  the 
"emergency"  unit.  Ordinarily  one  compressor  is  in  service,  and  it  automatically  starts 
and  stops  at  predetermined  air  pressures.  If,  however,  this  compressor  fails  to  start, 
the  emergency  compressor-set  will  automatically  start  when  the  air  pressure  drops  5 
pounds  below  the  normal  starting  pressure. 

In  the  east  shaft  of  each  main  tower  there  has  been  provided  a  small,  electric 
service-elevator  which  gives  access  to  the  tower  base,  the  tower  top  and  to  each  inter- 
mediate strut.  These  are  intended  particularly  to  facilitate  servicing  of  pier  lights  at 
the  tower-bases,  and  airway  beacons  at  the  tower-tops. 

A  storage  battery  has  been  provided  to  furnish  current  for  starting  the  gasoline 
engine;  for  the  indicator  lights;  for  operating  the  oil  switch;  and  for  emergency 
lighting  of  certain  lamps  in  the  power  house  and  at  the  toll  booths. 


n8 


BOOK  THREE 


119 


CONSTRUCTION  INVOLVED  NEW  PROB- 
LEMS FACED  AND  MET  WITH  COURAGE 
AND  RESOURCEFULNESS  BY  THE  COM- 
BINED FORCES  OF  THE  ENGINEERING 
STAFF  AND  BUILDERS. 


121 


THE      GOLDEN      GATE  BRIDGE 


(g  ®  Kfi  in  USJ  (g  l1 2  (D  M 

Before  the  contracts  for  construction  were  drawn  a  careful  study  of  the  construc- 
tion schedule  was  made  to  determine  the  most  economical  program  for  the 
District.  This  schedule  took  into  account  savings  that  might  follow  by  avoiding 
duplication  of  expensive  contractors'  equipment  and  keeping  interest  during  construc- 
tion at  a  minimum.  Interest  cost  during  construction  was  kept  at  a  minimum  not  only 
by  building  each  unit  of  the  work  as  rapidly  as  possible,  but  also  by  scheduling  the 
completion  of  each  unit  so  that  it  would  be  ready  simultaneously  with  the  other  units 
required  for  the  next  stage  of  construction. 

The  construction  schedule  of  a  suspension  bridge  is  narrowly  denned  by  the  natural 
sequence  in  which  the  various  units  must  be  built.  A  control  point  in  the  sequence  is  the 
start  of  cable  erection.  It  is  necessary  at  this  point  that  both  the  main  towers  and  the 
cable  anchorages  be  completed  ready  for  the  cable  erector.  If  the  completion  of  these 
various  units  is  simultaneous  and  if  their  construction  has  been  accomplished  in  the 
minimum  time,  then  the  interest  cost  has  been  kept  at  a  minimum.  The  construction 
of  the  various  foundations,  the  anchorages  and  piers  are  tasks  of  different  magnitude 
and  the  proper  scheduling  of  the  construction  of  these  foundations  determines  to  a  large 
degree  the  economics  of  the  entire  construction  schedule.  Included  in  the  work  to  be 
done  before  the  critical  date  of  starting  cable  erection,  is  the  construction  of  the  two 
main  towers  which,  if  carried  on  simultaneously,  involves  a  duplication  of  expensive 
equipment  and  contractor's  organization.  A  saving  in  the  contract  cost  of  the  main 
towers  is  effected  when  the  same  equipment  and  organization  can  be  used  on  both 
towers. 

On  the  Golden  Gate  Bridge,  the  construction  of  the  two  main  piers  presented  tasks 
so  greatly  varied  in  magnitude  that  the  District  had  the  option  of  either  constructing 
the  Marin  Pier  and  Tower  while  the  longer  task  of  building  the  San  Francisco  Pier  was 
under  way  and  thus  permit  erection  of  the  San  Francisco  Tower  later  with  the  same 
equipment  and  organization  as  the  Marin  Tower,  or  not  starting  the  Marin  Pier 
until  later  and  then  erecting  the  two  towers  simultaneously.  The  Engineer  chose  the 
former  program.  This  program  was  obviously  to  the  best  interests  of  the  District  since 
this  scheduled  the  work  in  accordance  with  the  capacities  of  fabrication  plants  of 
either  of  several  bidders  and  permitted  the  District  to  take  advantage  of  the  duplication 
in  fabrication  and  save  by  avoiding  duplication  of  equipment  for  erection. 

The  following  schedule  was  therefore  in  force  at  the  start  of  the  work.  It  was 
incorporated  in  all  contracts  not  only  for  the  main  bridge,  but  for  the  approaches  so 
that  all  work  was  contingent  upon  the  main  schedule  for  completion. 

Sept.  1,  1933— The  Marin  Pier  to  be  completed. 

April  1,  1934— The  San  Francisco  Pier  and  Fender  to  be  completed. 


122 


CONSTRUCTION 


Oct.  1,  1934— The  Anchorage  Base  Blocks  and  the  Anchor  Blocks,  including 
the  Anchorage  Steelwork  to  be  completed  in  readiness  to  receive 
the  cables. 

Jan.    1,  1.93?—  The  San  Francisco  and  Marin  Steel  Towers  to  be  completed  in 

readiness  to  receive  the  cables. 
Jan.    1,  1936— Cables  (except  wrapping)  to  be  completed. 
June  1,193  6— Anchorage  Weight  Block  to  be  completed. 
June  1,193  6— Stiff  ening  Trusses  and  Floor  Steel  to  be  completed. 
Dec.    1,  1936— Concrete  Pavement  to  be  completed. 

Work  on  all  four  main  foundations  viz:  main  piers  and  anchorages  was  begun 
simultaneously.  First  to  be  completed  was  the  Marin  Pier. 

CONCRETE  MATERIALS  AND  HANDLING 

One  of  the  unique  features  in  connection  with  the  contracts  for  the  anchorages  and 
main  piers  was  the  arrangement  for  the  delivery  of  ready-mix  concrete  to  the  point  of 
deposit.  These  two  contractors  made  an  agreement  with  the  Pacific  Coast  Aggregates 
Co.,  a  building  materials  firm,  whereby  Barrett  &  Hilp,  contractors  for  the  anchorages, 
built  a  dock  on  the  Marin  side  of  the  Gate  and  the  Pacific  Bridge  Co.,  contractors  for 
the  main  piers,  built  a  similar  dock  on  the  San  Francisco  side.  The  Pacific  Coast  Aggre- 
gates Co.  installed  equipment  on  both  docks  to  comprise  proportioning  or  Batching 
Plants  with  all  the  latest  improvements.  These  proportioning  plants  being  located  close 
to  the  work  supplied  practically  all  of  the  concrete  for  the  project.  The  San  Francisco 
Batching  Plant  was  located  one-half  mile  from  Fort  Point  which  was  the  nearest  point 
where  barges  could  be  anchored  safely  the  year  around. 

On  the  San  Francisco  side,  aggregate  was  brought  to  the  plant  on  barges  having  a 
capacity  of  500  tons.  Barges  were  unloaded  with  a  Wiley  Whirley  using  a  clam-shell 
bucket  of  three-yard  capacity  at  a  rate  of  about  160  tons  per  hour.  Aggregate  was 
placed  in  three  storage  bunkers,  one  for  sand  and  two  for  gravel,  each  bunker  having 
a  capacity  of  450  tons. 

The  aggregate  was  conveyed  by  belt  from  the  storage  bunkers  to  two  bins,  one  of 
which  was  located  above  each  batcher.  Each  bin  was  divided  into  four  equal  compart- 
ments and  had  a  total  capacity  of  200  tons. 

Cement  was  brought  to  the  material  dock  in  bulk  on  barges  carrying  2000  barrels 
each.  A  Fuller-Kinyon  portable  pump  with  a  capacity  of  100  barrels  per  hour  was  used 
to  unload  the  cement,  pumping  the  cement  into  a  500-barrel  tank  mounted  over  a  sta- 
tionary pump.  This  pump  discharged  the  cement  through  a  5 -inch  pipe  line  from  the 
500-barrel  tank  into  two  storage  tanks,  each  with  a  capacity  of  1500  barrels  and 
mounted  adjacent  to  each  batching  unit. 

On  the  Marin  side,  aggregate  was  unloaded  from  barges  with  a  steam  locomotive 
crane.  There  were  twelve  bunkers  each  with  a  capacity  of  100  tons.  The  cement  was 


123 


THE      GOLDEN      GATE  BRIDGE 


pumped  from  barges  with  a  portable  Fuller-Kinyon  pump  into  one  2000-barrel  ca- 
pacity tank.  A  stationary  pump  conveyed  the  cement  through  a  pipe  line  into  two 
tanks  having  a  capacity  of  2  5  0  barrels  each  and  mounted  adjacent  to  each  batching  unit. 

Cement,  aggregate  and  water  were  measured  separately  and  batched  directly  into 
truck  mixers.  Fairbanks  visible  dial  scales  were  used  for  weighing  aggregate  and  cement. 
The  aggregate  scale  was  separate  from  the  cement  scale  and  had  four  beams,  each 
with  a  capacity  of  6000  pounds.  A  poise  was  set  on  each  beam  for  the  required  weight, 
the  dial  indicating  that  weight,  and  as  the  material  was  discharged  into  the  weighing 
bin  the  dial  pointer  approached  zero.  When  zero  had  been  reached,  the  correct  weight  of 
material  was  in  the  weighing  bin  and  the  operator  manually  closed  the  gate  controlling 
the  flow  of  that  particular  aggregate.  A  flag  mounted  on  the  dial  indicator  intercepted 
a  photo-electric  beam  at  zero,  actuating  a  relay  and  causing  a  solenoid  to  unlock  the 
next  material  gate  and  allowing  the  next  scale  beam  to  be  used. 

The  cement  was  weighed  by  a  separate  scale  into  a  separate  weighing  bin.  The  poise 
was  set  on  the  beam  for  the  required  weight  and  this  weight  indicated  on  the  dial.  A 
screw  conveyor  carried  the  cement  from  the  storage  tank  into  the  cement  weighing 
bin.  In  operating  the  device,  when  the  dial  pointer  reached  zero,  a  photo-electric  beam 
was  intercepted  thereby  automatically  shutting  off  the  electric  motor  driving  the 
screw-conveyor  and  stopping  the  flow  of  cement. 

When  the  aggregate  and  cement  had  been  weighed  into  their  respective  weighing 
bins,  a  discharge  gate  was  automatically  unlocked,  permitting  the  batch  to  be  dis- 
concrete      charged  into  the  truck  mixer.  The  opening  of  the  discharge  gate  on  the  weighing  bin 

i*  plant  at 

the  right       automatically  actuated  the  discharge  of  water  from  a  syphon-type  Ransome  tank.  The 


CONSTRUCTION 


water  discharge  was  controlled  by  a  calibrated  wheel,  the  setting  of  which  governed  the 
point  at  which  the  syphon  broke,  stopping  the  flow  of  water  at  the  predetermined  point. 

Each  batching  plant  was  equipped  with  two  separate  batching  units.  All  discharge 
gates  were  lever-operated  manually.  With  both  units  operating,  the  plant  readily  turned 
out  120  cubic  yards  per  hour. 

The  concrete  was  mixed  in  Mixer-Trucks.  The  unit  comprised  a  mixer-drum 
mounted  on  a  truck  chassis  and  powered  through  a  power  take-off  from  the  truck 
motor.  A  hydraulic  hoist  raised  the  mixer  for  discharging  the  load.  The  mixer-drum  was 
cylindrical  in  shape  and  had  a  frustrum  of  a  right  circular  cone  at  one  end  for  charging 
and  discharging.  The  overall  length  of  a  mixer-drum  was  10  feet  8  inches  and  the 
mixing  capacity  four  cubic  yards.  The  mixer-drums  were  equipped  with  pick-up  and 
overthrow  blades  and  their  mixing  speed  was  1 5  R.P.M.  A  hinged  gate  with  rubber  hose 
gasket  was  fastened  at  the  end  opening. 

Each  mixer  truck  was  provided  with  a  timing  device  or  meter-box  for  the  purpose 
of  controlling  the  mixing  time  of  each  load.  This  device  was  so  arranged  that  the  load 
ticket  was  perforated  while  passing  through  a  slot  in  the  meter-box  at  a  fixed  speed.  The 
time  required  for  the  ticket  to  pass  through  the  slot  was  equal  to  the  required  mixing 
time.  The  ticket  was  inserted  in  the  slot  at  the  time  the  load  was  completely  charged 
into  the  mixer  and  the  load  was  not  discharged  until  the  ticket  had  passed  entirely 
through  the  slot  and  was  perforated  for  its  entire  length.  The  meter-box  was  connected 
by  a  flexible  speedometer  cable  to  a  friction  plate  on  the  mixer-drum  shaft.  The  speed  of 
the  mixer-drum  regulated  the  engagement  of  a  clutch  in  the  meter-box.  This  clutch 
would  engage  only  at  speeds  of  14  R.P.M.  or  over,  thereby  causing  the  ticket  to  move 
only  when  the  mixer  was  turning  within  the  required  speed  range. 

Aggregate  samples  were  secured  from  barge,  belt  and  bin  with  a  scoop  or  shovel.  All 
barge  loads  were  sampled  and  in  such  manner  that  a  composite  sample  was  made  from 
several  smaller  samples  taken  from  various  parts  of  the  barge.  Composite  samples 
weighed  about  40  pounds  for  coarse  aggregate  and  about  20  pounds  for  fine  aggregate. 
The  latter  samples  were  quartered  down  to  about  500  grams  for  testing.  Belt  samples 
were  occasionally  taken  as  a  check  on  barge  samples. 

Moisture  contents  of  the  aggregates  were  determined  from  samples  secured  at  the 
batching  plant  bin.  These  moisture  determinations  were  made  daily  and  several  times 
daily  during  large  pours. 

A  field  testing  laboratory  was  established  at  each  plant.  The  necessary  equipment 
was  installed  for  the  testing  of  aggregate  and  cement  and  for  experimental  and  test  work 
in  concrete.  These  laboratories  were  the  control  points  for  all  concrete  production. 

Concrete  mix  designs  were  based  on  the  following  theories: 

1.  Water-cement  ratio  for  strength,  the  volume  of  water  per  sack  of  cement  having  a 
direct  effect  upon  the  strength  of  the  concrete  obtained. 

2.  Fineness  modulus  grading,  the  grading  of  the  individual  and  combined  aggregates 
in  the  mix,  determining  the  consistency  and  workability  of  the  mix. 


125 


THE      GOLDEN      GATE  BRIDGE 


3.  Absolute  volume,  the  yield  of  a  mix  being  determined  by  the  sum  of  the  absolute 
volumes  of  the  component  parts  in  a  mix,  including  water  and  cement. 

Physical  characteristics  and  specific-gravity  tests  were  made  on  all  fine  and  coarse 
aggregates  used,  in  accordance  with  the  latest  approved  A.S.T.M.  Standards,  from 
which  weight-conversions  were  made,  batching  of  concrete  being  done  by  weight  in- 
stead of  volume.  Cement  testing  was  done  by  Smith,  Emery  &  Co.,  a  commercial  testing 
laboratory. 

All  mixes,  with  the  exception  of  a  few  "lean"  weight  mixes,  were  designed  upon  a 
minimum  strength  requirement  at  28  days,  tests  on  the  set  concrete  being  made  accord- 
ing to  A.S.T.M.  Standards.  In  addition,  a  minimum  cement  content  of  5.2  sacks  per 
cubic  yard  of  concrete  was  specified.  Cement  contents  of  the  various  strength  concrete 
mixes  used  ranged  from  5.2  to  8.0  sacks  per  cubic  yard,  with  grout  mixes  from  8.0  to 
12.0  sacks.  Strength  requirements  varied  from  2  500  pounds  to  4000  pounds  per  square 
inch,  and  the  maximum  size  of  aggregate  varied  from  %  inch  to  2  l/z  inch  (square  hole) 
according  to  particular  requirements  of  placing.  Grouts  for  topping  fillers  under  base 
plates,  etc.,  were  limited  to  x/4  inch  maximum.  In  all,  about  50  basic  mixes  were  designed 
and  used,  with  variations  in  each  mix  due  to  changes  in  aggregate  grading,  moisture,  etc. 

Upon  notification  of  the  starting  of  a  concrete  pour,  the  batching-plant  inspector  set 
the  weighing  scales  for  the  predetermined  mix,  checking  moisture  contents  before  set- 
ting water  wheel.  After  batching  the  first  load  into  the  mixer-truck,  the  truck  was  held 
at  the  loading  ramp,  and  the  load  thoroughly  mixed  for  four  to  five  minutes,  then 
examined  as  to  consistency  and  slump.  If  necessary,  corrections  were  made  for  the 
following  batch,  and  this  batch  mixed  and  examined.  Further  control  of  the  concrete 
was  exercised  by  the  batching-plant  inspector  through  his  inspection  of  concrete  at 
placement  and  his  contact  with  the  placing  inspector.  As  placing  proceeded,  the  placing 
inspector  would  notify  the  batching-plant  inspector  by  note  or  telephone  as  to  any 
changes  thought  necessary  in  the  consistency  or  workability  of  the  concrete.  Additional 
control  was  furnished  by  frequent  slump  tests  made  both  at  the  batching  plant  and  at 
the  pouring. 

Concrete  test  cylinders  were  made  during  each  pour,  one  7  day  and  one  28  day 
cylinder  being  made.  On  large  pours,  test  cylinders  were  made  every  two  hundred  yards. 
After  a  concrete  mix  had  been  used  consistently,  and  a  good  idea  of  the  quality  and 
strength  of  the  concrete  had  been  obtained,  the  seven  day  tests  were  omitted  and  only 
the  twenty-eight  day  tests  made.  Specifications  required  8  inch  by  1 6  inch  test  cylinders, 
but  due  to  the  insufficient  load  capacity  of  the  testing  machine,  6  inch  by  12  inch  test 
cylinders  were  substituted.  The  molds  used  were  either  6  in.  by  1 2  in.  steel  tubing  fitted 
with  spring  clamps  and  l/z  in.  thick  steel  base  plate,  or  the  standard  6  in.  by  12  in. 
paraffine  paper  mold  with  tin  bottom. 

Test  cylinders  were  made  as  concrete  was  being  placed  and  at  the  site  of  placing,  to 
minimize  handling  of  wet  concrete  from  site  to  field  laboratory.  A  truck  load  of  con- 
crete was  half  emptied  before  securing  the  test  sample,  in  order  to  approximate  average 

ia6 


CONSTRUCTION 


conditions  in  the  batch  of  concrete.  Test  cylinders  were  made  by  placing  the  concrete  in 
the  mold  in  layers  3  in.  to  4  in.  thick  and  rodding  each  layer  25  times  with  a  bullet 
pointed  5/%  in.  diameter  rod.  After  rodding  the  top  layer,  the  surface  concrete  was 
leveled  off,  covered,  and  the  cylinder  placed  under  cover  in  a  location  free  from  vibra- 
tion or  movement  to  allow  the  fresh  concrete  to  obtain  its  proper  set.  After  allowing  to 
set  for  48  hours,  the  molds  were  stripped  off,  the  cylinders  marked  and  taken  to  the 
testing  laboratory,  care  being  taken  not  to  injure  them  in  transit. 

On  arrival  at  the  laboratory,  the  test  cylinders  were  placed  in  a  moist  closet,  heated 
to  70°.  When  a  sufficient  number  were  on  hand,  they  were  removed  from  closet  to  an 
adjoining  level  table,  placed  in  a  vertical  position  and  capped  with  a  mixture  of  plaster 
of  paris  and  cement.  Oiled  glass  plates  were  used  to  obtain  a  true  level  surface,  being 
pressed  upon  the  fresh  capping  cement,  leveled  off  with  a  hand  level,  and  excess  material 
was  removed  from  under  the  plate  by  a  spatula.  After  the  cap  had  hardened,  the  cylinder 
was  reversed  with  the  plate  still  in  position,  and  the  opposite  end  capped.  Upon  comple- 
tion of  capping,  cylinders  were  replaced  in  a  moist  closet  to  prevent  cracking  and 
shrinking  of  caps,  the  glass  plates  being  removed  the  following  day. 

Cylinders  to  be  tested  were  removed  from  the  moist  closet,  wiped  off,  weighed, 
average  diameter  and  height  measured,  ends  checked  for  levelness  and  placed  in  a 
200,000  pound  Riehle  vertical  hydraulic  compression  machine.  An  adjustable  bearing 
block  was  used  on  the  top  end  to  compensate  for  any  inclination  of  the  cylinder  from 
the  vertical.  Load  was  applied  to  the  cylinder  uniformly  and  without  shock. 

The  total  load  indicated  by  the  testing  machine  at  failure  was  recorded,  and  the  unit 
compressive  strength  calculated  in  pounds  per  square  inch  of  area.  The  type  of  failure 
and  appearance  of  concrete  were  also  noted.  All  data  obtained  was  entered  upon  the 
laboratory  test  sheet  made  for  each  cylinder,  identifying  the  cylinder  with  information 
concerning  mix,  slump,  location,  age,  etc. 

ANCHORAGE  CONSTRUCTION 

The  construction  of  the  main  anchorages  and  pylons,  together  with  the  piers  and 
abutments  for  both  the  Marin  and  San  Francisco  Approaches  was  undertaken  under 
Contract  III  by  Barrett  &  Hilp.  Although  the  size  of  the  two  anchorages  varies  slightly 
on  account  of  the  difference  in  topography,  each  consists  of  the  same  three  distinct  types 
of  construction.  The  anchorages  proper  are  of  heavy  mass  concrete  requiring  methods 
similar  to  dam  construction;  the  housings  are  light  reinforced  concrete  buildings;  and 
the  pylons  high,  hollow,  reinforced  concrete  shafts. 

Construction  of  the  anchorages  was  divided  into  two  stages.  The  first  stage  included 
not  only  those  parts  necessary  to  permit  the  erection  of  the  main  cables,  but  also  as  much 
of  the  housing  and  pylons  as  could  be  built  without  interfering  with  the  operations  of 
the  cable  erector.  This  was  done  in  order  to  minimize  the  amount  of  work  that  had  to 
be  performed  after  completion  of  the  cables. 


127 


THE      GOLDEN      GATE  BRIDGE 


The  anchorage  at  either  end  of  the  bridge  comprises  two  separate  masses  of  concrete 
into  which  each  of  the  cables  is  anchored.  Each  mass  was  constructed  in  three  units: 
the  base  block  or  foundation;  the  anchor  block  containing  the  anchor  chains  and  gird- 
ers; and  the  weight  block  which  rests  on  top  of  the  anchor  block. 

The  Marin  Anchorage  is  located  against  the  side  of  a  sandstone  and  shale  hill.  The 
bottoms  of  the  East  and  West  base  blocks  are  at  elevations  78  and  84.5  respectively. 
The  San  Francisco  Anchorage  was  founded  deep  in  the  serpentine  ledge  along  the  shore 
at  elevations  —3  5  and  —45  for  the  East  and  West  base  blocks  respectively. 

The  bottoms  of  the  excavations  together  with  the  faces  toward  the  bridge  were  so 
cut  into  the  rock  that  the  bearing  surfaces  would  be  normal  to  the  reaction  of  the  com- 
pleted structure.  This  involved  cutting  the  bottom  of  the  excavation  into  a  toothlike 
surface  with  the  depth  of  the  teeth  approximately  four  feet. 

On  the  Marin  Anchorage,  excavation  was  done  by  means  of  a  power  shovel  and 
blasting  powder.  Suitable  rock  for  the  foundation  was  uncovered  at  plan-depth  except 
for  one  corner  of  the  east  base  block  where  a  small  amount  of  additional  excavation 
was  required. 

On  the  San  Francisco  side,  the  contractor  elected  to  first  relocate  and  rebuild  an  old 
granite  seawall  out  a  sufficient  distance  from  the  structure  so  that  it  could  be  used  as  a 


CONSTRUCTION 


During  all  of  the  excavations  for  the 
base  blocks  no  pumping  was  necessary. 
The  material  for  the  San  Francisco 
Anchorage  was  excavated  with  a  power 
shovel  and  blasting  powder.  Careful 
watch  was  kept  on  the  drilling  and  load- 
ing of  holes  for  the  blasting  to  prevent 
overbreak  that  would  have  impaired  the 
solidity  of  the  foundation  bed.  The 
serpentine  formation  in  which  the  ex- 
cavation was  located  was  sound  and  im- 
pervious. The  bottom  of  the  pit  was  dry 
at  all  times.  Spoil  from  the  excavation 
was  deposited  outside  the  newly  located 
seawall. 

The  blocks  were  divided  into  pours 
of  such  size  that  a  layer  of  concrete 
could  be  placed  over  fresh  concrete  that 
had  not  yet  reached  the  initial  set.  These 
pours  were  laid  out  so  that  maximum 
resistance  to  shear  would  obtain  under 
the  stresses  existing  in  the  completed  ~v 
structure.  Because  of  the  extreme  width 
of  the  blocks  (sixty  feet,)  the  ordinary  methods  of  bracing  the  forms  by  the  use  of  hog 
rods  and  struts  were  not  convenient.  The  contractor  developed  an  ingenious  scheme 
whereby,  as  the  concreting  proceeded,  one  foot  square,  steel  anchor  plates  were  em- 
bedded in  the  fresh  concrete.  To  these  plates  were  attached  5/% -inch  diameter  rods  which 
projected  toward  the  forms  at  an  angle  of  approximately  45  degrees.  As  the  concreting 
progressed,  the  anchor  plates  were  sufficiently  restrained  by  the  initial  setting  of  the 
concrete  so  that  the  walers  could  be  fastened  to  the  rods  and  held  to  true  lines. 

After  the  base  blocks  had  been  completed,  one  pour  was  made  on  the  anchor  blocks 
so  that  the  erection  of  the  anchor  chains  and  girders  could  be  begun.  The  latter  material 
was  furnished  under  Contract  I-A  and  erected  by  the  contractors  for  the  anchorages. 
The  backs  of  the  anchor  girders  rested  against  a  cylindrical  surface  with  the  axis  of 
the  cylinder  at  a  slope  of  .29594  and  .31711  on  1.0000  from  the  vertical  in  San  Fran- 
cisco and  Marin  respectively.  The  center  planes  of  the  girders  were  set  radial  to  this 
cylindrical  surface.  The  anchor  chains  were  supported  on  steel  falsework  which  was 
embedded  in  the  concrete  of  the  anchor  block  as  concreting  progressed.  Special  methods 
were  used  to  facilitate  the  full  distribution  of  the  cable  load  to  the  anchor  girders.  As  an 
aid  to  this  end,  the  heads  of  the  eye-bars  and  all  projecting  steelwork  ahead  of  the  anchor 
girders  were  cushioned  with  expansion  joint  material.  In  addition,  the  steelwork  was 


The  Marin  Anchorage 
— eye-bar  chains  nearly 
erected 


129 


CONSTRUCTION 


given  two  field  coats  of  paint  which  may  be  of  assistance  in  preventing  bond  between 
the  concrete  and  the  eye-bars  although  it  is  believed  that  a  coating  for  the  bars  could  be 
found  that  would  be  more  effective  for  this  purpose. 

Construction  of  pylons  at  the  shore-ends  of  the  side  spans  was  carried  on  simultane- 
ously with  the  main  anchorages.  These  pylons  are  a  distinct  structural  feature  of  the 
bridge  since  they  contain  cable  anchorages  that  restrain  the  cable  vertically  at  equal 
distances  from  the  main  towers.  This  required  anchorage  steel  to  be  set  in  the  tops  of 
these  pylons  and  it  was  necessary  to  have  this  steel  ready  to  receive  the  cables  upon  their 
completion. 

The  pylon  on  the  San  Francisco  side  is  located  partly  inside  and  partly  outside  of  the 
old  granite  seawall.  The  first  step  in  its  construction  was  to  relocate  and  rebuild  the  old 
seawall  to  clear  the  pylon.  The  old  granite  blocks  were  reused  in  the  new  seawall.  The 
seawall  was  constructed  so  as  to  be  used  as  a  cofferdam  for  the  foundations  of  the  pylon 
itself  which  consists  of  two  hollow  concrete  shafts,  each  approximately  3  2  feet  by  3  6 
feet  in  cross-section,  with  walls  in  general  two  feet  thick.  These  shafts  were  concreted 
in  vertical  lifts  of  ten  feet  each.  A  special  movable  wooden  form  was  used  that  could  be 
lifted,  as  a  unit,  to  the  next  pour.  The  shafts  were  concreted  to  elevation  187  at  which 
stage  the  anchorage  steelwork  constituting  the  cable  tie-down,  was  erected  with  the 
pylon.  Completion  of  the  pylon  could  not  be  accomplished  until  after  the  cables  were 
finished  and  the  footwalks  removed. 

The  pylon  on  the  Marin  side  is  located  on  the  side  of  the  hill  in  front  of  the  Marin 
Anchorage.  Footings  for  this  pylon  are  founded  on  hard  sandstone,  well  down  and 
within  the  ledge  of  the  cliff.  Material  encountered  here  was  extremely  hard  and  the 
footings  were  shafted  down  without  shoring.  This  pylon  also  was  constructed  in  two 
stages:  the  first  stage  being  completed  prior  to  cable  erection  and  the  second  stage  after 
the  footwalks  had  been  removed. 

The  Anchorage  Housings  are  a  part  of  the  anchorage  itself,  and  serve  the  useful  ^h*"  F"ncisco 
purpose  of  protecting  the  cables  below  the  splay  points  from  the  weather.  Footings  in      Anchorage  Housin 


THE      GOLDEN      GATE  BRIDGE 


all  cases  were  built  on  firm  rock  at  elevations  that  assured  their  stability  in  relation  to 
the  excavations  on  either  side  of  them.  The  housings  were  constructed  in  two  stages,  the 
first  stage  included  all  construction  that  could  be  done  without  interfering  with  the 
operations  of  the  cable  contractor.  The  second  stage  was  undertaken  after  the  cables 
had  been  completed. 

MARIN  PIER  CONSTRUCTION 

The  Marin  Pier  is  located  on  a  rocky  shelf  of  basalt  at  the  water's  edge  of  a  high 
cliff.  To  gain  access  to  the  site  it  was  necessary  to  build  a  road  1700  feet  long  from  the 
end  of  an  existing  road  at  Fort  Baker.  The  construction  of  this  road  which  was  the  first 
work  done  on  the  contract  was  commenced  on  December  22,  1932. 

The  plans  called  for  the  pier  to  be  founded  at  elevation  —20.  Since  the  site  was  par- 
tially under  water,  it  was  necessary  for  the  contractor  to  first  construct  a  water  tight 
cofferdam  around  the  site.  On  account  of  the  rocky  bottom  and  the  exposure  to  the  full 
force  of  the  ocean,  he  elected  first  to  place  stone  filled  wood  cribs  in  the  deeper  water 
to  the  outside  of  which  a  steel  sheet  pile  cofferdam  could  be  anchored.  In  the  shallow 
water  it  was  found  possible  to  drive  steel  rails  into  the  talus  from  which  steel  channel 
walers  could  be  supported.  The  steel  sheet  piling  was  driven  between  these  channel 
walers  with  whatever  penetration  of  the  piles  could  be  secured.  They  could  be  driven 
deeply  into  the  sand  pockets  between  boulders  but  no  penetration  whatsoever  could  be 
realized  where  they  encountered  large  boulders  or  the  rock  ledge. 

Three  wooden  cribs  were  built  at  a  shipyard  and  towed  to  the  site.  Upon  a  survey 
of  the  bottom  by  divers  the  cribs  were  altered  as  required  to  fit  the  contours,  filled  with 
large  stone  and  sunk  to  position.  With  the  cribs  in  place,  the  sheet  pile  cofferdam  was 
completed  by  tying  the  walers  to  the  cribs.  This  work  was  performed  with  a  crawler 
type  locomotive  crane  working  on  a  wooden  trestle  built  on  top  of  the  cribs. 

As  soon  as  the  cofferdam  was  completed,  it  was  unwatered  and  excavation  started. 
The  rock  was  blasted  and  the  spoil  was  removed  with  a  power  shovel  operating  within 
the  excavation.  When  the  excavation  had  reached  the  elevation  of  —20,  it  was  discovered 
that  rock  was  not  exposed  over  a  portion  of  the  southwest  corner  of  the  foundation. 
Accordingly  the  overlying  material  was  removed  and  the  foundation  bed  stepped-off 
to  meet  the  lowest  elevation  where  solid  rock  was  encountered  at  elevation  —33.5.  The 
foundation  steps  below  —20  were  filled  with  concrete  to  that  elevation  and  effectively 
keyed  into  the  base  slab  above. 

Because  of  the  huge  size  of  the  pier  it  was  impossible  to  concrete  the  base  slab  in  one 
operation.  Accordingly  this  slab  which  was  1 0  feet  thick,  was  concreted  in  four  sections. 
These  sections  were  of  such  size  that  the  concrete  could  be  placed  in  horizontal  layers 
approximately  one  foot  thick  and  a  complete  layer  deposited  before  the  preceding  one 
had  reached  its  initial  set.  In  this  manner  a  monolithic  mass  of  concrete  was  assured  for 
each  pour.  All  pour  sections  were  keyed  together  by  shear  keys  and  steel  dowels  to  insure 
unity  of  action. 


132 


On  top  of  the  base  slab  the  pier  shaft  was  concreted  in  two  vertical  lifts  each  con-  The  Marin  Pier  and 
sisting  of  four  pours.  The  first,  or  bottom  lift,  was  20  feet  high  from  elevation  —10  to  Lighthouse  at"the  right 
elevation  10  and  the  second  lift  was  34  feet  high  from  elevation  10  to  elevation  44. 
The  pour  blocks  of  each  lift  were  so  laid  out  that  they  overlapped  the  blocks  in  the  pour 
below  and  thus  with  the  aid  of  keys  the  entire  mass  was  united.  By  dividing  the  pier  into 
vertical  blocks  of  comparatively  small  horizontal  cross-section,  a  minimum  of  shrinkage 
cracks  was  assured.  Also,  by  concreting  alternate  blocks,  the  intermediate  key  blocks 
filled  the  spaces  without  the  usual  voids  caused  by  shrinkage. 

Embedded  in  the  pier  shaft  above  elevation  —9  is  the  anchorage  steel  for  the  main 
tower  columns.  This  anchorage  steel  consists  of  107  tons  of  structural  steel  which 
extends  above  the  top  of  the  pier  and  is  riveted  to  the  main  material  of  the  tower.  It  was 
essential  that  it  be  held  securely  in  position  during  the  concreting  operations  and  this 
was  done  with  complete  success.  The  various  mats  of  reinforcing  steel  in  the  pier  were 
supported  by  independent  means  which  in  no  way  affected  the  position  of  the  main 
anchorage  steelwork. 

On  account  of  the  large,  plane,  exposed  surfaces,  form  lumber  with  the  rough  side 
against  the  concrete  was  used.  This  gave  the  exterior  a  rough  texture  which  does  not 
reflect  the  light  in  such  a  manner  as  to  accentuate  minor  irregularities  in  the  surfaces  of 
the  work  as  would  be  the  case  with  a  smooth  finish. 

Since  the  top  of  the  pier  was  required  to  be  poured  slightly  above  finished  elevation 
to  permit  grinding  down  to  a  true  plane,  it  was  essential  that  the  top  surface  be  as  near 
a  true  plane  as  possible  in  order  that  the  grinding  could  be  accomplished  with  uniform- 
ity. The  upper  two  feet  of  concrete  under  the  bearing  plates  of  the  tower  were  placed 


133 


THE     GOLDEN      GATE  BRIDGE 


after  the  main  mass  of  the  pier  had  been  given  time  to  shrink.  A  plane  top  surface  with 
a  maximum  variation  of  %  inch  was  secured  by  setting  wooden  screeds  not  more  than 
four  feet  apart  over  the  bearing  area. 

The  upper  seven  feet  of  the  pier  contains  four  heavy  mats  of  reinforcing  steel  to 
take  care  of  the  horizontal  force  transmitted  to  the  pier  from  the  tower  above. 

Surface  reinforcing  was  placed  not  less  than  9  inches  from  the  surface  of  the  con- 
crete so  as  to  provide  ample  covering  as  protection  against  weathering. 

SAN  FRANCISCO  PIER  CONSTRUCTION 

The  site  of  the  San  Francisco  Pier  is  1100  feet  off-shore  at  the  narrowest  point 
of  the  Golden  Gate  where  the  tide  sweeps  with  a  velocity  of  6. 5  knots  and  where  there 
is  no  protection  from  the  full  force  of  heavy  seas  and  ocean  storms.  The  bottom  of  the 
strait  at  this  point  is  bare  rock— a  ledge  of  serpentine  from  which  all  traces  of  over- 
burden, except  large  boulders,  have  been  swept  away,  lying  60  to  80  feet  below  low 
water;  the  pier  footing  was  to  be  carried  to  100  feet  below  low  water.  The  site  afforded 
scant  facilities  for  construction  equipment  and  operations.  Thus,  every  proposed  scheme 
for  construction  had  to  face  not  only  the  general  problem  of  founding  a  pier  in  deep 
water  on  a  rock  ledge  devoid  of  overburden,  but  also  had  to  deal  with  strong  tidal  cur- 
rents daily,  and  occasionally  the  battering  of  heavy  seas  incidental  to  ocean  exposure. 

It  was  required  by  the  specifications  that,  "the  rock  surface  shall  be  exposed  to 
permit  thorough  inspection,  exploration  and  excavation,  and  the  depositing  of  the 
concrete  in  the  dry.  The  pier  shall  be  constructed  by  the  pneumatic  process."  A  mini- 
mum penetration  of  20  feet  into  the  rock  ledge  had  been  established  as  a  requirement  to 
insure  ample  confinement  of  the  supporting  rock.  As  to  method  of  construction, 
analysis  of  the  problem  indicated  the  essential  requirement  to  be  sufficient  protection  of 
the  pier  site  to  permit  excavating  and  leveling  off  a  bearing  surface  20  to  40  feet  down 
in  the  rock,  and  provision  for  inspection  of  the  foundation  bedrock  as  an  assurance 
of  its  security. 

To  afford  the  required  protection  the  original  design  contemplated  the  construc- 
tion of  a  concrete  fender-wall  around  the  pier  site,  founded  on  the  properly  benched- 
off,  rock  surface.  This  wall  as  designed  had  a  thickness  of  30  ft.  up  to  elevation  —45. 
Between  —45  and  —18  it  was  27^2  ft.  thick  and  above  that  the  thickness  varied  from 
14  ft.  at  —18  to  10  ft.  at  15.  This  fender  was  to  be  170  feet  x  311  feet  outside,  with 
rounded  ends,  and  110  feet  x  247  feet  inside.  Within  this  enclosure  a  pneumatic  caisson 
90  feet  by  18  5  feet  in  overall  plan  dimensions  with  rounded  and  pointed  ends,  was  to 
be  sunk  as  a  base  for  the  concrete  pier  superstructure,  the  latter  to  begin  at  about  eleva- 
tion —50. 

The  original  plan  called  for  the  construction  of  the  fender  wall  in  successive  units 
by  underwater  methods  and  for  pneumatic  sinking  of  the  pier  base  itself.  As  the  work 
progressed,  conditions  made  changes  in  the  construction  procedure  necessary,  and  from 


134 


CONSTRUCTION 


time  to  time  the  original  scheme  was  revised  and  developed.  The  final  construction 
retained  the  method  of  constructing  the  fender  wall  about  as  originally  specified,  but 
discarded  the  pneumatic  method  for  constructing  the  pier  base. 

One  important  result  of  these  changes  was  to  eliminate  the  pier  base  as  a  separate 
unit  and,  in  effect,  to  integrate  the  fender  with  the  deep  tremie  concrete  mass,  poured 
within  the  fender  as  supporting  base  for  the  pier. 

ACCESS  TRESTLE:  The  use  of  floating  equipment  at  the  pier  site  for  anything  but 
dredging  was  precluded  by  rough  water.  The  first  step  in  construction  was  to  provide 
access  to  the  pier  site  by  a  trestle  which  it  was  planned  to  continue  around  the  pier  site. 
A  steel  trestle  was  therefore  built  out  from  shore  to  the  pier  site;  the  deck  of  this  first 
trestle  was  at  elevation  15.  The  original  plan  for  trestle-bent  footings  was  to  drill  holes 
in  the  rock  slightly  larger  than  the  steel  columns  and,  after  insertion  of  the  columns  to 
place  concrete  around  them,  but  this  plan  was  abandoned  when  no  drills  could  be  found 
that  could  clear  the  holes  effectively  as  they  were  drilled. 

A  submarine  bombing  scheme  then  was  developed,  which  consisted  of  dropping  a 
small  bomb  on  the  rock  at  the  pile  location,  driving  it  into  the  rock  with  a  heavy  fol- 
lower, then  firing  it,  and  shattering  the  material  with  successive  blasts  of  this  sort  until 
it  was  possible  to  drive  a  steel  tubular-pile  footing  into  the  shattered  rock.  This  method 
was  successful.  The  steel  tubes  were  driven  into  position,  and  the  bottoms  of  the  columns 
were  inserted  in  them.  After  each  bent  was  erected,  the  tubes  were  filled  with  concrete. 
Under  this  plan,  trestle  erection  proceeded  rapidly  and  was  completed  October  19, 1933. 

Just  as  the  trestle  was  completed,  a  2000  ton  steamer  ran  through  it  about  400  feet 
offshore.  The  collision  carried  away  six  spans  entirely  and  because  the  trestle  deck  had 
been  securely  fastened  together,  the  impact  of  collision  thrust  the  remaining  portion 
of  the  trestle  about  6  feet  inshore.  Immediately  after  this  accident,  repair  of  the  trestle 
was  begun.  Wreckage  of  the  demolished  bents  was  removed  by  divers.  The  destroyed 
section  was  replaced  by  timber  bents  to  save  the  time  required  for  the  fabrication  of 
steel  bents. 

The  outshore  bent  of  the  access  trestle  was  built  in  the  form  of  a  steel  tower  that 
weighed  about  5  0  tons  and  was  designed  to  serve  as  a  guide  for  lowering  into  place  forms 
for  the  first  unit  of  the  concrete  fender  ring. 

The  outer  vertical  face  of  the  guide-tower  was  provided  with  two  8  5  pound  rails 
down  which  the  forms  for  the  first  section  of  the  fender  were  to  be  lowered ;  forms  for 
succeeding  sections  could  then  be  lowered  down  similar  rails  on  the  leading  face  of  the 
previously  concreted  section.  The  tower  was  supported  in  the  same  manner  as  the  trestle 
bents.  Four  footing  pipes  were  first  driven  into  the  rock  in  holes  made  by  small  pilot 
bombs;  then  the  tower  was  lowered  and  the  legs  were  guided  into  the  pipes  by  divers. 
Difficulty  and  hazard  attended  the  placing  of  this  50  ton,  115  foot  high,  steel  tower, 
because  of  the  force  of  the  waves  which  swept  in  from  the  open  sea,  and  the  tides. 
Entering  the  tower  legs  into  the  foundation  pipes  required  great  skill  on  the  part  of  the 


135 


Commencement  of 
construction  of 
fender-ring  at  end  of 
access  trestle 


four  divers  doing  the  work,  as  well  as  close  coordination  between  these  divers  and  the 
crew  above  water.  Working  periods  were  limited  to  slack  water  between  ebb  and  flow 
of  the  tide.  The  tower  was  placed  on  the  sloping  south  side  of  the  pier  excavation  men- 
tioned later;  the  north  or  lower  legs  were  founded  at  elevation  —90  (about  1 0  feet  above 
the  bottom  of  the  pier  excavation)  and  the  upper  or  south  legs  at  elevation  —70  on  the 
adjacent  sloping  surface. 

EXCAVATION  METHODS:  Excavation  of  the  pier  site  was  started  with  a  floating 
dredge  coincident  with  construction  of  the  access  trestle.  Measured  at  the  longitudinal 
center  line  of  the  bridge,  the  water  depth  at  the  south  or  land  side  of  the  pier  was  5  0  feet 
and  at  the  north  side  80  feet.  The  rock  ledge  was  of  such  hardness  that  it  could  not  be 
removed  without  blasting.  A  method  of  underwater  blasting  was  developed  which 
involved  blasting  with  small  pilot  bombs  until  a  sufficient  depth  of  rock  had  been 
loosened  so  that  a  large  bomb  containing  some  200  pounds  of  high  explosive  could  be 
driven  into  the  hole  well  below  the  adjoining  rock  surface.  A  novel  phase  of  this  method 
was  the  driving  of  the  large  bomb  into  place  by  means  of  a  2  500  pound  hammer,  after 
which  the  wire  leads  to  the  blasting  cap  in  the  bomb  were  recovered  by  a  diver  and 
carried  to  an  electric  blasting  machine  on  the  surface. 

After  blasting,  the  loose  rock  was  excavated  by  a  5  cubic  yard  bucket  with  specially 
reinforced  manganese-steel  teeth  and  lips.  The  great  amount  of  wear  on  this  bucket 


136 


CONSTRUCTION 


attested  the  hardness  of  the  rock.  In  general,  a  depth  of  1 5  feet  could  be  excavated  after 
one  layer  of  bombs  had  been  fired  20  feet  below  the  rock  surface.  Successive  layers  of 
bombs  were  staggered  so  as  to  remove  projecting  high  points.  This  program  of  excava- 
tion, carried  down  to  elevation  —100,  included  the  area  on  which  the  guide-tower 
was  to  be  erected. 

THE  FENDER  RING:  Several  methods  for  constructing  the  fender  previously  de- 
scribed as  a  means  for  protecting  the  pier  during  construction,  were  developed  at 
different  stages  of  the  work.  The  original  plan  was  to  erect  the  wall,  3  0  feet  thick  at  the 
bottom,  entirely  around  the  pier  site  and  within  this  fender  to  build  the  pier  base  on  a 
pneumatic  caisson.  The  fender  wall  was  to  have  been  founded  on  the  original  surface  of 
the  rock,  and  when  the  enclosure  was  completed,  a  pneumatic  caisson  was  to  have  been 
built  in  place  and  sunk  through  a  sand  leveling  fill  placed  inside  the  fender.  The  caisson 
was  to  have  penetrated  20  feet  or  more  into  the  rock  ledge,  thus  placing  the  pier  bottom 
at  elevation  —100. 

The  specification  contemplated  construction  of  the  fender  in  22  separate  units  each 
about  30  feet  square  in  plan.  The  first  revision  (See  diagram  "First  Revision"  page  143 ) , 
under  which  the  work  was  started,  provided  for  an  extension  of  the  inside  face  of  the 
fender  to  the  bottom  of  the  pier  excavation,  adopted  the  open  dredging  method  of  ex- 
cavation and  left  only  the  final  preparation  of  the  pier  foundation  to  be  done  under  air 
pressure.  The  concrete  was  to  be  placed  in  one  continuous  pour  for  a  height  of  about  8  0 
feet  in  each  of  the  22  separate  units  which  were  to  comprise  the  fender  ring,  ultimately 
extending  from  elevation  —100  to  elevation  15,  a  total  height  of  11 S  feet.  The  forms 
for  these  units  were  to  consist  of  a  series  of  steel  boxes  each  20  feet  high,  open  top  and 
bottom,  fitted  with  jaw  castings  on  one  side  to  engage  the  guide  rails  on  the  face  of  the 
guide  tower.  The  bottom  of  the  first  box  form  was  carefully  shaped  to  make  a  close  fit 
with  the  bottom  of  the  bay,  as  determined  by  very  accurate  soundings. 

To  insure  a  close  fit  between  successive  sections,  it  was  planned  to  lower  the  first 
box  until  the  top  was  just  awash  and  then  to  erect  a  second  20  foot  section  on  top  of  the 
first.  The  two  sections  were  to  be  fastened  together  by  riveted  splices  of  the  columns  in 
the  corners.  The  assembled  pair  of  units,  each  with  jaw  castings  engaging  the  rails,  was 
to  be  lowered  until  a  third  and  subsequently  a  fourth  section  could  be  added,  thus 
making  a  tier  of  sections  fastened  together.  When  the  tier  rested  on  the  bottom  the 
top-most  edge  could  have  been  at  elevation  —20. 

This  program  was  followed  up  to  the  point  where  four  sections  (80  feet  of  continu- 
ous forms)  were  suspended  in  engagement  with  the  rails  of  the  guide-tower.  The  plan 
anticipated  that  when  this  combined  form  had  been  rested  on  the  bottom  it  would  be 
filled  with  concrete  by  the  tremie  method  up  to  elevation  —20  without  interrup- 
tion. After  this  first  unit,  80  feet  high  had  been  completed,  the  same  procedure  of 
lowering  successive  boxes  and  riveting  them  together  was  to  be  followed  for  succeeding 
units  until  all  22  were  in  place,  thus  completing  the  fender.  The  point  of  note  in  this 


137 


THE      GOLDEN      GATE  BRIDGE 


plan  is  that  each  individual  unit  was  to  have  been  concreted  continuously  for  a  height 
of  80  feet  before  any  concrete  was  placed  in  the  next  unit.  Difficulties  met  in  this  plan 
will  become  apparent  in  the  following. 

After  the  legs  of  the  guide-tower  had  been  entered  into  the  pipes  embedded  in  the 
rock  foundation,  they  were  concreted  firmly  in  place.  The  steel  form  for  the  first  fender 
unit,  weighing  about  40  tons,  was  successfully  placed  in  the  guide  rails  and  lowered  until 
its  top  was  awash.  Additional  sections  were  added,  and  three  had  been  riveted  together 
as  planned  before  the  elements  interfered.  Then  a  storm  that  rolled  tremendous  waves 
through  the  Golden  Gate  caught  the  guide-tower  supporting  this  eccentric  load  of  three 
forms.  The  tall  tower  was  buffeted  to  such  an  extent  that  it  began  to  oscillate  about 
6  feet  backward  and  forward.  The  oscillation  evidently  caused  the  displacement  of  the 
foundation  pipes  in  which  footings  were  supported,  and  on  October  31,  1933  the  entire 
tower  and  the  forms  attached  to  it  were  carried  away. 

The  contractor  at  once  proceeded  to  recover  the  guide-tower  and  forms.  No  sooner 
had  they  been  salvaged  than  another  storm  caused  a  repetition  of  the  tremendous  rollers 
sweeping  in  through  the  Gate,  and  this  time  all  but  600  feet  of  the  access  trestle  was 
carried  away.  Coincident  with  the  removal  of  the  wreckage,  the  contractors'  engineers 
began  to  develop  plans  for  a  new  and  stronger  access  trestle. 

In  reconstructing  the  trestle,  it  was  decided  to  use  timber  not  only  because  of 
the  saving  in  time  by  avoiding  the  delay  necessary  for  fabrication  of  new  steel  bents,  but 
also  because  the  round  timber  piles  offered  less  resistance  to  the  strong  tidal  currents 
than  had  the  rolled-steel  "I"  sections  used  previously.  Further  precautions  included 
raising  the  trestle  deck  height  by  5  feet  so  as  to  keep  the  stringers  well  above  the  tops  of 
high  waves,  and  guying  the  bents  with  steel  cables  in  both  directions.  The  reconstructed 
trestle  deck  was  25  feet  above  mean  lower  low  water.  The  new  trestle  was  started 
December  1  5,  1933  and  was  completed  to  the  pier  site  March  8,  1934.  The  last  three 
bents  of  the  trestle  adjacent  to  the  guide-tower  were  made  of  steel  and  were  very  rigidly 
braced  both  above  and  below  water. 

Failure  of  the  guide-tower  had  demonstrated  the  difficulties  of  supporting  the  fender 
on  the  sloping  sides  of  the  pier  excavation  and  suggested  the  wisdom  of  having  fender 
footings  on  a  level  surface  at  the  same  elevation  as  the  pier  bottom. 

NEW  METHOD  OF  CONCRETING  FENDER  UNITS:  Accordingly,  a  modifica- 
tion of  the  fender  design  was  developed,  and  the  plan  of  construction  was  changed  to 
meet  it.  Departing  from  the  original  plan  for  a  continuous  pour  in  each  vertical  unit,  it 
now  was  decided  to  lay  up  the  fender  wall  in  courses  about  20  feet  high.  The  courses 
were  to  consist  of  blocks  30  feet  long  corresponding  in  plan  to  the  original  22  fender 
units.  The  start  of  the  first  course  was  to  be  made  at  the  point  where  the  first  vertical 
unit  had  been  started  and  it  was  decided  to  include  in  this  footing  the  columns  of  the 
guide-tower.  The  base  section  of  the  first  fender  unit,  therefore,  was  formed  and 
concreted  in  two  parts,  an  inshore  and  an  outshore  section. 


138 


CONSTRUCTION 


As  part  of  this  plan  the  area  excavated  to  elevation  —100  was  increased  to  permit 
the  entire  fender  ring  to  be  supported  on  a  level  foundation  at  the  same  elevation  as  the 
bottom  of  the  pier,  instead  of  only  the  inner  portion  of  the  ring  as  was  done  at  first. 
(See  diagram  "Second  Revision"  page  143.)  Also,  under  the  modified  plan,  the  fender 
units  were  to  be  built  up  to  elevation  —60  around  the  entire  elliptical  ring  before  any 
appreciable  amount  of  exposed  wall  was  raised  above  that  level.  This  is  the  plan  that  was 
finally  carried  to  completion. 

It  was  proposed  that,  after  the  fender  ring  had  been  closed  at  elevation  —40  the 
westerly  end  would  be  built  up  to  its  full  height  of  elevation  15  and  then  the  steel 
framing  over  eight  units  at  the  east  end  above  elevation  —60  would  be  temporarily 
removed  to  permit  entry  of  the  caisson,  which  would  have  been  built  at  a  shipyard, 
into  the  fender  ring.  After  the  caisson  had  been  floated  into  place,  the  plan  was  to  replace 
the  steel  framing  on  the  east  end,  complete  the  concrete  fender  ring  and  then  load  and 
sink  the  caisson  within  the  fender  enclosure. 

It  was  found  from  careful  study  of  the  stability  of  the  fender  sections  under  all 
weather  conditions  that,  because  of  their  greater  height  resulting  from  dredging  the 
full  fender  area  to  elevation  —100,  an  increase  in  the  fender  base-width  would  be  neces- 
sary. In  the  "Second  Revision,"  therefore,  the  base  section  of  the  fender  ring  was  in- 
creased in  thickness  by  a  1 0  foot  offset  inward  and  by  whatever  outward  offset  would  be 
necessary  to  carry  the  concrete  up  against  the  wall  of  the  excavation  within  which  the 
fender  was  built. 

The  inward  offset  of  the  fender  base,  with  its  top  at  elevation  —80,  extended  into  the 
area  that  was  to  be  covered  by  the  caisson.  In  consequence,  the  caisson  could  no  longer 
be  sunk  down  to  the  rock  surface  but  would  have  to  come  to  rest  on  the  ledge  of  the 
fender  base.  It  was  contemplated  that  the  space  between  the  caisson  and  the  inner  face 
of  the  fender  would  be  filled  with  concrete  from  elevation  —80  to  —50  by  tremie,  to  seal 
the  joint  in  order  to  make  possible  to  hold  the  compressed  air  while  gaining  the  founda- 
tion. Concrete  piers  were  planned  to  be  built  within  the  fender  area  under  the  intersec- 
tions of  the  caisson  cross-walls,  to  assist  in  carrying  the  weight  of  the  caisson  until  the 
working  chamber  could  be  sealed. 

The  excavation  over  the  fender  base  area  was  to  be  carried  to  elevation  —100  in 
general,  but  to  —105  at  the  east  end  of  the  fender  and  to  —110  at  the  northeast  sector 
where  the  original  rock  surface  dipped  down  in  a  narrow  depression  to  about  —95. 
Grouted  riprap  was  to  be  placed  between  the  fender  and  the  side  of  the  excavation. 

The  revised  plan  for  placing  concrete  in  the  fender  ring  involved  building  a  consid- 
erably larger  surface  of  formwork  under  water.  Because  most  of  the  steel  boxes  planned 
for  use  in  the  original  concreting  scheme  had  been  fabricated,  the  contractor  prepared 
to  utilize  as  many  of  them  as  possible.  Accordingly,  these  boxes  were  used  between 
elevation  —80  and  elevation  —40. 

The  larger  cross-section  of  footings  for  units  under  the  revised  plan  called  for  the 
development  of  a  lighter  form.  Therefore,  for  that  portion  of  the  fender  below  elevation 

139 

S.F.  TUBLIC  LIBRARY 


Jccess  trestle 


rtcing  cables 


Jfeel  Guide 
tower 


Cable  passes  through 
gusset  on  upper  truss 


Frame  For  farm, 
E/.-/00  fa  El  SO. 


Concrete  footing 


Lowering  forms  for  base  of  fender  wall 

The  bottom  form  for  the  pioneer 
unit  was  placed  in  two  sections.  The 
first  of  these  encompassed  the  legs  of 
the  guide  tower;  later  the  first  steel 
box  was  lowered  and  rested  upon  the 
bottom  form,  after  which  concret- 
ing of  the  remainder  of  the  base  of  the 
first  unit  and  the  steel  box  was  made 
as  a  continuous  pour.  On  all  the  re- 
maining sections  the  first,  or  bottom 
steel  box,  was  concreted  integrally 
with  the  base  block. 

The  second  steel  box,  constituting 
the  form  for  the  fender  wall  between 
elevation  —60  and  elevation  —40  was 
concreted  integrally  with  an  adjoin- 
ing box  on  the  next  unit  so  that  the 
second  course  of  the  wall  was  built  up 


THE      GOLDEN      GATE  BRIDGE 


—80,  each  form  was  built  as  a  rela- 
tively light,  wood  and  steel  frame, 
lowered  into  position  on  tricing  lines, 
two  to  each  form,  which  served  to 
guide  the  forms  to  their  proper  posi- 
tions. The  frame  alone  offered  a  mini- 
mum of  resistance  to  tidal  currents  as 
it  was  lowered.  Once  the  frame  was  in 
place  on  the  bottom  and  fastened  to 
the  adjoining  units,  the  sides  were 
built  up  with  wooden  panels  about  5 
feet  wide.  These  panels  were  weighted 
with  concrete  blocks  to  overcome 
buoyancy;  and  were  placed  by  divers 
using  a  fastening  adapted  to  quick 
manipulation  under  water.  All  of  the 
wooden  panels  and  the  principal 
members  of  the  steel  frame  were 
stripped  and  re-used  after  the  con- 
crete had  set. 

El.  Tap  of  rail 

ff.  +15   Tap  of  fender- 


WorJcmg  h-es/Ie 


Base  form  panels 
placed  by  divers: 


Typical  section  of  fender  and  types  of  concrete  forms  used 


Above:  Building  fender — working  out  in  both  directions  from  initial  unit.  Below:  Pouring  tremie  concrete  in 
fender.  Concrete  poured  into  hopper  just  above  the  water  is  deposited  in  the  forms  100  feet  below 


THE      GOLDEN      GATE  BRIDGE 


of  blocks  27^4  feet  x  60  feet  in  plan  and  20  feet  high. 

Above  elevation  —40,  an  entirely  different  plan  was  used  and  the  wall  was  built  of 
blocks  approximately  27l/z  feet  x  60  feet  in  plan  and  2  5  feet  high.  The  bents  and 
bracing  in  the  trestle  over  the  fender  side  were  so  designed  that  they  later  served  as 
guides  for  form  panels.  This  skeleton  steel  frame  offered  a  minimum  of  resistance  to  the 
current  during  construction  of  the  ring  below  elevation  —60  and  was  thoroughly 
braced  so  that  in  building  that  part  of  the  fender  above  elevation  —40,  two  20  foot 
sections  of  the  panel  forms  could  be  erected  simultaneously  with  safety.  The  forms 
were  designed  to  withstand  a  horizontal  pressure  of  130  pounds  per  square  foot.  Above 
elevation  —40,  form  panels  of  three  kinds  were  used:  steel,  weighed  timber  and  precast 
concrete.  The  latter  were  made  6  inches  thick  and  of  widths  to  fit  the  spaces  between 
the  vertical  guides.  The  precast  concrete  panels  were  used  principally  in  forming  the 
outside  of  the  fender  where  a  smooth  concrete  face  was  required. 

The  entire  fender  wall  was  firmly  bonded  together  with  keys  between  adjoining 
units  and  by  staggering  the  vertical  joints.  In  addition,  the  top  portion  of  the  wall 
above  elevation  —2  was  heavily  reinforced  with  steel  bars.  This  reinforcement  ties  the 
tops  of  the  units  together  and  horizontal  arch  action  will  be  developed  in  case  the 
structure  is  rammed  by  a  ship.  Above  elevation  —40,  enough  vertical  reinforcing  steel 
was  used  so  that  each  unit  would  stand  securely  as  a  vertical  cantilever  in  resisting  both 
wave  and  current  forces. 

TREMIE  FENDER  SEAL:  After  the  first  concrete  was  poured  in  the  pioneer  unit 
on  March  31,  1934,  progress  in  the  fender  ring  proceeded  according  to  schedule,  to 
the  point  where  the  eastern  end  of  the  ring  was  concreted  to  elevation  —40  and  the 
remainder  of  the  fender  wall  had  been  brought  up  to  elevation  IS,  the  ultimate  height. 
This  was  in  accord  with  the  earlier  plan  to  leave  the  eastern  end  open,  to  permit  the 
floating  in  of  the  caisson  as  the  contractor  had  elected  to  do. 

An  important  change  was  made  after  the  final  plan  of  fender  construction  had 
been  adopted.  It  was  decided  to  abandon  the  purpose  of  exposing  the  entire  area  of 
foundation  bedrock  within  the  caisson,  and  instead  to  place  a  tremie  concrete  seal 
within  the  fender  up  to  elevation  —64.  The  base  of  the  caisson  was  to  be  set  on  the  top 
of  this  seal  concrete  instead  of  on  the  fender  base  ledge  at  —80  as  previously  intended. 
However,  in  order  that  the  foundation  rock  could  be  inspected  (and,  if  necessary, 
further  excavation  done) ,  a  series  of  eight  inspection  wells,  4  feet  in  diameter  was  to  be 
provided  in  the  concrete  seal,  each  ending  in  a  15 -foot  steel  hemisphere  resting  on  the 
rock  surface.  These  shafts  could  then  be  entered  from  the  caisson  working-chamber 
under  the  protection  of  compressed  air  and  the  foundation  rock  examined.  This  de- 
cision was  reached  in  June,  1934  (See  diagram  "Third  Revision") . 

Results  of  the  dredging  operations  had  indicated  that  the  material  under  the  entire 
pier  area  was  uniform.  Hence  it  was  felt  that  the  area  made  accessible  by  the  eight 
inspection  wells  would  give  ample  characteristic  evidence  of  the  nature  of  the  founda- 

142 


CONSTRUCTION 


El  +  44 


CONCRETE 
SEAL 


ORIGINAL  PLAN 


FIRST  REVISION 


SECOND  REVISION 


-TREMIE  CONC 

THIRD  REVISION 


PLAN 


San  Francisco  Pier  and  Fender.  Diagram  shows  original  plan 
and  subsequent  progressive  development  during  construction 


The  fender  wall  has 
been  completed  and 
the  tremie  seal  is 
being  poured 


THE      GOLDEN      GATE  BRIDGE 


tion  rock.  In  case  inspection  indicated  any  necessity  for  going  deeper  with  the  pier 
foundation  it  still  would  be  possible,  by  excavating  in  the  inspection  chambers  under 
air  pressure  and  using  the  seal  concrete  as  the  deck  of  the  working  area,  to  carry  the 
pier  footings  to  a  lower  level. 

When  the  entire  fender  ring  had  been  brought  up  to  elevation  —40,  and  a  few  units 
at  the  west  end  had  been  continued  to  elevation  15,  the  effect  of  currents  and  wave 
action  on  the  bottom  was  so  greatly  diminished  that  divers  were  able  to  prepare  the 
surface  of  the  bottom  at  the  pier  site  for  the  tremie  seal.  The  area  to  be  covered  was  too 
great  to  attempt  a  single  continuous  pour  and  therefore  it  was  divided  into  seven 
sections,  each  30  feet  x  90  feet  in  plan.  Wooden  forms,  similar  to  those  used  in  the 
construction  of  the  fender  bases  were  designed  for  three  of  these  sections  and  were 
placed  by  divers.  Details  of  these  forms  were  such  as  to  permit  the  removal  of  all  wood 
used  as  forms  in  the  tremie  seal.  The  first  tremie  sections  were  carried  up  to  eleva- 
tion —64. 

CAISSON  MOORED  IN  ENCLOSURE— THEN  REMOVED:  On  October  8,  1934, 
with  all  skeleton  steel  bents  removed  from  the  east  end  of  the  fender,  a  caisson  was 
towed  to  the  site  and  moored  within  the  fender  enclosure.  Preparations  immediately 
were  begun  to  close  the  east  end  of  the  fender.  Before  this  could  be  done  however,  a 
violent  storm  arose  and  the  surging  of  the  caisson  within  the  fender  enclosure  caused  by 
wave  action  made  it  impossible  to  hold  it  firmly  in  place  with  mooring  lines.  It  battered 
the  steelwork  and  concrete  of  the  fender  with  such  force  as  to  threaten  to  wreck  itself 
within  the  fender  enclosure.  Several  of  the  fender  frame  members  were  badly  bent,  and 
the  inner  face  of  the  concrete  gouged  deeply. 

Because  wrecking  of  the  caisson  within  the  fender  at  this  time  would  endanger  the 
rest  of  the  work  and  seriously  delay  completion,  the  contractor  secured  permission  to 
remove  the  caisson  at  once  and  abandon  that  part  of  the  construction-plan  that  involved 
its  use.  Accordingly,  the  caisson  was  removed  and  the  closure  of  the  east  end  of  the 
fender  wall  was  begun  immediately. 

The  fender  ring  was  completed  on  October  28  and  by  November  4  the  tremie 
blanket  had  been  raised  to  elevation  —64.  In  lieu  of  using  the  caisson,  the  contractor 
planned  to  pump  out  the  fender  enclosure,  using  the  fender  wall  as  a  cofferdam. 
To  do  this,  it  was  necessary  to  add  more  concrete  to  the  seal,  raising  its  upper  surfaces 
to  elevation  —34.  This  additional  concrete  was  put  in  in  seven  units,  overlapping 
construction  joints  in  lower  portions  of  the  seal  and  increasing  the  thickness  over  the 
shelf  of  the  fender  base.  The  several  changes  made  in  the  seal  and  the  shape  of  the  pier 
shaft  above  elevation  —35  served  to  distribute  the  load  over  the  base  of  the  entire 
fender  in  addition  to  the  base  of  the  pier.  The  original  bearing  area  of  the  pier,  16,000 
square  feet  was  thus  increased  to  38,000  square  feet.  (See  diagram  "Fourth  Revision") . 

FENDER  UNWATERED  AND  PIER  COMPLETED:  On  November  27,  1934,  the 
pier  area  within  the  fender  wall  was  unwatered;  the  wall  was  found  to  be  remarkably 

144  Interior  of  fender  after  it  had  b« 

filled  with  tremie  concrete  to  e\e\ 
tion  — 3  5  and  then  pumped  out.  T 
vertical  shafts  of  the  eight  inspecti 
wells  can  be  seen 


THE      GOLDEN      GATE  BRIDGE 


tight,  and  very  little  pumping  was  needed  to  keep  the  bottom  dry.  The  shafts  of  the 
eight  inspection  wells  were  fitted  with  air  locks  to  permit  of  access  to  the  rock  surface 
under  air  pressure. 

Examination  of  the  foundation  within  these  wells  then  was  made  by  the  engineers 
and  by  Dr.  Andrew  C.  Lawson,  consulting  geologist.  In  addition,  pressure  tests  were 
made  by  hydraulic  jacks  braced  against  the  roof  formed  by  the  hemispherical  chambers. 
It  was  concluded  that  the  foundation  rock  was  adequate  in  all  respects  and  accordingly 
the  eight  inspection  chambers  and  shafts  were  filled  with  concrete. 

Within  the  open  cofferdam  formed  by  the  fender  ring  and  the  concrete  seal,  forms 
for  the  pier  proper  were  built.  On  January  3,  193  5,  the  pier  had  been  concreted  to  its 
final  height,  elevation  44.  Quantities  involved  in  the  south  pier  construction  were  as 
follows: 

Concrete  in  pier  and  fender,  cubic  yards   130,000 

Reinforcing  steel,  tons   647.9 

Rock  excavation  for  pier  and  fender,  cubic  yards   45,000 

All  underwater  concrete  was  deposited  through  tremies.  In  general,  each  position 
of  the  tremie  was  expected  to  deliver  to  an  area  of  900  square  feet.  A  concreting  rate  of 
100  cubic  yards  per  hour  was  common.  To  test  the  uniformity  of  tremie  concrete  at 
various  distances  from  the  tremie  pipe  cores  were  taken  with  a  diamond  drill.  These 
cores  showed  equal  distribution  of  coarse  aggregate  as  far  as  3  5  feet  from  the  tremie 
pipe  and  showed  a  compression  strength  of  more  than  4000  pounds  per  square  inch 
in  28  days. 

Concrete  was  batched  at  the  plant  of  the  Pacific  Coast  Aggregates  Co.  near  the 
bridge  site  and  was  delivered  by  trucks  that  mixed  in  transit.  All  concrete  placed  in 
fender  and  pier  contained  7  sacks  of  cement  ( 1  %  barrels)  per  cubic  yard. 

High-silica  cement  was  selected,  and  the  results  justified  this  choice  because  there 
was  decided  advantage  in  the  workability  of  the  concrete  where  large  tremie  pours  were 
made.  Tests  indicated  that  the  cement  would  show  a  high  degree  of  resistance  to 
sea  water. 

TOWER  ERECTION 

Fabricated  steel  was  shipped  from  the  contractor's  plants  at  Pottstown,  Pa.,  and 
Steelton,  Pa.,  by  rail  to  Philadelphia  and  thence  by  water  via  the  Panama  Canal  to 
Alameda.  There  it  was  unloaded  and  stored  until  required  at  the  site.  Steel  was  delivered 
to  the  erector  in  barge  loads  of  about  500  tons  each,  which  was  the  limit  of  storage  at 
the  tower  pier.  An  8  5  ton  stiffleg  derrick,  with  a  100  foot  boom,  unloaded  the  barges 
and  rehandled  the  steel  as  necessary  to  serve  the  erection  traveler. 

Preparation  of  the  pier  top  to  receive  the  tower  base  slabs  was  a  part  of  the  work 
included  in  the  tower  contract.  The  specifications  required  the  top  surface  of  the 
concrete  under  the  tower  base  to  be  ground  to  a  level  plane.  This  was  done  with  a 
carborundum  grinding  wheel  mounted  on  a  trolley.  The  trolley  supporting  bridge  itself 


146 


was  arranged  to  move  on  rails  accurately  leveled.  With  this  equipment  the  bearing  area 
under  each  tower  shaft,  amounting  to  about  1200  square  feet,  was  finished  to  the 
required  level  plane  with  variations  of  less  than  one-thirty-second  of  an  inch.  As  soon 
as  the  tops  of  the  pier  under  the  bearing  plates  had  been  surfaced,  the  base  plates  were 
set  in  a  thick  coating  of  freshly  applied  red  lead  paste.  By  varying  the  thickness  of  this 
red  lead  cushion,  the  plates  were  set  to  an  accuracy  of  .003  inch.  After  the  plates  had 
been  set,  the  steel  dowels,  4  feet  6  inches  long  and  6  ^4  inches  in  diameter,  were  set  in 
holes  provided  in  the  top  of  the  pier  and  grouted  in  position. 

The  erection  traveler  comprised  two  steel  trusses  79  feet  long  and  33  feet  deep 
extending  transversely  to  the  bridge.  They  were  spaced  28  feet  apart  and  joined 
together  with  suitable  cross  bracing  and  struts.  This  traveler  supported  two  stiffleg 
derricks,  each  of  85  ton  capacity  equipped  with  90-foot  booms.  Provision  was  made  in 
the  tower  shafts  to  support  the  travelers  at  predetermined  elevations  about  3  5  feet 
apart.  Preparatory  to  raising  the  traveler  from  one  position  to  the  next,  two  beams  were 
placed  across  the  uppermost  tower  sections,  one  above  each  end  of  the  traveler.  Each 
end  of  these  beams  was  equipped  with  four  sheaves  and  these  with  four  corresponding 
sheaves  at  the  lower  four  corners  of  the  traveler,  were  rove  with  one  inch  wire  rope 
leading  to  the  hoisting  engines  on  top  of  the  pier. 

The  derricks  were  independently  operated  by  two  electric  motor-driven  four-drum 
hoists,  located  at  the  base  of  the  tower.  Each  derrick  had  its  own  raising  gang  and  electric 


The  San  Francisco  Pier 
completed  and  prepara- 
tions being  made  for 
erection  of  the  San 
Francisco  Tower 


147 


Erecting 
the  Marin 
Tower 


signaling  system  for  transmitting  hoisting  signals  from 
the  derrick  to  the  engineer  below. 

As  soon  as  the  steel  erection  had  reached  a  height  of 
200  feet,  the  connections  were  made  to  the  anchorage 
angles  projecting  from  the  top  of  the  pier.  These  connec- 
tions involved  the  pre-stressing  of  the  angles  in  tension  to 
a  maximum  of  105,000  lbs.  per  angle,  then  drilling  holes 
from  the  solid  in  the  tower  webs,  after  which  the  connec- 
tions were  riveted. 

It  was  found  that  almost  perfect  bearing  between  the 
milled  surfaces  could  be  secured  by  proper  manipula- 
tion. Often  this  consisted  merely  in  striking  the  tops  of 
the  sections  with  a  pile  driver.  In  some  cases  heated  struc- 
tural hitches  were  applied  to  the  two  sections  so  that  they 
could  be  drawn  together  as  the  hitches  cooled.  Riveting 
was  permitted  when  the  opening  of  the  sections  was 
reduced  to  .006  inch  or  less,  but  it  was  found  that  after 
riveting  had  started  the  openings  were  closed  under  the 
vibration  and  heat  of  the  riveting  process. 

Rivets  in  vertical  seams  were  not  driven  until  all 
horizontal  joints  below  had  been  riveted.  There  were 


CONSTRUCTION 


about  600,000  field  driven  rivets  in  each 
tower.  The  rivets  were  heated  in  coal-burn- 
ing forges  located  on  scaffolds  outside  the 
tower  and  passed  to  crews  within  the  tower 
by  pneumatic  rivet-passers  through  holes 
6  J/2  inches  in  diameter  and  left  in  the  tower 
webs  for  that  purpose. 

Special  provisions  were  made  for  the 
safety  of  the  men  during  the  erection.  Every 
man  was  required  to  wear  a  hard  hat  to 
minimize  head  injuries  from  falling  objects. 
Because  of  the  confined  space  within  cells, 
extra  precautions  were  taken  against  lead 
poisoning.  This  ailment  was  suspected  in 
several  workmen  and  as  soon  as  its  likelihood 
was  discovered,  all  men  were  examined 
physically  every  two  weeks  and  blood 
counts  taken.  All  riveters  were  required  to 
wear  respirators,  and  provisions  made  so 
that  hands  could  be  kept  clean  to  prevent 
hand  to  mouth  infection.  As  a  result  of  this 
experience  on  the  Marin  Tower,  the  paint 


THE      GOLDEN      GATE  BRIDGE 


on  the  splices  of  the  San  Francisco  Tower,  then  in  the  process  of  fabrication,  was 
changed  from  red  lead  to  iron  oxide.  It  is  believed  that  the  erection  of  the  two  towers, 
involving  44,000  tons  of  steel  without  a  fatal  accident,  established  a  noteworthy  record. 

In  accord  with  the  program  and  for  reasons  previously  explained,  the  Marin  Tower 
was  erected  first  and  by  the  placing  of  the  saddles  on  its  top  in  November,  1934,  was 
then  completed  in  readiness  to  receive  the  cables. 

The  completion  of  the  San  Francisco  Pier  on  January  8,  193  5,  found  the  steel 
erector  ready  to  begin  the  erection  of  the  San  Francisco  Tower.  A  working  platform 
and  unloading  derrick  had  been  erected  on  the  outward  side  of  the  fender.  Grinding  of 
the  bearing  surfaces  was  rushed  by  working  double  shift  and  every  possible  expedient 
was  used  to  accelerate  the  construction  of  this  unit  of  the  work.  A  bonus  agreement  had 
been  entered  into  between  the  District  and  the  contractor,  since  the  early  completion 
of  the  San  Francisco  Tower  would  hasten  the  date  of  opening  of  the  bridge. 

The  same  traveler  and  other  equipment  used  on  the  Marin  Tower  were  used  in  the 
erection  of  the  San  Francisco  Tower.  The  tower  was  erected  ready  for  the  cable  con- 
tractor on  June  28,  1935. 


While  the  San  Francisco  Anchorage  and  Tower  were  progressing,  work  was  also  being  done  on  the  Presidio 
Approach  Road.  A  portion  of  the  Low  Viaduct  can  be  seen  in  the  left-background  and  the  High  Viaduct  piers 

can  be  seen  in  the  center-background 


CONSTRUCTION 


CABLE  CONSTRUCTION 

The  cables  are  the  largest  built  to  date.  Each  of  the  two  cables  is  thirty-six  and 
three-eighths  inches  in  diameter  (over  wrapping  at  a  distance  from  the  cable  bands) 
and  7650  feet  in  length  between  the  centers  of  the  eye-bar  pins  at  opposite  anchorages. 
Each  cable  is  made  up  of  27,572  parallel  wires  distributed  into  61  strands.  The  great 
lengths  of  spans,  combined  with  certain  unique  weather  conditions  encountered  at  the 
site,  introduced  new  experiences  in  cable  construction. 

At  the  ends  of  the  side  spans,  the  cables  are  maintained  at  a  constant  elevation  by 
means  of  tie-downs  instead  of  bent  or  pier  supports.  The  cables  terminate  in  anchorages 
of  the  gravity  type,  each  strand  being  held  at  the  end  by  a  cast  steel  strand  shoe  pinned 
between  a  pair  of  heat-treated  eye-bars. 

The  unloaded  position  of  the  cable  required  that  the  main  saddles  on  the  tower 
tops  be  set  shoreward  from  their  final  positions  a  distance  of  5  ft.  6  in.  in  the  case  of  the 
San  Francisco  Tower  and  3  ft.  7  in.  for  the  Marin  Tower.  This  was  accomplished  by 
having  temporary  brackets  on  the  tower  tops  to  support  the  overhanging  portions  of 
the  saddles.  Rollers  under  each  saddle  permitted  the  towers  to  be  jacked  back  toward 
the  shore  as  the  application  of  the  dead-load  deflected  them  toward  the  main  span.  Erecting  fooc-w>ik 


for  footwalks  and  for 
cable  spinning 


a  large  opening  was  Since  no  permanent  supports  were  provided  at  the  splay  castings,  it  was  necessary 

left  in  each  shaft  of  .  .  .  1  -       1     -      1       1  1        1  ■   -  -l     11      e    1  ■ 

the  Pylons  to  give  room     to  provide  temporary  bents  to  support  these  in  their  dead  load  position  until  all  or  this 
load  had  been  applied. 

Cable  construction  was  marked  by  several  innovations  in  design  and  erection 
practice. 

Prior  to  the  turning  over  of  the  San  Francisco  Tower  to  him,  the  cable  contractor 
had  been  proceeding  with  such  preparatory  field  work  as  could  be  done  without  inter- 
fering with  other  contractors.  This  preliminary  work  included  erection  of  platforms 
on  both  anchorages  and  platforms  and  equipment  on  top  of  the  Marin  Tower.  While 
this  work  at  the  site  was  in  progress  the  reeling  plant  at  California  City  was  being 
constructed  and  made  ready  for  service.  The  tower  contractor  and  the  cable  contractor 
worked  in  close  cooperation  on  the  top  of  the  San  Francisco  Tower  during  the  closing 
days  of  its  erection  prior  to  turning  it  over  to  the  latter. 

152 


CONSTRUCTION 


WIRE  HANDLING:  The  cable  wire  was  drawn  and  galvanized  in  the  New  Jersey 
plants  of  the  John  A.  Roebling's  Sons  Company,  covered  with  amorphous  wax  to 
prevent  deterioration  of  the  galvanizing,  and  shipped  by  boat  to  the  reeling  plant  at 
California  City.  This  plant  is  located  on  deep  water  in  San  Francisco  Bay,  which 
facilitated  the  delivery  from  eastern  seaports  and  also  shipment  of  reels  of  wire  to  the 
bridge  site.  Boats  docking  at  the  wharf  were  speedily  unloaded  and  the  coils  of  wire 
stored  in  the  600  ft.  x  100  ft.  building  which  had  been  erected  for  storage  and  for 
housing  the  reeling  plant.  A  total  of  1 17,000  coils  were  stored  in  this  manner.  A  machine 
and  blacksmith  shop  at  the  south  end  of  the  building  was  used  for  maintenance  of 
reeling  and  cable  spinning  equipment.  All  swifting,  splicing,  de-waxing  and  reeling  to 
intermediate  reels  was  done  on  the  main  floor.  A  platform  raised  above  the  level  of  this 
floor  was  used  for  reeling  from  intermediate  to  big  reels.  Various  movable  and  fixed 
overhead  cranes  were  located  throughout  the  mill  to  handle  and  move  coils  and  reels. 

Wire  was  received  at  the  plant  in  coils  5  feet  in  diameter,  125  to  250  loops,  and 
weighing  200  to  400  pounds.  All  coils  were  identified  with  the  official  inspection  seal 
and  also  marked  "right"  or  "left"  according  to  the  way  they  were  coiled. 

Coils  were  taken  from  storage  piles  to  thread-presses,  where  free  ends  were  cleaned, 
cut  square  and  threaded  for  a  length  of  7/$  in.  at  5  500  pounds  pressure,  the  wire  being 
slightly  flattened  along  the  thread  to  prevent  rotation  in  the  nipple.  After  threading, 
coils  were  sent  to  the  unwinding  swifts  according  to  their  marking,  dropped  over  the 
swift,  and  the  free,  front  end  of  the  coil  spliced  to  the  rear  end  of  the  previous  coil  on 
that  swift.  The  swifts  were  horizontal  wheels,  5  feet  in  diameter,  with  basket  frames 
attached,  set  on  vertical  shafts  that  rotated  and  unwound  the  coils  when  intermediate 
reelers  were  set  in  motion.  Tension  brakes  on  each  swift  prevented  coasting  when  the 
reeler  was  stopped.  Twenty  swifts,  set  in  a  V  formation,  prevented  wire  leaving  one 
swift  from  fouling  wire  from  swifts  ahead  or  behind. 

The  ends  of  the  coils  were  spliced  together  with  nipples,  four  nipple  presses  being 
located  convenient  to  the  swifts.  The  rear  end  of  the  unwound  coil  was  brought  to  the 
front  or  operating  end  of  the  nipple-press  where  it  was  locked  in  position  between  the 
nipple-press  dies.  The  nipple  was  then  placed  a  measured  distance  upon  this  end.  The 
front  end  of  the  following  coil  was  placed  in  the  opposite  end  of  the  nipple  until  the  ends 
butted.  The  nipple  was  then  pressed  on  the  wire  under  5  500  pounds  pressure,  the  splice 
rotated  60°  and  given  an  additional  press.  The  splice  was  then  removed  from  the  press 
and  examined.  A  total  of  117,000  splices  was  made  during  reeling,  of  which  11,000  or 
9.4%  were  tested,  an  average  strength  of  6820  pounds  being  obtained.  Every  hour  the 
inspector  on  duty  would  cut  out  a  splice  at  each  press  and  test  it.  If  a  splice  failed  to  meet 
specifications  the  press  was  adjusted  until  satisfactory  splices  were  produced.  Test 
splices  were  cut  out  about  12  inches  each  side  of  the  nipple  for  testing. 

After  leaving  the  nipple  press  the  wire  was  run  through  a  hot  water  de-waxing  tank, 
melting  the  wax  as  the  wire  proceeded,  the  excess  wax  being  removed  by  rubber 
scrubbers.  From  the  de-waxing  tank  the  wire  was  reeled  upon  5 -foot  diameter  inter- 


153 


THE      GOLDEN      GATE  BRIDGE 


Erecting  the 
storm  system 


mediate  reels,  twenty  in  number,  also  set  in  V  formation  to  correspond  to  the  swifts, 
one  swift  always  being  connected  to  the  same  reeler.  The  wire  was  reeled  evenly  upon 
the  reels  by  means  of  a  fleeter  that  moved  across  the  surface  of  the  reel  as  the  reel  rotated. 
After  10  to  14  coils  were  put  on  a  reel,  it  was  stopped  at  a  convenient  splice,  the  splice 
cut  out  and  the  full  intermediate  reel  lifted  to  the  big  reeling  platform.  An  empty 
intermediate  reel  was  set  in  place  and  reeling  again  started. 

The  intermediate  reels  set  upon  the  platform  were  placed  upon  vertical  unreeling 
machines  to  be  wound  upon  a  large  reel.  Unreeling  from  the  intermediate  reels  was  done 
by  tension  exerted  by  pulling  the  wire  on  to  the  large  reels,  the  intermediate  unreeling 
machine  being  motor-braked  to  prevent  coasting.  Large  reels  were  6  feet  in  diameter, 
3  feet  wide  with  9  inch  flanges  to  hold  the  wire  on  the  reel.  The  wire  was  fed  uniformly 
to  the  reels.  Six  large  reeling  machines  were  installed  on  the  platform,  five  being  in 
constant  use  and  one  in  reserve  for  possible  breakdown.  As  soon  as  an  intermediate  reel 
was  emptied,  a  full  one  was  substituted,  the  free  wire  end  spliced  to  the  free  end  on  the 
large  reel  and  reeling  continued.  Two  nipple  presses  handled  all  the  pressing  on  the 
platform.  From  41  to  46  coils  of  wire  were  reeled  upon  the  large  reels.  Reeled  wire  was 
then  covered  with  waterproof  paper  and  shipped  to  the  bridge  site  by  barge. 

Wrapping  wire  for  the  cable  was  handled  in  the  same  manner  except  that  the  coils 
were  spliced  to  each  other  by  electric-microwelding  instead  of  nipples.  The  ends  to  be 
welded  were  gripped  in  vises  and  butted  together,  the  microweld  adjusted  and  the 
welding  current  passed  through  the  wires,  automatically  welding  the  ends. 

The  welded  splice  was  then  removed,  clamped  in  an  annealer  attached  to  the  welding 
machine,  heated  to  1300°  F.  and  allowed  to  anneal.  After  annealing,  the  weld  was  filed, 
cleaned,  polished  and  painted  and  reeled  through  the  de- waxing  tank  to  the  inter- 
mediate reels. 


CONSTRUCTION 


FOOTWALKS  AND  STORM  SYSTEM:  The  footwalk  ropes  were  spread  out 
across  the  width  of  the  walk  so  that  they  effectively  supported  the  transverse  planking 
of  redwood  without  the  assistance  of  heavy  cross  beams  or  stringers.  To  facilitate 
erection  the  footwalk  was  made  up  in  panels  about  ten  feet  in  length,  the  transverse 
boards  being  nailed  to  longitudinal  spacer  boards.  Every  tenth  panel  embodied  a  rigid 
steel  underframe  which  extended  the  full  width  of  the  walk.  Each  such  frame, 
consisting  of  channel  cross-beams  connected  by  light  floor  trusses  and  braced  laterally 
by  diagonal  rods,  served  as  the  rigid  leading  panel  of  a  train  of  ten  panels  which  was 
erected  as  a  unit  by  assembling  and  sliding  down  the  ropes.  The  rigid  panel  also  provided 
the  stiff  cross-members  for  attaching  storm  ropes,  cross  bridges,  and  the  ties  between 
the  footwalk  and  the  tramway  support  ropes.  Directly  under  the  main  cable  the  floor 
of  the  footwalk  consisted  of  wire  mesh. 

Overhead,  two  ropes  supported  the  pipes  to  which  the  tramway  rope  sheaves  were 
affixed.  These  pipes  were  spaced  at  about  200  foot  intervals  and  at  each  pipe  location  the 
tramway  support  ropes  were  connected  to  the  footwalk  by  wire  rope  ties. 

The  main  footwalk  ropes  were  spliced  by  means  of  special  sockets  near  the  center 
of  the  main  span  and  were  discontinuous  at  the  towers  and  at  the  splay  bents.  At  the 
latter  points  and  on  either  side  of  the  main  saddles  they  were  socketed  and  connected  to 
transverse  girders  by  means  of  threaded  rods  which  enabled  them  to  be  adjusted  to  the 
proper  sag  before  the  erection  of  the  footbridge  panels,  and  permitted  adjustment  of 
the  footbridge  elevation  as  the  sus- 
pended structure  was  being  erected.  At 
the  splay  bents,  a  group  of  seven  ropes 
connected  to  each  end  of  the  transverse 
girder  transmitted  the  stress  to  eye-bars 
embedded  in  the  main  anchorage  con- 
crete. Similarly,  at  the  main  saddles,  a 
group  of  seven  ropes  on  each  end  of  the 
girders  passed  over  a  temporary  saddle 
and  transmitted  the  pull  of  the  main 
ropes  around  the  main  saddles. 

At  the  center  of  the  main  span  a 
structure  of  considerable  weight  was  re- 
quired to  provide  a  crosswalk,  the  fram- 
ing for  the  transfer  station  above  the 
walk,  and  the  storm  system  connections 
beneath  the  footwalk.  At  four  other 
points  in  the  main  span  and  at  one  point 
in  each  side  span,  light  frames  or  struts 
provided  the  support  for  intermediate 


At  the  upper-left,  the  overhead  catenary  ropes  are  seen  with  pipe  spreaders  on  which 
mounted  the  split  sheaves  which  will  support  the  tramway.  Below  the  footwalk  are 
lower  ropes  of  the  storm  system 


are 
the 


THE      GOLDEN      GATE  BRIDGE 


The  storm  system  was  of  unique  design.  The  upper  part  consisted  of  ropes  running 
beneath  the  sides  of  each  footwalk  and  tied  to  it  at  about  one  hundred  foot  intervals. 
At  the  center  of  the  main  span  these  ropes  engaged  the  lower  framework  of  the  transfer 
station.  Below  this  rope  and  fastened  to  it  was  a  triangular  bracing  system  which 
transmitted  wind  stresses  to  the  towers  at  two  levels— the  base  of  the  tower  and  about 
halfway  between  the  base  and  the  top.  Four  struts  in  the  main  span  tied  the  vertical 
planes  of  bracing  together  and  participated  in  the  stresses  induced  in  the  transverse 
diagonal  systems.  Thus  three  more  or  less  distinct  systems  made  up  the  whole  of  the 
storm  system:  first,  the  ropes  running  beneath  and  approximately  parallel  to  the  side 
of  the  footwalks;  second,  the  lower  diagonal  system  including  the  transverse  struts;  and 
third,  the  overhead  tramway  system  with  its  vertical  ties  to  the  walk.  The  bracing  as  a 
whole  was  very  effective  against  high  velocity  winds  blowing  from  any  direction. 

The  first  step  in  the  erection  of  the  footwalks  began  in  the  side  spans  with  the  raising 
of  skylines  between  the  anchorages  and  main  tower  tops.  A  traveling  carriage  supported 
on  these  skylines  hauled  the  footwalk  ropes  from  reels  mounted  at  the  splay  bents,  to 
the  tower  tops,  where  connections  were  made  to  the  transverse  footwalk  girders.  All  of 
the  side  span  footwalk  ropes  were  in  this  manner  pulled  to  the  tower  tops  (and  left  in 
slacked  position)  before  the  erection  of  the  main  span  footwalk  ropes  began. 

In  the  main  span  the  ropes  were  unreeled  from  a  barge  as  it  was  towed  from  one 
tower  to  the  other.  The  raising  of  the  ropes  was  accomplished  by  means  of  the  ropes 
which  had  previously  been  used  as  skylines  for  the  erection  of  the  side  span  ropes.  The 
ends  of  these  skyline  ropes  were  passed  over  the  tower  tops  and  carried  down  to  the  base 


CONSTRUCTION 


of  their  respective  tower  legs.  When  the  ends  of  the  rope  to  be  raised  had  been  brought  to 
the  bases  of  the  towers,  each  was  clamped  to  one  of  the  skyline  ropes  and  by  them  hauled 
to  their  respective  tower  tops.  Both  ends  were  raised  simultaneously,  all  operations  being 
controlled  by  portable  radio.  Coast  Guard  cutters  stopped  all  vessels  going  in  and  out  of 
the  harbor  during  the  raising  operation,  which  lasted  about  twenty  minutes  for  each 
rope. 

The  footwalk  decking  was  placed  by  assembling  the  10-foot  long  panels  into  trains 
about  100  feet  in  length.  The  side  span  trains  were  assembled  at  the  anchorages  and 
hauled  upward,  while  the  main  span  trains  were  assembled  at  the  tower  tops  and  slid 
downward  toward  the  center  of  the  main  span. 

Due  to  the  exceedingly  arduous  climbing  required  of  the  men  who  had  to  move 
along  the  footwalks,  a  man-hauling  rope  was  provided  on  one  footwalk  and  that  foot- 
walk  was  made  slightly  wider  than  the  other  walk  to  provide  room  for  the  passage  of 
the  men  who  made  use  of  the  rope.  This  rope  was  placed  just  above  the  stationary  hand- 
rail rope  and  moved  at  such  a  rate  that  the  climber  could  take  hold  of  it  and  be  assisted 
in  climbing  the  footwalk  at  a  comfortable  rate  of  speed. 

SPINNING  FACILITIES:  Tramway  ropes,  the  function  of  which  was  to  haul  a 
spinning  carriage  from  the  anchorage  to  the  center  of  the  main  span  and  return, 
traveled  upon,  and  were  supported  by  "split"  sheaves,  which  in  turn  were  supported 

by  the  overhead  catenary.  Return  sheaves  for  the  tramway  ropes  could  have  been  one  of  the  four 

located  at  midspan  except  that  the  installation  of  the  necessary  supporting  framework  sheave  spinning^ 

would  have  added  materially  to  the  weight  already  concentrated  at  that  location.  For  bights  of  wire 


The  spinning  plant  at      this  reason  the  cross-over  and  return  sheaves  were  placed  at  the  farther  tower  tops.  Such 

the  Marin  Anchorage  .  .  ■        i  1  1  1  •       ■  1 

a  system  can  be  used  conveniently  only  when  the  spinning  program  contemplates 
stringing  wire  for  each  cable  alternately.  Each  of  the  four  ropes  required  was  driven  by 
an  electrically  powered  drum  located  on  the  anchor  blocks  and  a  counterweight  was 
inserted  in  the  anchorage  cross-overs  for  the  purpose  of  maintaining  a  constant  tension 
on  the  rope.  Each  rope  was  carried  over  the  tower  top  on  two  groups  of  sheaves  mounted 
on  frames  located  above  the  ends  of  the  saddles.  The  support  for  these  frames  was  so 
designed  that  the  group  of  sheaves  could  be  shifted  laterally  to  make  the  spinning 
carriage  pass  directly  over  the  strand  and  live  wire  sheaves  into  which  the  wires  were 
to  be  deposited,  or  moved  out  of  the  way  during  the  adjustment  of  the  strands. 

The  principal  equipment  at  each  anchorage  consisted  of  the  unreeling  machines, 
the  wire  counterweights,  the  tramway  drive  engines,  the  tramway  counterweights,  the 
splice  presses,  a  thirty-ton  derrick  used  principally  for  handling  reels  of  wire  and  a 
ten-ton  derrick  for  assisting  in  operations  carried  on  in  the  vicinity  of  the  splay  bent. 
When  the  spinning  operation  had  developed  to  where  three  bights  of  wire  were  to  be 
carried  by  each  carriage,  six  unreeling  machines  were  operated  at  each  anchorage.  These 
machines  were  hydraulically  driven  and  were  capable  of  rapid  acceleration  or  decelera- 
tion at  the  will  of  the  operator.  As  the  wire  was  fed  from  the  reels  it  passed  through  a 
counterweight  system  and  the  unreeling  operator,  by  observing  the  position  of  the 


158 


CONSTRUCTION 


counterweight,  speeded  up  or  slowed 
down  the  reel  to  conform  to  the  rate  at 
which  the  spinning  wheel  progressed. 

On  the  tower  tops  a  structural 
frame  over  each  saddle  supported  the 
tramway  sheaves  and  the  hydraulic 
lifting  jacks  which  here  handled  the 
completed  strands.  There  were  two 
such  jacks,  of  eighty  tons  capacity, 
provided  on  each  tower  top  and  these 
were  shifted  to  either  cable  as  required 
by  the  strand  adjusting  operations. 
Rollers  above  the  jacks  permitted  them 
to  be  shifted  laterally  for  moving  the 
strands  from  the  spinning  saddles  to 
their  positions  in  the  permanent  sad- 
dles. At  their  lower  ends,  the  jacks  were 
connected  to  a  curved  lifting  girder 
which  transmitted  the  pull  of  the  jacks 
to  the  strand  through  a  series  of  special 
grommets  and  lifting  bands. 

STRAND  ARRANGEMENT:  Heretofore,  all  large  bridge  cables  of  parallel  wire 
have  been  constructed  with  the  original  hexagon  (which  makes  up  the  shape  of  the  cable 
cross-section  before  compacting)  placed  with  a  straight  side  at  the  bottom.  In  other 
words,  the  strands  were  placed  in  the  cable  so  as  to  lie  in  horizontal  and  diagonal  rows. 
The  Golden  Gate  cables  were  constructed  with  a  corner  of  the  hexagon  at  the  bottom 
and  with  two  sides  vertical  so  that  the  strands  lay  in  vertical  and  diagonal  rows.  There 
were  several  advantages  derived  from  this  arrangement  for  these  very  large  cables. 

With  the  conventional  arrangement  of  flat  bottom  hexagon,  serious  difficulties  are 
encountered  at  the  saddles.  Since  it  is  practically  impossible  to  place  strands  in  the  saddle 
and  preserve  their  circular  cross-section,  the  horizontal  saddle-dimension  of  any  row 
of  strands  must  be  increased  with  a  corresponding  decrease  in  vertical  dimension. 
Another  difficulty  is  that  it  is  impracticable  to  hold  fillers  on  the  top  and  center  of  the 
strands  in  the  row  below  that  in  which  the  strands  are  being  placed.  If  these  fillers  are 
omitted,  there  remain  voids  into  which  the  wires  ultimately  slip  causing  the  cable  to 
slump  in  the  saddle.  This  action  might  not  become  complete  until  after  the  entire  load 
is  on  the  structure  and  thus  bring  about  a  condition  of  higher  stress  in  the  lower  wires 
of  the  cable.  The  strand  arrangement  adopted  has  a  further  advantage  in  that  the 
operation  of  compacting  to  a  circular  cross-section  is  facilitated  because  there  is 
involved  a  minimum  vertical  displacement  of  wires. 


The  spinning  carriage 
has  just  passed  over  the 
top  of  tower  with  three 
bights  of  wire  (6  wires) 


159 


THE      GOLDEN      GATE  BRIDGE 


With  the  hexagon  rotated  it  is  not  necessary  to  try  to  force  a  certain  number  of 
strands  into  a  given  horizontal  row  and  the  fillers  are  much  more  easily  held  near  their 
correct  location.  The  new  arrangement  of  strands  worked  out  satisfactorily.  No  fillers 
had  to  be  omitted  and  the  strands  were,  at  all  stages  of  construction,  very  near  to  their 
correct  positions  in  the  saddle. 

Another  distinct  advantage  gained  from  the  chosen  orientation  of  the  hexagon  was 
derived  from  the  fact  that  during  construction  it  was  possible  to  keep  separators 
between  the  vertical  rows  of  strands  at  intervals  along  the  length  of  cable,  and  to  use 
substantial  cable  formers  which  preserved  the  shape  of  the  cable  in  spite  of  non-uniform 
temperature  conditions.  The  separation  between  the  rows  provided  ventilation  tending 
to  keep  the  various  strands  at  a  more  uniform  temperature  during  the  day  and  resulted 
in  a  more  rapid  equalization  of  temperature  at  night.  Only  one  difficulty  of  any 
consequence  was  encountered  with  this  arrangement  of  the  hexagon.  When  only  a  few 
strands  had  been  completed  and  the  formers  could  not  be  used,  no  strand  was  supported 
directly  from  the  side  by  any  other  strand,  so  that  a  very  slight  wind  caused  the  strands 
to  override  one  another.  This  made  adjustment  difficult  until  sufficient  strands  were  in 
place  to  support  the  relatively  heavy  formers. 

To  further  facilitate  compacting  to  a  circular  cross-section,  certain  strands  at  or 
near  the  corners  of  the  hexagon  were  made  smaller.  Although  this  expedient  was  of 
some  value  in  helping  to  round  up  the  cable  it  had  several  disadvantages  from  a  practical 
Cable  formers  with     standpoint.  There  was  a  certain  loss  of  economy  in  the  design  of  the  anchorages;  an 

vertical  separators  kept         .  .  .  ...... 

strands  in  vertical  rows      increase  in  the  cost  of  erection  due  to  the  varying  size  of  spinning  saddles,  compacting 


CONSTRUCTION 


tongs  and  other  tools  required;  and  some  small  nuisances  in  the  planning  and  execution 
of  strand  adjustment.  All  observations  on  strand  adjustments  and  much  of  the  adjusting 
were  done  during  the  early  morning  hours  to  secure  uniform  temperature  conditions. 

SPINNING  THE  CABLES:  The  setting  of  the  first  or  guide  wire,  required  special 
accuracy  and  care.  Four  wires  to  serve  as  guide  wires  were  hauled  across  the  west  walk 
from  the  Marin  anchorage  and  one  was  selected  for  the  sag  observations.  In  the  main 
span,  a  levelman  located  in  the  west  leg  of  the  San  Francisco  Tower  foresighted  through 
a  handhole  to  a  lighted  target  located  in  the  same  corresponding  handhole  in  the  Marin 
Tower.  He  then  directed  the  setting  of  an  inverted  rod  under  the  guide  wire  at  the 
center  of  the  main  span.  The  instrument  man  directed  the  movements  of  the  rod  target 
by  telephone.  Telephones  were  used  also  to  convey  to  the  center  of  the  main  span,  the 
tower  verticality  readings  from  the  bases  of  the  tower  legs,  and  thermometer  readings 
from  the  tower  tops.  When  the  data  from  the  observations  had  been  assembled  at  mid- 
span  and  interpreted  by  means  of  the  sag  charts,  the  required  movement  of  the  wire  was 
made  at  the  tower  top  to  correct  the  sag. 

The  sags  for  side  span  guide  wires  were  observed  by  means  of  transits  located  on  the 
pylons  at  the  ends  of  the  side  spans.  A  target  located  near  the  tower  top  served  as  a 
foresight  to  establish  a  line  of  sight  which  was  parallel  to  the  side  span  chord.  The 
distance  between  the  guide  wire  and  the  line  of  sight  was  measured  by  an  inverted  rod 
held  on  the  guide  wire.  As  in  the  case  of  the  main  span  adjustment,  the  tower  leg  was 
plumbed  with  a  transit  and  temperature  readings  were  taken  at  three  points  along 
the  span. 

After  the  first  wire  on  the  west  walk  had  been  set,  the  other  three  were  adjusted  to 
identical  sags.  Two  of  these  were  then  removed  to  the  east  walk,  and  two  additional  ones 
hauled  out  on  each  walk  and  adjusted  to  the  same  length  as  the  original  four. 

The  procedure  for  setting  the  first  strand  of  the  west  cable  was  identical  to  that 
followed  in  setting  the  guide  wire,  but  for  setting  the  first  strand  of  the  east  cable  it 
was  felt  that  it  was  essential  to  secure  an  accurate  relative  elevation  between  the  two 
cables  rather  than  make  an  independent  setting.  In  order  to  accomplish  this  in  the 
simplest  manner,  the  main  span  sags  were  compared  by  setting  up  a  level  on  one  of  the 
footwalks  near  midspan  and  determining  the  difference  in  elevation.  The  difference  in 
span  for  the  two  strands  was  found  by  making  a  direct  determination  of  the  skew 
between  the  saddles  on  each  tower  top. 

For  the  side  span  setting  of  the  first  strand  of  the  east  cable,  the  same  logic  governed 
the  procedure.  The  difference  in  spans  between  the  east  and  west  sides  was  again  found 
by  means  of  the  transit  on  the  tower  top.  The  sags  for  both  the  east  and  west  sides  were 
observed  simultaneously  by  means  of  transits  at  the  pylons.  The  application  of  the 
sag-span  ratio  gave  the  correct  difference  in  sags  to  which  the  east  cable  had  to  be 
adjusted.  This  method  of  direct  comparison  eliminated  dependence  upon  two  of  the 
most  troublesome  observations,  namely,  temperature  and  tower  verticality. 


161 


The  transfer  station  The  most  radical  departure  from  previous  procedure  was  made  in  the  stringing 

at  1  Mai^Tspan* the  method.  Formerly  the  wires  were  strung  in  each  cable  by  the  use  of  two  wheels,  each 
carrying  one  bight  of  wire  so  that  four  wires  were  laid  in  the  cable  each  trip  of  the  two 
wheels.  In  this  case,  however,  four  traveling  carriages  were  used,  each  provided  (at  first) 
with  two  sheaves  to  carry  two  bights  of  wire.  Each  carriage  traveled  only  to  the  center 
of  the  main  span  where  it  met  another  bringing  wire  from  the  opposite  anchorage.  The 
bights  were  then  transferred  from  one  carriage  to  the  other  and  the  carriages  returned 
to  the  respective  anchorages  from  which  they  started.  By  means  of  this  system,  it  was 
possible  to  have  four  carriages  stringing  wire  at  one  time,  with  sixteen  wires  strung  in 
a  cycle,  as  compared  with  four  wires  by  any  previous  system.  The  workmen  became  so 
proficient  in  adjusting  and  putting  away  the  wires  that  it  was  later  found  practicable  to 
add  a  third  wheel  to  each  carriage  and  pull  six  wires  instead  of  four  so  that  production 
was  speeded  up  almost  six  times  over  what  would  have  been  possible  if  the  methods  used 
on  previous  bridges  had  been  employed.  Each  carriage  was  propelled  by  an  independent 
hauling  rope  so  that  in  case  of  a  mishap  to  one  tramway,  it  was  not  necessary  for  all 
wheels  to  stop.  Frequently  two  carriages  worked  while  repairs  were  made  on  a 
breakdown  affecting  the  other  two. 

Wire  stringing  was  conducted  alternately  on  each  walk.  When  the  maximum 
efficiency  had  been  attained,  three  days  of  stringing  was  required  to  complete  one  set-up 
of  four  strands.  Likewise,  this  was  about  the  minimum  time  required  to  put  the  strands 
away  in  the  saddles,  adjust,  and  prepare  for  a  new  set-up  on  the  opposite  walk.  Thus  the 
two  sets  of  operations  dovetailed  very  satisfactorily  and  justified  thoroughly  the 
contractor's  programming  and  plant  layout  based  on  such  a  plan.  The  essential 
departure  from  former  systems  and  which  made  such  a  program  possible,  was  that  four 
carriages  could  be  operated  on  one  walk  instead  of  two  carriages  on  each  of  the  two 
walks.  Under  this  arrangement  it  is  noteworthy  that  the  four  carriages  operated 
continuously  without  interruption  for  strand  adjustment,  etc.,  and  the  same  spinning 

162 


CONSTRUCTION 


and  adjusting  crews  were  employed  continuously  on  the  same  work,  being  shifted  from 
one  cable  to  the  other. 

At  the  beginning  of  stringing,  when  each  carriage  carried  two  bights  of  wire,  two 
wheels  or  sheaves  were  mounted  side  by  side  on  either  side  of  the  carriage.  When  the 
three-bight  system  was  instituted  another  wheel  was  mounted  both  fore  and  aft,  and 
in  the  plane  of  the  hauling  rope,  making  four  wheels  on  each  carriage.  The  rear  wheel, 
as  determined  by  the  direction  of  travel  of  the  carriage,  was  utilized  to  pull  the  third 
bight  and  the  front  one  did  not  operate.  The  resultant  pull  of  the  three  bights  was  thus 
kept  in  the  plane  of  the  hauling  rope.  A  total  of  42  strands  of  the  122  was  strung  by  the 
two-bight  system  and  the  remainder,  or  80,  by  the  three-bight  system.  No  funda- 
mentally new  methods  were  developed  for  the  unreeling  of  the  wire.  The  unreeling 
machines  and  their  operation  in  conjunction  with  the  wire  counterweight  towers  were 
not  new  developments,  but  had  been  used  before.  The  stringing  of  two  and  later  three 
wires,  rove  simultaneously  on  each  strand  shoe  and  carriage,  was  an  innovation.  On  a 
typical  trip,  these  carriages,  traveling  at  a  maximum  rate  of  650  feet  per  minute,  would 
progress  from  the  anchorage  to  the  midspan  transfer  station  in  about  six  and  one-half 
minutes.  At  this  point,  the  bights  of  wire  would  be  transferred  from  one  carriage  to  the 
other.  This  was  a  manual  operation  requiring  one  minute.  The  transfer  having  been 
accomplished,  the  direction  of  travel  of  the  carriages  was  reversed  and  they  returned 
to  the  anchorages  from  which  they  started. 

The  adjustment  of  the  "dead"  or  standing  wires  in  any  given  span  followed  closely 
after  these  wires  had  been  laid  in  the  most  remote  support  of  that  span  and  the  "live"  or 
running  wires  were  adjusted  later  in  the  proper  span  sequence.  It  was  essential  in  order 
to  avoid  confusion,  that  each  of  the  three  wires  be  properly  placed  in  all  live  wire  sheaves 
and  dead  wire  hooks  and  that 
they  be  adjusted  in  proper  se- 
quence. To  insure  this,  quick 
drying  lacquer  was  sprayed  on 
the  running  reels  at  the  anchor- 
ages, one  of  the  wires  being  thus 
spotted  red,  another  green,  and 
the  third  left  unspotted. 

The  motive  power  for  ad- 
justing the  wires  was  provided 
by  moving  ropes  placed  on  the 
walk.  These  ropes,  placed  side  by 
side  to  form  a  group  of  four  at 
the  end  of  each  span,  extended 
about  100  feet  along  the  walk. 
They  were  actuated  by  electri- 
cally driven  drums  placed  be- 

Transferring  wire  from  one  spinning  car- 
riage to  the  other  at  the  center  of  the 
Main  Span.  The  spinning  carriages  shown 
have  only  2  sheaves  each.  Later,  2  more 
sheaves  were  added 


CONSTRUCTION 


neath  the  walk,  the  machines  being  remotely  controlled  by  the  adjusters  at  midspan.  On 
receiving  an  electric  light  signal  from  midspan,  a  workman  connected  the  proper  wire 
to  a  come-along  rope  by  means  of  a  link  consisting  of  a  short  wire  rope  with  a  come- 
along  gripping  device  attached  to  either  end.  The  operation  was  then  in  the  hands  of  the 
adjuster  at  the  center  of  the  span.  By  the  manipulation  of  his  control  buttons,  he  pulled- 
up  or  slacked-off  the  wire  until  it  had  attained  the  proper  sag.  An  electric  light  signal  to 
the  clamp-man  then  instructed  the  latter  to  make  the  wire  fast.  Because  of  the  length 
of  the  main  span  and  the  prevalence  of  fogs,  each  of  the  four  adjusters  was  in  telephonic 
communication  at  all  times  with  the  two  quarter-point  adjusters. 

The  first  twelve  or  eighteen  wires  in  any  strand  were  adjusted  parallel  to  a  guide 
wire  after  which  the  guide  wire  was  removed.  All  strands  were  opened  up  after  comple- 
tion to  check  the  quality  of  the  adjustment.  Any  wire  that  fell  outside  the  tolerance  for 
uniformity  of  sag  was  corrected  by  cutting  and  splicing  to  the  correct  length.  How- 
ever, very  few  splices  were  necessary.  The  specifications  required  that  with  all  wires 
hanging  free,  not  more  than  six  wires  of  the  entire  strand  should  lie  outside  of  a  group 
measuring  vertically  seven  inches  from  top  to  bottom. 

Splicing  together  the  ends  of  successive  reels  of  wire  at  the  anchorages  was  accom- 
plished by  means  of  hydraulic  presses  which  compressed  a  steel  nipple  tightly  over  the 
previously  swedged  ends  of  the  two  wires  to  be  joined.  For  occasional  splices  which  were 
necessary  at  points  along  the  footwalk,  the  common  die  cut  threads  and  screw  nipples 
were  used. 

After  the  spinning  of  a  set  of  strands  had  been  completed  and  they  had  been  opened 
up  for  inspection,  they  were  seized  at  five  foot  intervals  by  a  wrapping  of  about  three 
turns  of  heavy  adhesive  tape.  Below  the  splay  point  at  the  anchorages,  wire  seizings  were 
used.  The  strands  were  lifted  from  the  spinning  saddles  at  the  tower  tops  by  means  of  a 
pair  of  hydraulic  pulling  jacks  attached  near  either  end  of  the  curved  lifting  girder. 
Connection  between  the  strand  and  girder  was  made  by  means  of  a  series  of  galvanized 
lifting  straps  which,  with  some  intermediate  seizing  straps,  had  been  placed  in  the 
spinning  saddles  before  starting  to  lay  wires  in  the  strand.  After  all  of  the  wires  had 
been  placed  in  a  strand,  these  straps  were  bent  up  and  connected  to  the  lifting  girder 
through  a  turnbuckle  which  provided  for  adjusting  the  straps  to  a  uniform  tension.  The 
intermediate  seizing  bands  were  bent  up  over  the  strands  and  tightened  by  means  of  a 
special  device  operated  by  an  ordinary  hand  wrench.  The  strand  was  then  lifted  from 
the  spinning  saddle,  shifted  laterally  and  lowered  into  the  correct  position  in  the  main 
saddle.  When  movements  of  the  strand  were  no  longer  required,  the  projecting  portions 
of  the  lifting  and  seizing  straps  were  cut  off,  the  inaccessible  portions  being  left  beneath 
the  strand.  At  the  splay  bents,  where  the  deflection  of  the  cable  was  slight  and  the 
spinning  saddle  assembly  was  comparatively  short,  the  strand  was  seized  with  wire  and 
lifted  by  means  of  rope  grommets  attached  to  a  short  lifting  beam. 

During  spinning,  the  strand  shoe  at  the  anchorage  was  mounted  ahead  of  its  final 
position  on  a  cast  nickel-steel  strand  leg  which  held  the  strand  shoe  so  as  to  leave  one  side 


3ur  strands  are  shown  in 
'inning  position 


l65 


THE      GOLDEN      GATE  BRIDGE 


unobstructed  for  the  placing  of  the  loops  of  wire.  After  completion  of  the  placing  of 
wires  in  a  strand,  the  strand  leg  provided  the  link  between  the  strand  shoe  and  the 
pulling-jack  mechanism  by  means  of  which  the  end  of  the  strand  was  pulled  back  to 
its  correct  position  between  the  eye-bar  heads. 

For  adjusting  a  typical  set-up  of  four  strands,  movements  in  the  main  span  were 
made  by  shifting  two  of  them  over  each  tower  top.  In  the  side  span  those  strands  which 
required  no  shifting  at  the  adjacent  tower  top  were  adjusted  first  by  inserting  shims  in 
the  strand  shoes  at  the  anchorage.  After  two  strands  had  been  satisfactorily  adjusted  in 
the  main  span  they  in  turn  were  set  in  the  side  span.  It  appears  that  the  ideal  program  for 
adjusting  strands  is  to  attempt  to  set  them  slightly  high  during  the  daytime,  take  read- 
ings that  same  night  and  make  the  adjustments  the  following  day,  basing  the  movements 
at  the  saddles  and  the  shim  changes  on  values  computed  from  the  night  readings.  This 
method  is  satisfactory  provided  that  the  differential  sag-length  ratios  are  accurately 
known,  and  provided  the  computations  and  movements  are  carefully  supervised.  To 
insure  correct  results,  however,  the  settings  were  checked  on  a  succeeding  night  and 
further  changes  made  if  then  found  necessary.  Obviously  this  method  required  a  con- 
siderable length  of  time  and,  where  delay  might  impede  spinning  on  the  next  set  of 
strands,  it  was  more  desirable  to  bring  out  the  adjusting  crews  at  night  and  complete 
the  operation  in  a  single  shift.  Each  of  these  methods  was  used  at  different  times  on  the 
Golden  Gate  Bridge.  For  the  first  few  set-ups,  the  crews  worked  at  night  until  the 
accuracy  of  the  ratios  was  verified.  For  subsequent  set-ups  the  latter  method  was  used 
except  where  the  contractor  elected  to  adjust  at  night  to  avoid  possible  interruption  of 
the  spinning.  In  all,  52  of  the  122  strands  of  the  two  cables  were  adjusted  by  reading  at 
night  and  making  the  necessary  movements  during  the  following  day;  the  remainder, 
or  70  strands,  were  adjusted  by  night  crews. 

The  correct  position  of  a  strand  was  not  determined  by  tangency  with  the  strand 
beneath,  but  by  a  calculated  dimension  from  the  under  frame  of  the  cable  former, 
located  at  the  center  of  each  span.  Throughout  all  adjusting  operations,  an  effort  was 
made  to  avoid  a  flat  cable.  For  instance,  the  side  span  strands  were  pulled  up  from  one- 
sixteenth  to  one-eighth  of  an  inch  farther  than  the  necessary  sag  change  would  indicate 
after  experience  had  shown  that  this  closely  corrected  the  slight  drop  due  to  slumping 
when  the  seizing  bands  in  the  tower  saddles  were  cut. 

COMPACTING  AND  WRAPPING:  Six  compactors  were  used  to  squeeze  the  cable 
to  a  circular  cross-section.  Each  consisted  of  a  frame  which  surrounded  the  cable  and 
supported  a  battery  of  twelve  jacks  radially  directed  so  as  to  exert  a  force  normal  to  the 
surface  of  the  cable.  The  jack  assembly  was  supported  on  a  structural  steel  frame  which 
was  designed  to  travel  on  the  cable  on  large  wooden  spools.  The  frame  was  stationary 
for  three  moves  of  the  jacking  assembly  which  rode  on  tracks  on  the  frame.  After  the 
three  moves,  the  jacking  assembly  gripped  the  cable,  and  the  supporting  frame  was 
moved  ahead  to  a  new  position  in  readiness  for  three  more  moves  of  the  jack  assembly. 

1 68 


THE      GOLDEN      GATE  BRIDGE 


All  movements  of  the  assembly  were  made  by  means  of  hand-operated  cable  winches. 
Each  of  the  jacks  having  a  piston  diameter  of  5  7/&  inches  and  operating  under  a  maxi- 
mum pressure  of  6000  pounds  per  square  inch,  exerted  a  pressure  of  8 1  tons,  or  a  total  of 
972  tons  for  the  twelve  jacks  on  each  compactor.  The  shoes  contacting  the  surface  of 
the  cable  were  6  inches  wide  and  completely  surrounded  the  cable  so  that  the  total  con- 
tact area  was  about  678  square  inches.  Assuming  10%  friction-loss  in  compacting,  the 
resulting  maximum  unit  pressure  per  square  inch  of  contact  surface  would  be  2  5  80 
pounds.  After  the  start  of  operations,  it  was  found  that  little  further  compaction  was 
accomplished  after  the  fluid  pressure  in  the  jacks  had  exceeded  5000  pounds  per  square 
inch  and,  for  most  of  the  work,  this  pressure  was  used.  An  electrically  driven  pump  for 
supplying  the  fluid  pressure  accompanied  each  compactor,  being  moved  along  the  foot- 
bridge on  a  timber  sled.  Incorporated  in  the  compacting  unit  were  two  auxiliary 
hydraulic  jacks  which  tightened  the  seizing  bands.  The  cable  was  compressed  at  intervals 
of  three  feet,  which  therefore  was,  in  general,  the  seizing  band  spacing.  The  seizings 
consisted  of  galvanized  metal  straps,  two  inches  wide,  which  were  held  tightly  by  engag- 
ing the  ends  in  a  special  socket  and  wedge  device.  After  the  adjustments  under  working 
conditions  had  been  made,  each  compacting  machine  was  able  to  compact  204  lineal 
feet  of  cable  per  day  of  eight  hours. 


The  mean  diameter  after  compacting  was  close  to  36  1/16  inches  (at  the  seizing 
bands) .  Under  the  permanent  bands,  after  final  tightening,  the  mean  diameter  was  3  5  7/g 
inches. 


CONSTRUCTION 


As  soon  as  one  whole  span  of  either  cable  was  compacted,  it  was  immediately  meas- 
ured for  length.  All  measurements  were  conducted  at  night  and  by  two  independent 
field  parties.  The  band  spacings,  as  previously  computed  on  the  basis  of  theoretical 
lengths,  were  then  corrected  to  distribute  the  difference  found  between  actual  and 
theoretical  length,  which  was  small.  For  securing  the  correct  location  of  the  vertical 
axis  of  the  bands,  a  true  bottom  of  the  cable  was  located  at  night  after  the  cable  had 
assumed  a  uniform  temperature  throughout  its  cross-section. 

All  cable  bands  were  lowered  from  the  tower  tops  by  means  of  carriages  riding  on 
the  ropes  which  had  supported  the  tramway  during  the  spinning  operations.  For  the 
placing  of  cable  bands  and  suspenders,  and  the  jumping  of  the  wrapping  machines, 
these  ropes  served  as  high-lines  to  support  carriages  upon  which  were  mounted  chain- 
falls  for  lifting  and  transporting  the  moderate  loads  above  the  cables. 

The  band-bolts  were  tightened  to  a  high  stress  almost  immediately  upon  erection  of 
the  band.  The  specifications  called  for  a  stress  of  92,000  pounds  in  each  bolt.  In  antici- 
pation of  a  diminishing  stress  with  the  addition  of  dead  load,  the  bolts  were  tightened 
at  the  first  tightening  to  approximately  120,000  pounds  each.  The  final  tightening  was 
done  when  a  little  more  than  half  of  the  concrete  had  been  placed  on  the  roadway  and 
at  this  time  the  bolt  stresses  were  found  to  have  slacked  off  to  between  70,000  and  80,000 
pounds.  For  the  final  tightening,  the  stress  was  again  brought  up  to  120,000  pounds  to 
allow  for  the  effect  of  the  remainder  of  the  dead  load  yet  to  be  added. 

Various  types  of  wrenches  for  tightening  the  bolts  were  tried.  An  electrically  driven 
gear  and  ratchet  wrench  had  been  developed  by  the  contractor  for  this  particular  pur- 
pose and  was  used  for  the  first  tightening.  A  wheel  wrench  5  feet  in  diameter,  which  was 
actuated  by  a  cable  wrapped  around  the  grooved  rim  and  pulled  by  an  electric  hoist  was 
used  later.  A  short  socket  wrench,  turned  by  striking  the  end  of  the  handle,  was  used 
for  the  final  tightening. 

All  of  the  bolts  were  tapped  at  both  ends  with  a  small  conical  hole  for  the  application 
of  a  strain  gage.  A  record  was  kept  of  the  strain  readings  on  all  of  the  bolts  at  various 
stages  of  the  operations.  Special  extensometers  were  designed  for  taking  these  strain 
measurements. 

The  suspenders  consist  of  four  parts  of  2  11/16  inch  diameter  wire  rope.  The  longest 
suspender  rope  is  approximately  980  feet  long  overall.  They  were  unreeled  from  the 
tower  tops,  both  ends  being  hauled  down  the  footbridge  by  the  use  of  the  high-line,  and 
then  lowered  over  a  pair  of  temporary  sheaves  mounted  on  the  cable  band.  A  center 
mark  on  each  rope  was  made  to  correspond  with  the  top  of  the  split  in  the  cable  band. 

Six  wrapping  machines  were  used  on  the  cable  wrapping.  These  machines  were  of  a 
type  developed  by  the  contractor  erecting  the  cable.  In  this  type  of  machine,  the  bobbins 
are  so  constructed  that  the  wire  on  them  surrounds  the  cable.  Two  wires  are  wound  on 
the  cable  simultaneously  so  that  two  bobbins  are  provided  on  each  machine.  With  this 
type  of  machine,  the  wrapping  must  stop  while  the  bobbins  are  being  filled.  The  wrap- 
ping wire  was  fed  to  the  bobbins  from  reels  mounted  on  the  tower  tops.  The  machines 


171 


THE      GOLDEN      GATE  BRIDGE 


One 
wrapping 


of  the 
machi 


six 
nes 


were  designed  to  function  either  as"pushers"or"pullers."  This  means  that  they  could  be 
operated  either  to  ride  on  the  bare  cable  with  the  wrapping  wire  being  laid  behind  the 
machine,  or  to  ride  on  the  wrapped  cable  with  the  wire  being  laid  ahead  of  the  machine. 
This  adaptability  was  utilized  to  eliminate  most  of  the  hand  wrapping  usually  required 
near  the  cable  bands. 

The  machine  was  assisted  in  its  progress  by  means  of  the  tension  on  a  rope  passing 
over  a  sheave  at  the  tower  and  carrying  a  heavy  counterweight.  The  advance  was  con- 
trolled by  a  tie-back  set  of  falls  released  by  a  hand  winch.  A  workman,  closely  observing 
the  laying  of  the  wires,  released  the  tie-back  cable  at  the  required  rate  of  speed  and  per- 
mitted the  forward  cable  to  advance  the  machine.  After  the  initial  running  adjustments 
were  made  and  the  crews  trained,  the  wrapping  machines  were  daily  wrapping  two  and 
one-half  50-foot  panels  of  cable  "pushing"  and  four  and  one-third  50-foot  panels  of 
cable  "pulling." 

All  splices  in  the  wrapping  wire  were  made  by  means  of  portable  electric  welding 
machines  which  were  carried  along  the  footwalk  with  the  wrapping  machines.  These 

welders  were  especially  designed 
for  this  purpose  and  besides  pro- 
ducing a  butt  weld,  they  also,  by  a 
second  operation,  accomplished  the 
annealing  necessary  when  welding 
wire  of  high  carbon  content. 

Since  a  considerable  length  of 
time  was  to  elapse  between  the 
completion  of  the  compacting  and 
the  cable  wrapping,  the  cable  was 
given  a  coat  of  Galvanized  Metal 
Primer  immediately  after  com- 
pacting. The  wrapping  wires  were 
laid  in  a  heavy  red  lead  paste  ap- 
plied immediately  ahead  of  the 
wrapping  machine.  Over  the 
wrapping  (and  on  the  suspenders) 
another  coat  of  Galvanized  Metal 
Primer  was  applied,  followed  by  a 
paint  containing  68%  red  lead  and 
32%  glyptol  type  synthetic  ve- 
hicle. As  a  final  covering,  the  cable 
and  suspenders  were  given  a  coat  of 
International  Orange  Paint. 


CONSTRUCTION 


ERECTION  OF  STIFFENING  TRUSSES  AND  FLOOR 

The  erection  of  the  stiffening  trusses  and  floor  on  the  Golden  Gate  Bridge  was  given 
thorough  study.  Shipments  of  steel  from  the  East  were  scheduled  to  arrive  not  only  well 
in  advance  of  the  time  they  were  needed  for  erection  but  also  prior  to  the  date  of  an 
anticipated  shipping  strike.  The  material  was  unloaded  from  the  ocean  going  vessels  at 
the  Alameda  plant  of  the  Bethlehem  Steel  Co.  At  the  yard,  the  various  pieces  were 
sorted  and  stored  in  the  order  they  would  be  required  for  erection.  Moreover,  an  inspec- 
tion of  the  painted  surfaces  was  made  by  the  Engineer  and  a  definite  painting  program 
adopted,  as  described  below. 

All  material  for  the  suspended  structure  under  the  specifications,  was  intended  to 
have  one  shop  coat  of  red  lead  mixed  in  the  proportion  of  2  5  pounds  of  red  lead  to  a 
gallon  of  linseed  oil.  From  experience  with  the  tower  steel,  it  was  determined  that  steel 
shipped  from  the  east  by  boats  should  have  greater  protection  than  that  afforded  by  the 
one  red  lead  shop  coat.  As  a  result  of  exposure  tests  of  paint  at  the  site,  it  appeared  that 
the  best  paint  for  the  Golden  Gate  Bridge  was  quick  drying  material  composed  of  pig- 
ment and  a  synthetic  vehicle  of  the  glyceryl  phthalate  type.  Although  a  portion  of  the 
suspended  structural  steel  had  already  been  shipped  with  the  original  shop  coat  applied, 
it  was  decided  to  change  the  specifications  so  as  to  permit  the  application  of  not  only  the 
priming  coat,  but  also  the  second  coat  (and  in  some  instances  the  third)  of  paint  in  the 
shop  as  an  additional  protection  for  the  steel  during  shipment.  Based  on  the  experience 
of  the  exposure  tests  a  synthetic  red  lead  paint  as  described  above  was  used  for  the  three 
under  coats  of  paint.  A  careful  study  was  made  to  determine  what  surfaces  could  be 
given  all  three  coats  and  what  surfaces  only  part  of  them.  In  general,  the  second  coat 
was  applied  to  all  surfaces  and  the  third  coat  was  applied  to  the  insides  of  boxed  sections. 
All  of  the  material  after  unloading  from  the  ocean  going  steamers  at  the  Alameda  yard 
of  the  contractor,  was  carefully  inspected  and  any  damage  to  the  paint  coats  was  re- 
paired. In  many  cases,  this  required  entire  re-painting  of  certain  material  that  had  been 
shipped  prior  to  the  change  in  paint  procedure.  It  was  intended  that  before  any  piece  of 
steel  left  the  storage  yard  for  the  site,  the  paint  should  be  in  such  shape  as  to  meet  with 
the  revised  specifications  as  to  the  number  of  coats  in  good  condition  on  the  various 
surfaces. 

The  supplementary  painting  agreement  included  the  application  of  one  coat  of  the 
final  paint  to  the  outside  surfaces  of  both  steel  towers  and  this  was  applied  prior  to  com- 
mencement of  cable  erection. 

As  required  for  erection,  the  steel  was  loaded  on  barges  and  towed  to  the  site.  Here  it 
was  unloaded  onto  a  material  platform  at  the  base  of  each  tower,  using  two  one-hundred 
foot  Chicago  Booms  at  the  roadway  level  for  this  purpose.  The  various  pieces  were  lifted 
to  the  roadway  level  by  the  Chicago  Booms,  loaded  on  flat  cars  and  hauled  out  to  the 
travelers  as  the  work  progressed. 

The  time  required  for  erection  of  the  suspended  structure  was  one  of  the  factors 


173 


CONSTRUCTION 


which  determined  the  date  of  completion  and  therefore,  it  was  important  that  the  time 
be  minimized  by  adopting  a  carefully  worked  out  procedure  which  took  cognizance  of 
all  special  problems.  This  procedure  was  worked  out  in  detail  in  advance  of  the  com- 
mencement of  the  work  so  that  it  was  determined  in  advance  what  fitting  up  and  rivet- 
ing could  be  accomplished  at  the  various  stages  of  erection.  The  benefit  of  this  well 
studied  program  was  reflected  in  the  rate  of  progress  effected. 

A  great  aid  to  the  speed  of  erection  was  the  use  of  a  safety  net.  This  net  made  of 
manila  rope,  Yg  m-  diameter  and  6  in.  square  mesh,  was  placed  progressively  under  the 
suspended  structure  as  the  latter  was  erected  so  that  eventually  it  extended  under  the 
bridge  its  entire  length  between  pylons  and  was  wide  enough  to  extend  ten  feet  outside 
the  trusses  on  both  sides.  This  safeguard  was  required  by  the  Chief  Engineer.  In  addition 
to  saving  nineteen  lives  during  construction,  there  is  no  question  but  what  the  men 
worked  faster  and  more  efficiently  since  they  felt  the  protection  of  the  net  below  them 
and  were  able  to  move  about  more  freely.  The  use  of  the  safety  net  has  attracted 
only  favorable  comment  from  the  public  and  has  set  a  precedent  that  will  long  be 
remembered. 

The  procedure  adopted,  permitted  the  suspended  steel  erector  to  start  work  before 
the  first  suspenders  were  ready  to  receive  the  loads.  This  was  accomplished  by  canti- 
levering  the  first  three  panels  of  trusses  and  floor  out  each  way  from  the  towers,  thus 
gaining  working  space  on  which  the  four  traveler  derricks  could  be  assembled.  Each 
traveler,  weighing  about  79  tons,  was  equipped  with  one  75  foot  boom.  Power  was 
derived  from  oil-burning  steam  boilers. 

Left:  Erecting  the  suspended  structure.  Note  the  safety  net,  wider  than  the  bridge,  always  extended  out  beyond 
the  point  where  men  are  working.  Below:  The  net  at  forward  end  of  erection  was  carried  on  a  traveling  crane 
which  cantilevered  out  ahead  of  the  workmen.  When  it  moved  forward  it  paid  out  a  section  of  net  behind  itself 


Erection  of  the  suspended  structure 
began  on  June  18.  On  July  20,  1936,  all 
four  travelers  were  in  place  and  rigged 
up  ready  to  proceed  with  the  erection 
except  that  the  safety  nets  ordered  by 
the  Engineer  had  not  been  provided. 
Owing  to  delay  in  the  manufacture  of 
cable  bands  by  the  Roebling  Company, 
the  placing  of  the  suspenders  near  the 
tower  first  required  for  continuing  the 
erection  of  the  stiffening  trusses,  was  not 
accomplished  until  August  31,  1936. 
Erection  of  the  stiffening  trusses  out- 
ward from  the  initial  cantilever  erec- 
tion, started  on  September  11,  1936. 

The  general  procedure  of  erection  of 
the  first-pass  steel  was  to  cantilever  out 
an  additional  two  panels  of  truss  from 
the  last  connected  suspender.  The  trav- 
eler then  raised  the  outward  end  of  the 
truss  until  the  next  suspenders  could  be 
connected  to  the  newly  erected  vertical. 
As  soon  as  the  suspenders  were  con- 
nected, the  traveler  slacked  off  the  truss 
until  its  weight  was  taken  by  the  newly 
connected  suspenders.  A  similar  operation  connected  the  opposite  truss  members.  With 
the  new  two  panels  of  trusses  connected  to  the  suspenders,  the  floor-beams  and  laterals 
were  erected  and  the  necessary  stringers  to  move  the  traveler  forward  were  placed. 

When  the  travelers  met  at  the  center  of  the  main  span,  the  closing  top  chord  mem- 
bers were  placed.  Following  this,  the  closing  bottom  chord  members  were  placed.  Since 
under  this  condition,  the  distance  between  bottom  chord  panel  points  in  the  closing 
panel  would  be  less  than  normal,  in  order  to  provide  for  entering  the  last  bottom  chord 
with  at  least  1  inch  clearance,  this  member  was  fabricated  3%  inches  shorter  than 
normal.  With  the  top  chord  joints  pinned  for  a  stress  of  not  less  than  700,000  pounds, 
the  bottom  chord  panel  points  of  the  closing  panel  could  be  jacked  apart  and  the  closing 
chord  pinned  in  place.  Thus  the  stiffening  trusses  were  made  continuous  from  tower  to 
tower  with  proper  configuration. 

During  the  entire  operation,  the  cable  contractor  manipulated  the  jacks  behind  the 
saddles  at  the  tops  of  the  towers,  jacking  the  tower  tops  shoreward  in  accordance  with 
the  prescribed  program  which  kept  the  tower  deflection  within  12  inches  in  either 
direction.  As  the  travelers  moved  out  in  all  spans  from  the  towers,  the  structure 

176 


CONSTRUCTION 


Seven  lines  of  stringers  were  placed  during  the  first-pass  of  the  travelers.  The  balance  of 
the  stringers  together  with  the  curbs  and  handrailing  were  placed  during  the  second-pass. 
Note  painters  on  the  suspenders 


assumed  a  curve  that  was  concave  upward.  Under  such  a  shape,  the  top  chords  were  in 
compression  and  the  milled  ends  tight  together.  While  in  this  condition,  the  top  plates 
of  the  top  chord  splices  were  riveted.  Later,  when  the  trusses  assumed  their  normal 
shape,  (convex  upwards) ,  these  riveted  top  plates  acted  as  a  tie  to  prevent  the  opening 
of  the  top  chord  splices  when  the  bending  moment  induced  in  the  trusses  caused  the 
bottom  chords  to  be  in  compression.  The  bottom  chord  splices  consequently  came  to  a 
bearing  under  this  load  condition.  As  a  result  of  this  manipulation,  all  milled  ends  of 
chords  came  to  proper  bearing.  It  was  not  permissible  to  rivet  chord  splices  unless  the 
opening  between  milled  ends  was  .006  in.  or  less.  Since  the  chords  were  in  compression 
at  the  time  of  riveting,  even  if  the  joint  was  open  by  the  amount  of  the  allowance,  as 
soon  as  riveting  was  started  the  jarring  and  heat  caused  the  opening  to  close. 

As  rapidly  as  the  erection  of  the  first  pass  proceeded,  the  lateral  system  was  riveted. 
This  was  possible  since  the  lateral  system  is  in  the  plane  of  the  top  chord  and  from  the 
beginning,  the  top  chord  joints  were  tight.  Where  the  riveting  gangs  were  not  able  to 
keep  up  with  the  erection,  the  lateral  connections  were  completely  pinned  and  bolted. 
As  a  result  of  this  procedure,  the  lateral  system  was  connected  up  soon  after  the  trusses 
were  joined  in  the  center  and  thus  the 
lateral  stability  of  the  trusses  under  erec- 
tion condition  was  early  achieved. 

Erection  of  the  second  pass  material, 
which  included  the  remainder  of  the 
roadway  stringers,  sidewalk  material 
and  curbs,  was  effected  as  the  travelers 
moved  back  toward  the  towers.  The  steel 
curbs  were  set  in  position  and  aligned, 
then  removed  and  set  aside  to  clear  the 
operations  of  the  paving  contractor. 

As  soon  as  the  material  had  been 
erected,  all  field  seams  between  the  gus- 
sets and  the  main  material  were  given 
two  coats  of  paint  prior  to  the  general 
application  of  the  third  under  coat. 
Field  rivets  and  gusset  plates  were 
treated  likewise.  Any  damaged  surfaces 
were  spotted  with  three  coats  of  paint. 
The  intent  being  that  with  the  comple- 
tion of  the  steel  erection,  the  surfaces 
would  be  ready  for  the  final  coat  of 
paint  and  any  damage  done  by  other 
contractors  would  be  their  responsibil- 
ity for  repairs. 


THE      GOLDEN      GATE  BRIDGE 


The  first-pass  erection  was  completed  when  the  two  center  span  travelers  met  at 
mid-span  on  November  20,  1936.  Substantially  all  suspended  steel  was  erected  on 
December  14,  1936. 

ROADWAY  PAVEMENT  AND  SIDEWALKS 

A  carefully  worked  out  program  for  placing  the  concrete  roadway  was  incorporated 
in  the  paving  contract.  This  program  took  advantage  of  the  fact  that  as  all  travelers 
moved  back  toward  the  towers  they  left  behind  them  the  steel  floor-structure  ready  to 
receive  the  concrete  pavement.  There  was  room  at  one  side  for  the  paving  contractor 
to  operate  a  material  track  past  the  travelers.  The  specified  program,  therefore,  required 
the  paving  contractor  to  follow  immediately  behind  the  travelers,  as  they  moved  back 
toward  the  towers,  placing  forms  and  reinforcing  steel  for  two  outside,  20  ft.-wide 
strips  of  pavement.  The  material  for  forms  and  reinforcing  steel  for  the  main  span  was 
to  be  taken  out  over  a  material  track  at  one  side.  An  understanding  had  been  reached 
with  the  steel  contractor  that  in  return  for  his  cooperation,  the  District  would  consider 
that  he  had  met  the  essential  time  requirements  of  his  contract  when  the  paving  con- 
tractor was  thus  able  to  proceed  with  his  work.  Under  this  program  when  the  travelers 
reached  the  towers,  the  paving  contractor  would  have  completed  the  placing  of  forms 
and  reinforcing  steel  in  two  20  ft.-wide  strips  throughout  the  length  of  the  bridge 
ready  for  concreting.  Unfortunately,  due  to  lack  of  cooperation  on  the  part  of  the 
contractors,  the  three  weeks  time  which  could  have  been  gained  by  this  program  was 
lost  and  no  effective  work  was  done  at  the  center  of  the  main  span  until  the  travelers 
reached  the  towers  and  were  dismantled. 

On  January  19,1937,  34  days  after  the  placing  of  steel  had  been  completed,  the  first 
concrete  in  the  roadway  deck  was  placed. 

The  roadway  slab  was  divided  into  three  longitudinal  strips,  20  feet  wide  for  ease  in 
finishing  and  construction.  It  was  divided  every  fifty  feet  with  a  special  pre-moulded 
expansion  joint  to  prevent  the  participation  of  the  roadway  slab  in  the  truss  stresses.  All 
pours  therefore,  were  in  widths  of  20  feet  and  in  multiples  of  50  feet  in  length.  Wooden 
forms  were  used,  suspended  from  the  tops  of  the  stringers  by  special  supporting  devices 
that  were  removed  with  the  stripping  operation.  The  slab  was  reinforced  transversely 
with  fabricated  reinforcing  steel  trusses  having  the  web  members  of  the  trusses  arc- 
welded  to  their  chords  by  machine-made  welds.  Longitudinally,  the  slab  was  reinforced 
with  l/z  inch  round  bars.  The  trusses  were  held  the  required  distance  above  the  forms 
( 1  inch  clear)  by  steel  blocks  which  were  welded  both  to  the  trusses  and  to  the  tops  of 
the  stringers.  The  field  welding  was  done  by  portable  gasoline  driven  welding  outfits. 
Form  panels  from  the  roadway  were  re-used  in  the  sidewalk  construction. 

Concrete  was  hauled  over  the  construction  trestle  to  the  base  of  the  San  Francisco 
Tower  in  transit-mix  trucks.  Here  it  was  dumped  into  a  hopper  and  raised  to  a  hopper 
above  the  roadway  level  by  means  of  the  usual  concrete  hoist.  At  this  point  it  was  loaded 


178 


THE      GOLDEN      GATE  BRIDGE 


into  industrial  railway  side  dump  cars  and  hauled  to  the  point  of  deposit  by  gasoline 
industrial  locomotives.  At  the  point  of  deposit,  the  concrete  was  distributed  by  hand 
operated  buggies.  Special  vibrating  finishing  machines  were  used  in  addition  to  hand 
controlled  mechanical  vibrators  in  order  to  insure  a  smooth  soffit  and  dense  concrete. 
With  the  reinforcing  steel  held  solidly  in  place  by  welding  to  the  stringers  and  the  top 
surface  finished  with  mechanical  surfacers  on  the  finishing  machines,  the  finished  slab 
was  well  within  the  tolerance  of  l/%  inch  in  10  feet  set  up  by  the  specifications.  The 
maximum  rate  of  progress  was  1700  lineal  feet  of  20  foot  slab  in  eight  hours. 

Concreting  of  the  deck  proceeded  without  serious  interruption  until  February  17. 
On  this  date  an  unfortunate  accident  occurred  which  cost  the  lives  of  ten  men  working 
on  a  stripping  scaffold  near  the  center  of  the  main  span.  It  also  held  up  further  opera- 
tions of  the  paving  contractor.  In  this  accident,  the  stripping  scaffold  fell  into  the  net 
and  carried  away  the  entire  half  of  the  main  span  net  between  the  net  traveler  and  the 
San  Francisco  Tower.  Workmen  were  not  permitted  to  work  in  the  area  where  the  net 


CONSTRUCTION 


was  missing.  Materials  however,  were  hauled  over  this  area  to  the  Marin  side  where  con- 
struction of  forms  and  setting  of  reinforcing  steel  went  ahead. 

On  March  3,  1937,  replacement  of  the  net  was  started  and  it  was  completed  on 
April  2,  1937.  Concreting  operations  were  immediately  resumed,  with  the  result  that 
the  roadway  paving  was  completed  on  April  15,  1937.  During  this  operation  the  west 
lane  was  kept  clear  for  the  cable  contractor  who  was  engaged  in  removing  the  wooden 
sections  and  footwalk  ropes  from  the  west  footwalk.  Other  operations  by  the  erector 
were  necessary  at  the  same  time  so  that  the  work  of  the  three  contractors  had  to  be  care- 
fully coordinated  in  order  to  avoid  confusion  and  in  the  interests  of  safety. 

As  fast  as  the  form  material  could  be  stripped  from  the  roadway  and  placed  in  the 
sidewalk  space,  sidewalk  concreting  was  put  under  way.  The  speed  of  this  operation 
depended  upon  the  number  of  expert  finishers  employed.  Since  all  operations  on  the 
bridge  at  this  time  began  to  feel  the  scarcity  of  skilled  workmen  of  all  crafts,  the  rule 
for  employment  of  residents  only  was  waived  where  necessary  so  as  to  minimize  delay. 

During  the  concreting  operations  of  the  paving  contractor,  there  was  considerable 
leakage  from  the  forms  which  splattered  the  painted  surfaces  with  grout  and  cement 
stain.  The  paving  contractor  was  required  under  his  contract  to  clean  off  this  stain  and 
repaint  wherever  the  paint  coats  were  damaged  by  his  operations.  In  general,  this  was 
wherever  the  concrete  or  cement  stain  had  to  be  removed  since  it  was  necessary  to  use 
steel  wool  and  putty  knives  to  clean  off  the  foreign  material.  These  surfaces  were  care- 
fully cleaned  under  the  supervision  of  an  inspector  and  then  retouched  with  the  cor- 
responding coats  of  paint  to  restore  them  to  a  condition  ready  to  receive  the  final 
paint  coat. 

CONSTRUCTION  OF  SAN  FRANCISCO  AND  MARIN  APPROACHES 

The  Marin  Approach  piers  carrying  the  structure  between  the  abutment  and  the 
anchorage  were  located  in  various  types  of  ground.  The  footings  on  the  side  of  the  hill 
were  all  in  exposed  rock  of  the  hillside.  Those  in  the  valley  were  in  swampy  ground 
where  wooden  sheet  pile  cofferdams  were  necessary  to  reach  suitable  foundation 
material. 

The  San  Francisco  Approach  piers  were  carried  down  into  the  sandstone  ledge  on 
the  hillside  and  at  such  elevations  that  they  could  not  be  affected  by  either  the  excava- 
tions for  the  anchorage  blocks  or  for  the  adjacent  piers.  Excavation  for  these  piers  was 
carried  on  within  the  confines  of  wooden  sheet  pile  cofferdams  where  necessary. 

Erection  of  the  Marin  Approach  superstructure  was  started  on  January  17,  1936. 
The  trusses  were  erected  on  specially  designed  timber  falsework  towers  which  were 
framed  with  timber  connectors.  These  towers  were  made  up  in  sections  so  that  they 
could  be  used  for  varying  heights  of  spans  and  re-used  for  both  this  approach  and  the 
San  Francisco  Approach  trusses  and  arch.  A  stiff  leg  traveler  derrick  was  used  and  erec- 
tion of  the  Marin  Approach  was  completed  on  August  21,  1936. 


181 


THE      GOLDEN      GATE  BRIDGE 


Erection  of  the  San  Francisco  Approach  superstructure  was  started  on  July  21, 
1936,  using  the  same  traveler  that  had  been  used  on  the  Marin  Approach.  Erection  of 
the  319  foot  arch  over  Old  Fort  Point  was  carried  on  simultaneously.  For  the  erection 
of  this  two-hinged  arch,  two  guy  derricks  were  utilized  for  the  arch  ribs  after  which 
the  erection  was  completed  with  the  approach  traveler  when  it  had  reached  that  point. 
With  the  aid  of  jacks  on  the  falsework,  the  chords  of  the  arch  were  brought  to  proper 
bearing. 

CONSTRUCTION  OF  PRESIDIO  APPROACH  ROAD 

The  Presidio  Approach  Road  includes  the  structural  steel  High  Viaduct,  the  rein- 
forced concrete  Low  Viaduct,  and  the  paved  roadway  and  grading  between  the  Toll 
Plaza  and  the  intersection  of  Lyon  Street  with  Marina  Boulevard  at  the  eastern  limits 
of  the  Presidio.  In  January,  1934,  in  order  to  help  relieve  unemployment  in  the  District, 
the  contractor  was  permitted  to  proceed  with  the  work  on  the  Low  Viaduct  in  advance 
of  the  time  that  it  was  required.  The  main  contract  for  this  work  was  awarded  in  two 
parts  of  which  Part  II  contained  the  Low  and  High  Viaducts.  Work  on  these  structures 
was  undertaken  only  as  rapidly  as  the  funds  were  appropriated  by  the  Board  of  Directors 
of  the  District.  Part  I  of  this  contract  was  awarded  on  August  4,  1936. 

The  Low  Viaduct  structure  consists  mostly  of  simple  reinforced  concrete  spans  of 
32.5  feet.  The  footings  are  on  piles  as  are  the  footings  of  the  east  abutment  for  the 
structure.  The  length  of  the  structure  between  abutments  is  3308  feet.  Wherever  the 
cut-off  for  the  piles  was  below  ground  water,  wooden  piles  were  used.  On  the  hillside 
where  ground  water  was  at  great  depth  below  the  surface,  concrete  piles  of  the  cast-in- 
place  type  were  used.  The  length  of  wooden  piles  averaged  between  3  8  and  40  feet.  All 
piles  were  driven  to  refusal. 

Because  of  the  swampy  character  of  the  ground  under  the  viaduct,  it  was  necessary 
to  adopt  a  type  of  falsework  for  supporting  forms  that  would  not  be  affected  by  the 
variable  ground  conditions  under  the  structure.  Accordingly,  all  falsework  was  sup- 
ported by  the  foundations  of  the  structure  itself.  Each  column  was  enclosed  with  a  four 
post  tower  bearing  on  the  corners  of  the  footing  slabs.  This  tower  supported  a  falsework 
of  rolled  steel  beams  utilizing  the  stringers  from  the  High  Viaduct  and  its  approaches 
before  they  were  required  for  erection.  These  steel  beams  supported  the  forms  them- 
selves and  proper  allowance  was  made  for  the  deflection  of  the  beams  so  that  the  result- 
ing roadway  floor  would  be  a  true  surface  as  required. 

This  structure,  being  composed  of  alternate  four  post  towers  with  simple  spans 
between,  lent  itself  to  an  economical  and  rapid  procedure  for  construction.  In  the 
simple  spans,  one  end  was  fixed  to  the  tower  span  with  steel  dowels  and  the  other  end 
was  left  free  to  move  by  means  of  metal  expansion  plates  embedded  in  the  concrete.  The 
upper  bearing  plates  were  of  steel  and  the  lower  ones  of  bronze.  On  account  of  the  heavy 
reinforcement  of  the  columns  and  beams  of  the  viaduct,  internal  vibrators  were  used 


182 


The  pier  of  the  High 
Viaduct  of  the 
Presidio  Approach  Road 


THE      GOLDEN      GATE  BRIDGE 


to  insure  dense  concrete  free  from  voids.  Work  on  the  Low  Viaduct  was  started  June 
18,  1934  and  completed  on  September  22,  1936.  The  Low  Viaduct  also  provided  con- 
nections for  both  ramps  of  the  Richardson  Avenue  Approach. 

The  piers  for  the  High  Viaduct  and  the  short  approaches  at  each  end  were  originally 
designed  as  spread  footings  to  be  carried  to  suitable  material.  Foundations  for  Pier  4  and 
westward  were  so  constructed.  Borings  at  Pier  5  and  eastward  disclosed,  below  the  sand 
formation,  a  stratum  of  peat  of  varying  thicknesses.  It  was  therefore  decided  to  place 
the  piers  located  above  this  stratum  on  concrete  piles.  Four  piers  were  thus  founded. 

The  concrete  was  deposited  in  the  upper  part  of  these  piers  by  a  locomotive  crane 
with  dump  buckets.  Internal  vibrators  were  used  to  compact  the  concrete  and  insure 
its  density.  Work  on  the  High  Viaduct  substructures  was  started  on  February  23,  1934 
and  completed  June  5 ,  193  5. 

The  erection  of  the  High  Viaduct  superstructure  involved  no  unusual  difficulties. 
The  erector  did  however  adopt  a  unique  falsework  plan  for  this  work.  Clusters  of  six 
long  piles  were  driven  a  few  feet  into  the  sand  soil  beneath  the  structure  until  their  tops 
were  just  below  the  elevation  of  the  bottom  chord.  The  tops  were  pulled  together  and 
lashed  with  wire  rope.  Caps  were  placed  on  top  of  the  clusters  and  the  chords  supported 
from  them. 

Erection  of  the  High  Viaduct,  together  with  the  concrete  roadway  slab  which  was 
a  part  of  this  contract,  were  completed  on  December  4,  1936.  A  simple  concrete  balus- 
trade was  used  on  both  viaducts. 

Plywood  panel  forms  were  used  for  the  concrete  structures. 


184 


CONSTRUCTION 


DATE. 

ip 

Perce 

SO  4 

NT  Cc 

0  s 

)  M  P  LE.TE 

iO  « 

•O  1 

fr- 
et) 

< 

•i 

- 

/ 

< 

j 

u. 

— ^ 

1 

vS) 
CO 
<T> 

Q 

f  '  i 

1 

-  J — *- 

1  / 

1 

y 

o 

< 

y 
/ 

/ 

f- 

L- 

T 

s 

—* 

/ 

< 

s 

f 
1 

u. 

ft 

/ 

"3 

■J. 

— i 

*- 

m 
cO 
0) 

o 

■- 

— 

— -»■ 

1 

\ 

2 

- 

/ 

V 

— 

— 1 — 
1 

o 

■  1 

I/) 

<: 

/ 

-> 

.<£> 

/ft? 

-> 

Pi 

<< 

5 

— ( 

<: 

^>  / 

2 

o 

—  t 

,<?- 

J-/ 

u. 

V 

'  ✓ 

"3 

> 

(0 
0) 

Q 

— 

/ 

2^ 

—  J 

-A 

* 

i 
i 

O 

- 

1 

t— 

— i 

-f- 
1 

s 

Y 

< 

/ 
/ 

h- 

I 



— 1 

! 

s 

i 

< 

— 
/ 

5 

T 

u. 

/ 

i 

-j 

/ 

S 

(0 
CO 
0) 

Q 

y 

2 

1 

o 

* 

-|— 

- 

< 

-> 

— 

* 

f 

i 

5 

'/ 

< 

i 

IO  2 

7  3i 

Per 

CENT  < 

30MPLE 

tE 

?  <9£ 

t 

3 

0 

185 


MATERIALS.  MANUFACTURERS 
THROUGH  EXTENSIVE  RESEARCH 
AND  DEVELOPMENT  HAVE  PRO- 
DUCED MATERIALS  OF  HIGH  STRENGTH 
AND  QUALITY  WITHOUT  WHICH  THE 
WORLD'S  LONGEST  BRIDGE  SPAN 
COULD  NOT  HAVE  BEEN  BUILT. 


187 


THE      GOLDEN      GATE  BRIDGE 


The  materials  of  which  the  structure  is  composed  vary  in  class  and  grade  be- 
cause of  the  type  of  the  bridge.  The  basic  structural  divisions  of  the  bridge  consist 
of  towers  and  anchorages,  cables  and  floor  system.  The  towers  and  the  anchorages 
sustain  the  cables  while  the  floor  structure  is  suspended  from  the  latter.  The  various 
divisions  are  composed  principally  of  rolled  structural  steels  which  occur  in  the  towers 
and  suspended  structure,  heat-treated  eye-bars  which  are  embedded  in  the  anchorages 
and  wire  which  forms  the  cables.  The  latter  have  such  appurtenances  as  cast  steel  bands 
and  suspender  ropes  of  wire  while  throughout  other  parts  of  the  structure  are  distributed 
various  kinds  of  other  materials.  With  the  exception  of  cable  wire,  the  materials  had  to 
be  either  combined  or  worked  into  members  at  the  shop. 

The  quality  of  each  grade  of  material,  with  some  exceptions,  was  ascertained  by 
means  of  both  chemical  and  physical  tests.  The  chemical  determination  comprised  ladle 
and  check  analyses.  The  physical  determination  embraced  the  regular  mill  or  foundry 
tension  and  bend  tests  and  the  check  tension  test.  The  physical  check  test  was  made  to 
obtain  more  accurate  information  regarding  the  properties  than  can  be  secured  from 
mill  tests  and  was  intended  primarily  for  structural  steel  but  was  used  for  all  materials. 

Application  of  the  tests  varied  with  the  character  of  the  material.  For  every  melt  a 
ladle  analysis  was  made  on  samples  secured  at  the  time  of  pouring  the  molten  metal  into 
molds.  A  check  analysis  was  made  on  either  semi-finished  or  finished  material.  The 
physical  tests  were  employed  in  a  manner  controlled  by  the  type  and  grade  of  the  ma- 
terial and  the  method  of  its  manufacture.  At  one  end  of  the  list  was  material  such  as 
wire  of  which  each  piece  was  tested.  At  the  other  end  was  material  such  as  eye-bars  of 
which  representative  pieces  had  to  be  investigated.  In  between  these  extremes  was  the 
material  that  was  tested  by  means  of  random  choices  of  samples. 

The  different  tests  were  used,  of  course,  for  the  purpose  of  gaining  assurance  that 
the  prescribed  properties  of  each  grade  of  material  were  within  the  limits  set  by  specifi- 
cations. In  this  connection,  three  conditions  which  attend  manufacture,  viz.,  chemical 
composition,  mechanical  treatment  and  heat-treatment,  had  to  be  considered.  These 
factors  are  variables.  The  element  carbon,  for  example,  because  of  conditions  under 
which  molten  metal  solidifies  in  an  ingot  mold,  tends  to  segregate  in  such  a  manner  that 
the  top  of  the  ingot  becomes  high  in  carbon  content  and  the  bottom  low  in  this  respect 
as  compared  with  the  intermediate  portion.  Concerning  mechanical  treatment  there 
occur,  for  instance,  many  cases  where  ingots  in  a  melt  of  steel,  and  even  parts  of  an 
ingot,  must  be  worked  differently  to  produce  pieces  of  different  thickness  and  sizes. 
Thermal  variations  occur  in  all  the  heat  treating  practices.  Of  the  three  factors,  com- 
position is  the  underlying  one.  The  specifications  have  recognized  their  variable  nature 
by  providing  means  for  investigating  their  effect.  A  check  analysis  was  authorized  in 


188 


MATERIALS 


connection  with  material  suspected  of  being  unduly  segregated.  Physical  tests  besides 
the  usual  number  were  required  when  the  thickness  of  material  exceeded  defined  limits. 
And  for  each  lot  of  heat-treated  material  physical  tests  had  to  be  made. 

Accordingly,  the  testing  programs  were  arranged  to  include  specimens  from  those 
parts  of  each  lot  of  material  which  would  reveal  the  ranges  in  properties.  The  chemical 
properties  were  found  by  analysis  of  material  from  top  and  bottom  cuts  of  ingots  when- 
ever possible.  The  physical  properties  were  determined  from  tests  of  like  material  when 
it  was  used  for  the  work  and  when  the  number  of  tests  required  by  the  specifications 
permitted  such  a  selection. 

In  order  to  acquire  the  desired  information,  identification  of  material  naturally 
became  an  important  consideration.  The  identity  of  not  only  the  melt  but  also  of  the 
pieces  within  the  melt  had  to  be  known.  In  the  discussion  bearing  on  the  various  ma- 
terial, the  manufacturing  procedures  are  described  for  the  purpose  of  showing  the 
system  of  identification  used  as  well  as  the  reasons  for  adopting  the  different  test 
methods. 

The  materials  in  the  main  steel  structure  of  the  bridge  are  discussed  here  under  the 
following  headings : 

1 .  Structural  Steel 

2.  Heat-Treated  Eye-Bars 

3.  Wires  and  Ropes 

4.  Cast  Steel 

5.  Forged  Steel 

6.  Other  Materials 

7.  Distribution  of  Materials  in  Main  Steel  Structure 

STRUCTURAL  STEEL 

The  principal  grades  of  rolled  steel  in  the  bridge  are  silicon,  carbon  and  rivet.  In- 
cluded under  carbon  there  is  copper-bearing  carbon  steel  and  a  carbon  steel  of  special 
composition.  The  latter  is  used  only  in  the  architectural  treatment  of  the  tower  bracing 
above  the  roadway;  the  copper-bearing  carbon  steel,  principally  in  the  end  panels  of 
the  floor  structure  and  in  the  railing.  Silicon  steel  occurs  only  in  the  towers  and  the 
suspended  structure  while  the  two  remaining  grades  may  be  found  in  all  divisions  of 
the  bridge. 

MANUFACTURE:  The  four  forms  in  which  practically  all  of  the  rolled  steel  was 
used  for  this  structure  are  plate,  shape,  flat  and  rivet-rod.  The  term  "flat"  as  used  in 
this  report  means  any  plate  less  than  10  in.  in  width.  Some  of  the  sections,  such  as  plates 
of  several  inches  thickness  and  round  bars  of  large  diameter,  are  referred  to  as  "thick 
material."  Each  of  the  four  forms,  with  minor  exceptions,  was  made  in  a  different  plant, 
though  all  steel  was  made  in  basic  open-hearth  furnaces.  The  operations  involved  in 
producing  each  of  these  rolled  steels  were  essentially  the  same. 


189 


MATERIALS 


The  process  employed  in  making  the  above  products  followed  standard  practice. 
The  operations,  listed  in  the  order  in  which  they  are  conducted,  include  melting  of  raw 
materials;  pouring  the  metal  into  ingot  molds;  stripping  these  molds  from  the  ingots 
and  placing  the  latter  in  soaking  pits  or  furnaces  to  prepare  them  for  preliminary  (or, 
in  some  cases,  final)  rolling;  rolling  the  ingots  on  a  blooming  mill  and  then  shearing  the 
resultant  section  to  semi-finished  pieces  called  slabs,  blooms  or  billets,  depending  on 
their  size  and  shape;  reheating  these  pieces  in  furnaces  and  rolling  them  on  a  finishing 
mill  to  the  desired  form;  and,  finally,  shearing  them  to  yield  the  finished  mill  product. 
Movement  of  material  in  ingot  form  from  open  hearth  furnace  up  to  the  blooming 
mill  (which  produced  semi-finished  material,  as  slabs  for  plates,  blooms  for  shapes,  or 
billets  for  smaller  forms)  was  the  same  for  all  products.  Beyond  the  blooming  mill  the 
semi-finished  material  passed  through  the  rolling  process  which  was  suited  to  produce 
the  desired  form  and  which  was  consistent  with  that  form  except  in  the  case  of  plates. 
Slabs  for  the  latter  were  rolled  in  two  ways.  Those  which  produced  plates  wider  than 
60  in.  were  rolled  on  a  sheared-plate  mill,  that  is,  the  plate  was  rolled  in  such  fashion 
that  it  had  to  be  sheared  to  size  on  all  four  edges.  Those  slabs  which  produced  narrower 
plates  were  rolled  on  a  universal-plate  mill,  the  finished  plate  having  rolled  edges  but 
sheared  ends. 

IDENTIFICATION:  Identification  by  melts  is  standard  practice  in  the  manufac- 
ture of  metallic  materials ;  the  same  scheme  being  followed  for  all  products  in  the  early 
stages  of  the  process.  Material  is  charged  by  melts  in  soaking  pits  and  other  reheating 
furnaces  where  it  is  located  by  means  of  charging  sheets  which  record  position  of  pieces 
in  the  furnace,  or,  as  in  continuous  furnaces,  by  means  of  markers  which  serve  as  divid- 
ing lines  between  melts  as  well  as  parts  of  a  melt.  In  other  steps  the  means  vary  but 
identity  of  the  melt  is  maintained.  Since  tests  in  this  work  were  to  be  made  on  material 
from  top  and  bottom  cuts,  the  pieces  rolled  from  these  portions  of  ingots  had  to  be 
followed  through  the  operations. 

The  identity  of  the  structural  steel  was  carried  out  not  only  to  permit  selection  of 
specimens  but  also  to  insure  the  use  of  correct  grades  in  fabricated  members  composed 
of  more  than  one  grade. 

The  only  material  that  did  not  require  some  means  of  identification  between  ingot 
and  finished  product  was  the  I-beam  material.  The  ingot  passed  directly  from  blooming 
mill  to  finishing  mill.  The  product  was,  of  course,  identified  by  reference  to  the  soaking- 
pit  charging  records. 

To  preserve  the  identity  of  slabs,  from  which  the  plates  are  rolled,  they  were 
stamped,  while  quite  hot,  at  the  blooming  mill  during  shearing  operations.  The  steel 
stamping  included  the  number  of  the  melt  and  a  letter  which  indicated  the  slab's  loca- 
tion in  the  ingot.  The  complete  marking  was  so  placed  that  the  top  end  of  the  top  cut 
or  the  bottom  end  of  the  bottom  cut  could  be  identified.  This  end  was  recorded  on  the 
charging  sheet  when  the  slab  was  placed  in  the  reheating  furnace  preliminary  to  being 

the  center  of  the  main  span  the  ^9^ 
les  are  only  ten  feet  above  the 
dway.  Note  the  steel  curbs  and 
handrails 


THE      GOLDEN      GATE  BRIDGE 


rolled  into  a  plate.  In  such  a  system  of  identification,  however,  identity  of  the  ends  may 
be  lost  in  the  course  of  drawing  the  slabs  out  of  the  furnace  and  placing  them  in  position 
for  rolling.  Furthermore,  identity  of  the  ends  may  also  be  lost,  as  in  the  case  of  sheared 
plates,  because  of  peculiarities  in  rolling  procedure.  In  the  sheared-plate  mill  the  slab 
usually  undergoes  both  transverse  and  longitudinal  rolling.  In  the  event  the  final  rolling 
operation  is  performed  transversely  then  what  were  originally  ends  of  the  slab  finally 
become  the  sides  of  the  plate.  Such  confusion  in  respect  to  ends  cannot  occur  in  con- 
nection with  universal-plate  rolling  because  the  width  of  the  slab  is  made  such  that  the 
slab  passes  through  the  mill  only  in  the  direction  of  its  length  which  is  always  measured 
lengthwise  of  the  ingot.  Identity  of  the  ends  as  it  affects  testing  of  plates  will  be  referred 
to  subsequently. 

Blooms,  from  which  were  rolled  all  angles  larger  than  4  by  4  as  well  as  other  shapes 
above  the  same  size,  were  not  stamped  for  identification  because  they  moved  directly 
from  blooming  mill  through  a  continuous  furnace  to  finishing  mill.  In  the  continuous 
furnace,  markers  were  used  to  indicate  divisions  between  melts  and  cuts. 

Billets,  (which  produced  rivet-rods,  flats  and  small  shapes)  were  seldom  marked 
with  respect  to  location  in  the  ingot  because  orders  on  the  mill  usually  required  these 
forms  in  small  quantities,  calling  for  only  a  part  of  a  melt  or  a  part  of  an  ingot.  Those 
rolled  into  rivet-rods  and  small  shapes  were  identified  only  as  to  melt.  Billets  for  flats 
also  were  stamped  only  with  the  melt  number  except  in  the  few  cases  when  sizable 
orders  were  placed  with  the  mill.  In  such  instances  location  in  the  ingot  was  included 
with  the  markings. 

The  finished  material  was  stamped  with  the  number  of  the  melt  from  which  it  had 
been  produced.  Rivet  rods  were  identified  by  means  of  stamped  metal  tags  attached  to 
bundles  of  these  pieces.  Every  individual  piece  of  other  products  was  steel-stamped  with 
this  number.  To  facilitate  identification  at  the  fabricating  shops,  the  ends  of  silicon 
steel  products  were  painted  with  green  paint  and  of  copper-bearing  steel  with  yellow 
paint. 

All  specimen  material  was  marked  with  melt  number,  and  also  with  cut  notation  in 
cases  where  identity  had  been  extended  that  far.  The  latter  occurred  in  all  specimen 
material  excepting  that  which  represented  rivet-rods,  small  shapes  and  most  of  the  flats. 

CHEMICAL  AND  PHYSICAL  REQUIREMENTS:  Chemical  and  physical  prop- 
erties specified  for  each  of  the  three  grades  of  rolled  steel  were,  in  part,  those  given  in 
Table  3.  These  requirements,  however,  had  some  modifications  that  have  not  been 
indicated  in  the  table. 

The  restrictions  in  connection  with  chemical  properties  pertained  to  the  content  of 
different  elements.  These  reservations  limited  the  amount  of  manganese  in  silicon  steel 
to  1.20%  as  a  maximum;  fixed  a  range  of  0.05  %  to  0.1  5  %  for  the  amount  of  silicon  in 
structural  carbon  steel;  permitted  an  over-run  of  10%  in  carbon,  25%  in  phosphorus 
and  25%  in  sulfur  on  check  analysis;  and  established  0.20%  as  the  minimum  amount 


192 


MATERIALS 


TABLE  3.— SPECIFIED  CHEMICAL  AND  PHYSICAL  PROPERTIES  FOR  STRUCTURAL  STEELS 


Carbon  Steel  (a) 

Silicon  Steel  (b) 

Structural 

Rivet 

Carbon  (max.)  

Phosphorus  (max.): 

Acid  Process  

Basic  Process  

Sulfur    (max.)     .  

Silicon   

0.06 
0.04 
0.05 

0.04 
0.04 
0.045 

0.40 

0.06 
0.04 
0.05 
0.20  to  0.45 

80,000  to 
95,000 
45,000 
1,500,000 
Ten.  Str. 
30 

a  n     npsf1  1 
_                >  See  text 
Copper  1 

Tensile  strength,  lbs.  per  sq.  in  

Yield  Point,  Minimum,  lbs.  per  sq.  in..__ 

Elongation  in  8"  minimum,  per  cent*  

Reduction  of  Area,  minimum,  per  cent* 

60,000  to 
70,000 
36,000 
1,500,000 
Ten.  Str. 
42 

52,000  to 
60,000 
30,000 
1,500,000 
Ten.  Str. 
52 

(a)  Each  group  of  ten  melts  of  carbon  steel  to  be  used  in  the  towers  which  consecutively  have  met  the  individual  minimum 
yield  point  requirement  had  to  have  a  minimum  average  yield  point  of  38,000  lbs.  per  sq.  in. 

Tensile  tests  of  specimens  from  thick  material  or  that  of  a  thickness  or  diameter  greater  than  1  ]/4  inches  had  to  show  ultimate 
strength  and  yield  point  as  great  as  the  minimum  specified,  a  minimum  elongation  in  two  inches  of  1,600,000  tensile  strength, 
and  a  reduction  in  area  of  not  less  than  30  per  cent. 

(b)  Each  group  of  ten  melts  of  silicon  steel  to  be  used  in  the  towers  which  consecutively  have  met  the  individual  minimum 
yield  point  requirement  had  to  have  a  minimum  average  yield  point  of  47,000  lbs.  per  sq.  in. 

"■See  Text. 

of  copper  that  had  to  be  present  in  steels  specified  to  contain  this  element.  The  latter 
constituent  averaged  about  0.25%  in  amount.  In  the  case  of  the  material  for  the  tower 
bracing  enclosure  plates,  the  carbon  content  was  limited  to  0.15%  as  a  maximum  on 
ladle  analysis  but  no  physical  tests  were  prescribed. 

Modifications  in  regard  to  physical  properties  defined  requirements  for  the  percent- 
age of  elongation  and  reduction  of  area  in  structural  carbon  and  silicon  steel.  To  arrive 
at  the  minimum  percentage  of  elongation  for  structural  carbon  material  between  %  in. 
and  1  in.  in  thickness,  one  from  the  per  cent  elongation  derived  by  the  ratio  given 
was  to  be  deducted  for  each  increase  in  thickness  of  l/%  in.  (or  fraction  thereof)  but  the 
elongation  in  no  case  could  be  less  than  18%  .  For  the  silicon  steel  over  1  in.  thick  the 
same  amount  of  deduction  was  to  be  made,  but  for  each  increase  of  %  in.  (or  fraction 
thereof)  and  to  a  minimum  of  14%.  The  percentage  in  reduction  of  area  for  the  two 
grades  was  defined  similarly.  For  structural  carbon  steel  between  %  in.  and  1  %  in.  in 
thickness,  one  from  percentage  reduction  for  each  increase  in  thickness  of  !/8  in-  (or 
fraction  thereof)  was  to  be  made  but  the  minimum  could  not  be  less  than  3  5  r<  .  For 
silicon  steel  over  %  in.  thick  the  minimum  was  to  be  calculated  the  same  way  but  the 
ultimate  minimum  could  not  be  below  24%. 


193 


THE     GOLDEN      GATE  BRIDGE 


For  ascertaining  both  kinds  of  properties,  specifications  required  four  groups  of 
tests  to  be  made  but  did  not  in  all  cases  define  requirements  as  to  number  of  specimens 
nor  their  location.  These  tests  comprised  ladle  and  check  analyses  for  composition,  and 
mill  and  check  tests  for  physical  properties.  In  connection  with  chemical  tests,  the  usual 
ladle  or  melt  test  had  to  be  made  on  samples  selected  in  the  customary  way,  but  with 
respect  to  check  analyses,  specifications  did  not  prescribe  the  number  nor  location  of 
samples.  For  gauging  physical  properties,  the  specifications  required,  in  the  matter  of 
check  tests,  only  a  number  deemed  necessary  to  check  the  yield  point,  but  in  the  case  of 
the  mill  tests  they  were  more  definite.  At  least  two  tension  and  one  bend  test  had  to  be 
made  from  each  melt  or  variety  of  product  such  as  plates,  shapes  or  flats.  In  connection 
with  this  work,  sheared  and  universal-mill  plates,  which  are  termed  "plates,"  have  been 
considered  as  different  products.  Specifications  further  required  that  in  the  event  a 
variety  in  a  melt  differed  %  m-  or  more  in  thickness,  one  tension  and  one  bend  test  had 
to  be  made  from  both  the  thickest  and  thinnest  material  rolled.  Every  specimen  for 
physical  test  had  to  have  its  longitudinal  axis  in  the  direction  of  rolling. 

SELECTION  OF  SPECIMENS:  Inasmuch  as  it  was  desired  to  determine  the  prob- 
able limits  of  chemical  and  physical  properties,  and  because  such  limits  would  most 
likely  be  revealed  by  tests  of  material  from  top  and  bottom  cuts  of  ingots,  a  procedure 
was  established  for  the  selection  of  physical  and  chemical  test  material  from  these  parts 
of  the  melt.  The  specimen  material  was  required  to  be  taken  from  the  top  end  of 
top-cut  material  and  from  the  bottom  end  of  pieces  rolled  from  bottom  cuts,  but  the 
cuts  did  not  have  to  be  from  the  same  ingot  to  represent  a  given  melt.  In  cases  where 
extreme  cuts  of  ingots  were  not  applied  to  this  work,  or  where  one  kind  of  cut  only 
could  be  tested  because  the  number  of  tests  required  per  melt  by  specifications  had  to 
be  used  up  in  covering  the  prescribed  gauge-variation  in  the  product,  this  general 
method  of  specimen-selection  had  to  be  varied.  It  had  to  be  altered  also  in  connection 
with  plate  tests  because  after  the  rolling  of  plates  had  gotten  under  way  it  was  felt  that 
the  identity  of  the  ends  of  some  slabs  was  being  lost  during  reheating  and  rolling  opera- 
tions. In  order  that  the  top-most  and  bottom-most  ends  of  these  cuts  would  be  tested, 
specimens  were  taken  from  both  ends  of  plates. 

The  location  of  the  physical  test  specimen  in  the  rolled  piece  depended  upon  the 
shape  of  the  product,  but  for  all  products,  excepting  sheared  plates,  the  axis  of  the 
specimen  was  always  taken  lengthwise  of  the  ingot  or  in  the  direction  of  all  rolling.  For 
testing  angles,  specimens  were  cut  about  l/z  in.  in  from  the  toe;  for  beams  and  channels, 
from  a  point  in  the  web  midway  between  the  flange  and  axis  of  section;  but  for  rivet- 
rods  and  most  of  the  flats  the  full  section  as  rolled  was  used  to  provide  the  specimen.  For 
plates  the  axis  of  specimen  coincided  with  the  axis  of  piece  as  rolled,  but  in  the  case  of 
sheared  plates,  it  did  not  necessarily  coincide  with  the  axis  of  the  ingot  because  the  final 
rolling  could  be  conducted  transversely. 

The  samples  for  check  analyses  were  drilled  from  the  physical  test  specimen.  In  case 


194 


MATERIALS 


-a 
c 

rt 
u 

a 


ON  i-H 
O  <N  i-i  "s 
r*-\     ©     ©  © 


O    i-i  © 


©  © 


©  o 

0  0  ^ 

ON  f 

NO  r< 


ON  NO  «*N 
K     *  N 

£  ^  1 


1-1 

B 

oo 
0 

y 

00 

< 


U 
D 

H 

oo 

H 

IX, 

O 

t/3 

w 

H 

e$ 
w 

(U 

0 

►J 
< 
U 

t-H 

on 
>h 

Oh 
Q 

i-l 
< 

u 

W 

U 
W 

a 
< 
pi 

w 

> 


w 


oo 
H 

oo 

H 
►J 


Q 

< 
or> 
U4 
oo 

>H 

w 
.-I 
Q 

< 
i—i 

o 

Q 
w 

w 
H 
pj 

Q 
I 

£ 
O 

p< 

H 

oo 


3 

CO 


PU 


on 


> 
< 


o 
H 


oo  w"> 
NO  — '  f*"s 
r-i    ON    O    O  <N 

odd©© 


2    NO    NO  (N 

*c    2  «  2 


o 
o 


<*N  OO  O  ©  fS 
©     ©     ©     ©  © 


iH  (\] 

OS  N 


©  © 
©  © 


© 

©    ©    ©  © 


NO  NO 

^  d  ^  ~ 


■i-  ON 

©  r*N  t-H  <N  ^N 
C"S     ©     ©     ©  C-4 

©-*©©© 


©  © 
©  © 
Tf  ON 


— i  K 


rv  © 

v>  oo 


©  © 

©  (N  <*">  "•-•> 

«-r-S     ©     ©  ©  <N 

©  — i     ©  ©  © 


©  © 

O  O    »    w  N 

NO  C-T  <N 

OO  v-v 


©  Csl 

<*-\    ©     ©    ©  C-J 


©  © 
©    ©  © 
©  NO 


K    "I    tN  v- 


N    OO  -t 


OS  N  N  ^  ^ 
<N    ©    ©    ©  <N 

©'—<©©©' 


©  © 

©  ©  NO 

©  OO  "  • 

.  -  ro  <N 

N  N  N  w 

oo  v-s 


SO  NO 


©  NO 
r*"s  © 


CO  OO 
— i  (N 

©  © 


©  © 

O  O  <N           |x  T»- 

0N  *    ^  '  f^S 

NO*"  ©  (N    ^"  *" 

OO  b-N 


C 
O 


_ 

so  a  3 

S  o  a 


.s  c 


a,  « 


— '      C  "+H 


a 

o 
o 

3  rS 


s  3 


c  °  o 

4j  <LI  <U 

(J  X  J 

3  £  E 


USf^ooooH^WpiZZ 


195 


THE      GOLDEN      GATE  BRIDGE 


-T3 
C 

rt 
■h 

a 


< 


SO  ^ 
OS    SO  rH 

rH    «^    ©  O 

©  ©  ©°  © 


o  © 

©  © 

SO    ^.    <N  I* 


as  so  cm  <*s 

i-c  oo 

os  -<f 


< 


N  SO 
K  K   1-1   m  M 

rH  1^  ©  ©  © 
©'©'©©'© 


©  © 
©  © 


3S    t-x  OS 
»    00     S©'     *  J 

r>  S  «*» 


C 


3 
00 


i— '  OS  rH  rn  Os 
<N  ©    ©  © 

©©©'©© 


©  © 
©  © 


SO 


00  so" 
rsi 


OO  r*s 
OS  (M 

fsl 


K  oo 
vs    ©  I— i    <«■»  ts, 

rH  SO  ©  ©  © 
©©'©'©© 


©  © 


SO 


©  C\l 
fS  vs 


K     »  ^     N  ,. 

rH     <^     ©     ©  rH 

©     ©     ©     ©     ©  !C 


o  © 

°    P  SO    OS    <^  fN 

-  rs!  ~  *  ° 

. — (  IX  (SI 

^  <N  V- 


CM  <^  ©  © 
©    O    ©'  © 


©  © 
©  © 
OS  00 


Tj-  ©  (N  ^ 
SO  Tf 


OO     cr>  \n 

SO  HI 


Ph 


M  O  h  m 
<s)  ©  © 

©©'©'© 


©  © 

©  ©  OS 

°V.  1  K 

+  H  N 
SO 


O    N  M 

*  «  s 


C/2 


SO  SO 

OS     ©     rH  m 

rH     SO     ©  © 

©     ©     ©  © 


©  © 

©    ©    ©    -4-   K  K 

°.  «     vd  2  ; 

N    N  ^ 
so  -<f 


so  oo 

OS  SO  rH  Cvl  OS 
rH     1^     ©     ©  © 

©©'©'©© 


©  © 
©     ©  rH 


-*f  OS  <N| 
SO  rr> 


©    SO  ^ 

k  ~  y  r 


.S  c 


a.  rt 


at 


<  -5 


^     —        C     MH     *5  f-H 


S  O 

*— ■  •— i  — 

_o  oo  a,  3 

"~  <-<        tO  sj_( 

»-  «    O  -3  ._ 

rt  «  j-;  — i 

U  i2  P<  (/i  i/i  h 


C  c/5 
O 

«  c 


o  o 


>"  W  Ph 


c 

o 

■*3    <u  iu 


196 


MATERIALS 


of  plates,  when  the  procedure  for  selecting  specimens  was  changed,  the  drillings  were 
taken  from  the  top  specimen  showing  the  highest  tensile  strength  and  from  the  bottom 
one  which  gave  the  lowest  strength.  Such  selection  of  samples  had  for  its  basis  the 
assumption  that  physical  properties  are  controlled  principally  by  chemical  composition. 

During  the  course  of  the  work,  occasion  arose  for  testing  the  entire  product  of  a 
silicon  steel  melt  which  contained  2 1  ingots.  These  ingots,  all  of  the  same  size,  were  first 
cut  into  either  three  or  four  slabs  with  differences  in  weight  allowed  to  produce  the 
desired  lengths  of  plates  and  then  rolled  into  20  by  ^4  in.  universal-mill  plates.  The 
resultant  product  was  tested  physically  at  both  ends  and  found  to  vary  in  tensile 
strength  from  93,600  to  78,200  lb.  per  sq.  in.,  while  two  check  analyses  showed  0.3  5% 
carbon  for  the  top  cut  and  0.27%  for  the  bottom. 

The  various  chemical  and  physical  properties  of  structural,  silicon  and  carbon  steels 
in  the  towers  and  the  suspension  structure  are  shown  in  Tables  4  and  5 . 

HEAT-TREATED  EYE-BARS 

The  eye-bars  incorporated  in  the  structure  are  located  in  the  cable  anchorages  and 
there  serve  to  fix  the  ends  of  the  cables.  The  bars  spread  fanwise  in  chains  of  three-link 
lengths  from  the  end  of  a  cable  to  girders  embedded  near  the  bottom  of  the  anchorage. 
The  eye-bars  are  connected  between  themselves,  to  the  strand  shoes  around  which 
cable  wires  are  looped,  and  to  the  girders,  by  means  of  pins.  There  are  1464  eye-bars  in 
the  anchorages  and  they  weigh  2520  tons. 

In  dimensions  these  eye-bars  are  alike  only  in  respect  to  width.  This  is  1 0  in.  They 
vary  in  thickness  from  1  %  in.  to  2  */&  in.,  and  in  length,  or  between  centers  of  pin-holes, 
from  33  ft.  4  in.  to  66  ft.  8  l/z  in.  The  pin-holes  have  a  diameter  of  either  10  1/32  in.  or 
11  17/32  in.  for  10  in.  and  11  ^2  in.  pins,  respectively.  The  bars  are  made  of  quenched 
and  drawn  carbon  steel  which  originated  in  basic  open-hearth  furnaces. 

For  ascertaining  quality  of  the  material,  the  methods  of  analyses  differed  somewhat 
from  those  outlined  under  structural  steel.  Unlike  the  means  employed  in  the  case  of 
the  latter,  eye-bars  had  to  be  tested  full  size  in  order  to  obtain  the  desired  information 
with  respect  to  their  physical  properties.  Such  a  testing  procedure  demanded  some  kind 
of  system  for  grouping  bars  into  lots  which  could  be  represented  by  test  bars  and  for 
this  reason  the  history  of  each  bar  became  a  matter  of  prime  importance. 

MANUFACTURE:  The  manufacturing  process  proved  to  be  uniform  with  respect 
to  principal  operations.  Briefly,  the  procedure  consisted  of  rolling  slabs  through  a 
universal-plate  mill  into  flats  of  the  desired  section  and  length,  forging  the  heads  and, 
finally,  heat-treating  the  bars.  In  the  last  step,  members  were  heated  and  quenched  one 
at  a  time,  but  drawn  two  at  a  time. 

IDENTIFICATION:  Each  eye-bar  received  numbers,  by  which  it  was  known  there- 
after, at  the  rolling  mill.  The  identifying  marks  consisted  of  melt  number  and  slab 
number.  They  were  steel  stamped  on  the  flat  deep  enough  and  at  such  place  that 


197 


THE      GOLDEN      GATE  BRIDGE 


subsequent  operations  of  forging  and  heat-treatment  would  not  eradicate  them.  Since 
the  slab  number  indicates  location  in  the  ingot,  the  eye-bar,  after  it  had  been  completely 
manufactured,  could  be  traced  to  a  top,  bottom  or  intermediate  portion  of  an  ingot 
in  a  particular  melt. 

CHEMICAL  AND  PHYSICAL  REQUIREMENTS:  Specifications  set  limits  for 
amount  of  phosphorus  and  of  sulfur  in  the  material  and  for  physical  properties  of 
heat-treated  members.  These  requirements  are  given  in  Tables  6  and  7,  respectively. 

For  obtaining  their  physical  properties,  specifications  required  full-sized  and  also 
Brinell  hardness  tests  to  be  made  on  the  completed  members.  At  least  3  bars  for  each 
100  needed  for  the  work  had  to  be  tested  to  destruction.  All  bars,  on  the  other  hand, 
had  to  be  subjected  to  Brinell  hardness  tests  as  set  forth  in  the  specifications  of  the 
American  Society  for  Testing  Materials  entitled  "Standard  Methods  of  Brinell  Hardness 
Testing  of  Metallic  Materials  (Designation  ElO-27)".  The  results  of  the  latter  tests 
were  to  be  considered  merely  as  a  rough  measure  of  the  strength  of  individual  bars. 

RESULTS  OF  TESTS:  The  two  prescribed  kinds  of  physical  tests  were  used  in 
conjunction  with  each  other  for  determining  acceptability  of  the  undestroyed  eye-bars. 
The  means  adopted  for  ascertaining  their  strength  had  as  its  working  basis  the  relation 
between  the  strengths  of  bars  destroyed  in  test  and  the  hardness  numbers  obtained  from 
the  same  bars  by  Brinell  test.  By  comparison  of  these  hardness  numbers  with  those  ob- 
tained by  Brinell  test  from  the  undestroyed  bars,  acceptability  of  the  latter  was  deter- 
mined. Test  bars,  however,  were  picked  not  alone  for  establishing  the  above  relation  but 
also  with  a  view  of  investigating  the  effects  on  their  strength,  of  irregularities  in 
manufacture. 

For  the  purpose  of  selecting  test  specimens  that  would  be  representative  of  lots  into 
which  the  bars  had  been  divided  in  a  general  Way  as  manufacture  progressed,  a  rather 
complete  history  of  each  bar  was  available.  Before  heat-treatment,  the  bar's  chemical 
analysis  was  known,  its  location  in  the  ingot  and  its  physical  properties.  After  heat- 
treatment,  additional  information  in  the  form  of  temperature  records,  Brinell  hardness 
results  and  notations  about  mechanical  treatment  were  at  hand.  With  these  data  as  a 
guide,  bars  were  selected  and  tested  during  progress  of  the  work  for  the  following 
principal  reasons,  aside  from  those  concerning  hardness  results:  Wide  variations  in 
chemical  properties  as  compared  to  the  general  run  of  bars;  unusual  heat-treating 
temperature  records;  wide  variations  in  the  preliminary  or  mill  tests  which  the  eye-bar 
manufacturer  required  on  untreated  material;  reforging  and  retreatment  operations 
and  excessive  cold-working  occasioned  by  straightening  operations. 

The  average  results  of  all  full-sized  tests,  together  with  the  extremes,  are  given  in 
Table  7.  These  results  have  been  arranged  with  respect  to  location  of  test  bar  in  the 
ingot.  They  have  not  been  corrected,  however,  for  the  slight  error  found  in  them  by 
means  of  calibration  tests  conducted  on  the  testing  machine  used  for  the  work  and  the 
Emery  testing  machine  at  the  National  Bureau  of  Standards,  U.  S.  Department  of 


198 


MATERIALS 


TABLE  6. — AVERAGE*  CHEMICAL  PROPERTIES  OF  THE  HEAT-TREATED  EYE-BARS— 
DETERMINED  FROM  LADLE  AND  CHECK  ANALYSES 


Test** 

C 

MN 

P 

S 

Si 

Specified  (max.): 

L.1L1K      _     

.... 

.... 

v.vj 

i^necK  _       

— 



U.U  > 

U.U63 

.... 

Ladle: 

Maximum  

0.39 

0.74 

0.037 

0.048 

0.14 

Average  

0.3  5 

0.64 

0.024 

0.036 

0.09 

Minimum  

0.30 

0.55 

0.012 

0.012 

0.06 

Top: 

(Quarter-Point : 

Maximum  

0.45 

0.78 

0.042 

0.056 

0.18 

Average    

0.38 

0.64 

0.025 

0.039 

0.10 

Minimum.___     

0.26 

0.53 

0.011 

0.025 

0.17 

Center: 

Maximum  

0.49 

0.77 

0.043 

0.054 

0.18 

Average  

0.39 

0.65 

0.025 

0.03  8 

0.1 1 

Minimum 

0.26 

0.53 

0.011 

0.023 

0.07 

Bottom: 

Quarter-Point: 

Maximum  

0.44 

0.76 

0.037 

0.046 

0.17 

Average....   

0.32 

0.62 

0.021 

0.033 

0.10 

Minimum     ... 

0.26 

0.50 

0.010 

0.024 

0.07 

Center: 

Maximum     ... 

0.46 

0.74 

0.036 

0.046 

0.18 

Average  

0.32 

0.63 

0.021 

0.032 

0.10 

Minimum  — _     

0.26 

0.52 

0.010 

0.023 

0.07 

*6i  Melts. 

*''See  text  for  location  of  samples  for  check  analyses. 


THE     GOLDEN      GATE  BRIDGE 


Commerce.  The  results  of  these  tests  on  a  10  by  2  in.  by  16  ft.  8  l/z  in.  bar  indicated  that 
for  the  same  elongation  the  eye-bar  testing  machine  loads  were  slightly  higher  than 
those  of  the  other  machine. 

The  Brinell  hardness  test  was  applied  to  the  member  at  points  midway  between  its 
edges.  The  test  bars  had  both  sides  measured  for  hardness  at  2-ft.  intervals.  Of  those  bars 
not  tested  to  destruction  the  short  ones  had  one  side  Brinell  tested  at  three  places,  or 
near  each  head  and  at  mid-length;  the  long  bars,  at  other  points  in  addition.  The  highest 
average  hardness  number  of  the  bars  incorporated  in  the  structure  proved  to  be  217, 
the  lowest,  179.  Average  hardness  numbers  of  the  test  bars  are  recorded  in  Table  7. 

The  average  chemical  properties  of  the  eye-bars  are  given  in  Table  6.  For  the  check 
analyses  shown  there,  samples  were  taken  from  at  least  one  top  and  one  bottom  bar  in 
each  melt.  The  test  material  was  obtained  from  the  center  of  the  flat's  cross-section  with 
a  % -in.  diameter  drill.  That  a  comparison  of  compositions  between  this  point  and  some 
average  place  could  be  made,  drillings  were  also  taken  from  the  quarter-point  in  the 
same  section  or  from  a  point  located  half  way  between  center  and  edge. 

TABLE  7.— AVERAGE  PHYSICAL  PROPERTIES  OF  THE  HEAT-TREATED  EYE-BARS— 
DETERMINED  FROM  THE  FULL-SIZED  TESTS 


Location 
of  Bar 
in  Ingot 


Ten.  Str., 
lbs.  per 
sq.  in. 


Yield  Point, 
lbs.  per 
sq.  in. 


Elong. 
in  18', 
per  cent 


Red.  of 
Area, 
per  cent 


Brinel 

No.* 


Specified: 
Minimum. 


Top: 

Maximum 
Average- 
Minimum.. 

Intermediate: 
Maximum. 
Average- 
Minimum 


Bottom: 
Maximum. 
Average  .. 
Minimum. 


Grand  Average  (a) 


80,000* 

98,100 
92,400 
87,100 

91,400 
89,400 
87,900 

91,200 
85,500 
79,700 

89,100 


50,000* 

63,200 
59,400 
56,200 

58,600 
57,400 
55,800 

58,100 
54,700 
50,400 

57,100 


8.0 

11.8 
10.0 


11.7 
10.6 
9.4 

13.4 
11.2 
7.9 

10.6 


53.7 
40.5 
24.8 

45.0 
42.1 
35.5 

50.5 
44.4 
37.3 

42.4 


214 
203 
186 

211 

197 
187 

209 
194 
179 

198 


''Hardness  number  of  any  bar  is  an  average  result. 

''"''Values  are  minimum  for  any  single  test.  Any  twelve  consecutive  tests  had  to  have  an  average  ultimate  strength  of  85,000 
and  yield  point  of  5  3,300  lbs.  per  sq.  in. 

(a)  39  Melts. 

(b)  1  bar,  10"xl/4";  28  bars,  10"x2";  15  bars,  10"x2!/8". 


200 


MATERIALS 


WIRES  AND  ROPES 

The  parts  of  the  bridge  composed  of  wires,  all  of  which  have  been  galvanized, 
are  cables  and  their  appurtenances.  The  latter  are  suspender  ropes,  hold-down  ropes  and 
wrapping  wire.  The  cables,  made  up  of  0.192  in.*  diameter  wire  spliced  with  sleeves, 
extend  from  anchorage  to  anchorage  and  pass  over  the  towers.  Suspender  ropes  are 
looped  over  bands  attached  to  the  cables  and  serve  as  hangers  for  the  floor  system.  These 
particular  ropes  have  a  nominal  diameter  of  2  11/16.  in.  Hold-down  ropes  which  are 
of  like  form  but  27/%  in.  in  diameter  are  attached  to  the  cables  in  a  similar  manner  but 
for  the  purpose  of  holding  down  the  cables  at  the  shore-ends  of  the  side  spans.  The  two 
kinds  of  ropes  and  the  cables  constitute  integral  parts  of  the  bridge.  The  hand  ropes  and 
the  wrapping  wire  are  accessories.  Hand  ropes,  1  in.  in  diameter,  are  attached  to  the 
cables  by  means  of  vertical  rod  supports.  Wrapping  wire  0.148  in.  in  diameter,  is  used 
to  cover  portions  of  the  cables  not  otherwise  sealed,  or,  generally  speaking,  those  parts 
between  cable  bands. 

Wires  used  in  the  bridge  amount  to  2  3 , 1 8  5  tons.  Of  this  quantity  21,597  tons  entered 
into  formation  of  the  cables,  1211  tons  into  construction  of  suspender  and  hold-down 
ropes  while  the  remainder  went  into  hand  ropes  and  wrapping  wire.  This  material,  with 
the  exception  of  some  cable  wire  and  the  ropes,  was  shipped  to  the  bridge  site  in  the  form 
of  bundles  or  coils  after  it  had  been  dipped  in  a  wax  (known  as  Socony-Vacuum  E.  F. 
205-15)  and  tied  with  Ys-m.  tarred  marline.  A  very  small  portion  of  the  waxed  cable 
wire  was  spliced  and  reeled  before  being  sent  out  but  the  ropes  were  manufactured 
completely,  oiled  and  put  on  reels  for  shipment. 

For  the  purpose  of  reviewing  the  quality  of  these  materials,  this  portion  of  the  report 
has  been  divided  into  three  sections:  Cable  Wire;  Ropes;  and  Wrapping  Wire. 

CABLE  WIRE:  Wire  manufacture  is  an  intricate  process;  at  least  it  embraces  more 
practices  than  are  used  for  making  any  other  kind  of  bridge  material.  When  this  is  borne 
in  mind,  as  well  as  the  fact  that  the  huge  tonnage  of  cable  wire  required  for  the  structure 
meant  production  of  thousands  of  coils,  the  necessity  for  a  system  of  identification 
becomes  apparent  as  an  important  requirement  for  ascertaining  the  quality  of  each 
melt.  Accordingly,  there  follows  a  brief  description  of  the  process  employed  in 
producing  the  wire  and  the  means  of  preserving  its  identity. 

Manufacture:  The  manufacturing  process,  in  its  simplest  steps,  consisted  of 
melting,  rolling,  patenting,  drawing  and  galvanizing  operations. 

The  steel,  made  in  acid  open-hearth  furnaces,  was  produced  in  melts  of  small 
quantity  and  handled  throughout  the  work  by  melts.  The  average  melt  contained  28 
ingots,  or  168  billets,  which  gave  154  coils  of  galvanized  wire,  each  about  380  pounds 
in  weight.  For  the  cables,  73  5  acceptable  melts  were  made  to  produce  1 13,341  coils  of 
galvanized  wire. 

*Wire  diameters  are  nominal  and  before  galvanizing,  when  not  otherwise  stated. 


201 


THE      GOLDEN      GATE  BRIDGE 


The  rolling  procedure  transformed  ingots  into  rods  and  involved  two  operations.  In 
the  first  one  the  ingot  was  brought  to  rolling  temperature  in  a  soaking  pit,  reduced  in  a 
blooming  mill  and  then  passed  directly,  without  re-heating,  through  a  continuous  billet 
mill.  In  the  second  operation  the  billet  was  re-heated  and  rolled  through  a  continuous 
mill  into  rod  form. 

The  subsequent  steps  of  manufacture,  or  patenting,  drawing  and  galvanizing  pro- 
cedures, transformed  the  rod  into  the  finished  wire  product.  In  the  patenting  process 
the  rods  underwent  heat-treatment.  The  work  was  of  a  continuous  type  because  as  one 
coil  passed  through  the  furnace  another  was  attached  to  the  disappearing  end,  the  joint 
being  disconnected  on  completion  of  its  journey.  The  treated  coils  of  rods  were  then 
passed  through  other  departments  to  be  cleaned,  pickled,  coated  with  lime  and  baked, 
or,  in  other  words,  were  prepared  for  the  drawing  operation.  In  the  latter  step  the  rods 
were  drawn  into  wire  by  pulling  them  through  dies  progressively  smaller  in  diameter. 
In  the  galvanizing  operation,  the  coils  of  wire  were  passed  through  a  molten-lead  bath, 
acid  and  fluxing  solutions,  and  finally,  through  a  spelter  bath  to  give  it  the  zinc  coating. 
The  procedure  was  a  continuous  one,  each  coil  being  attached  to  the  preceding  one  and 
then  disconnected  after  it  had  been  led  onto  a  reel.  The  coils  were  removed  from  these 
blocks  and  then  tested. 

Identification:  The  system  of  identification  described  here  was  followed  not  only 
on  wire  for  the  cables  but  also  on  rope  and  wrapping  wires.  It  was  established  for  the 
purpose  of  preserving  identity  of  the  materials  from  ingot  to  finished  product. 

The  means  of  identification  employed  varied  as  the  material  passed  from  one  stage 
of  manufacture  to  another  because  of  conditions  attending  different  steps.  When  not 
charged  into  furnaces  immediately  after  stripping  the  molds  from  them,  the  ingots  of 
a  melt  were  stacked  and  the  melt  number  painted  on  a  few  pieces  in  each  pile.  Through 
the  soaking  pit  identity  of  the  ingot  was  preserved  in  the  usual  manner,  or  by  means 
of  charging  records.  The  individual  billets,  on  the  other  hand,  were  stamped  with  the 
melt  number  at  the  billet  mill  because  they  not  only  had  to  be  stored  until  rolled  into 
rods  but  also  had  to  be  handled  with  other  steels  on  beds  provided  for  surface  inspection. 
Between  the  billet  and  the  galvanized-coil  forms  the  lot  system  was  employed,  each  lot 
being  composed  of  material  from  the  same  melt  and  marked  with  tags.  Finally,  to  each 
of  the  galvanized  coils  was  attached  a  metal  seal  bearing  a  serial  number  by  which  the 
coil  could  be  traced  to  its  melt. 

The  only  parts  of  the  material  that  required  identification  as  to  location  in  the  melt 
were  the  short  pieces  of  billets  from  which  samples  were  drilled  for  check  analyses.  These 
pieces  were  cut  from  the  top  end  of  top  billets  and  the  bottom  end  of  bottom  billets. 
Their  identity  was  carried  along  from  the  ingot  by  closely  following  the  ingot  through 
the  billet  mill.  As  the  top  end  of  the  ingot  or  the  front  end  of  the  first  billet-length 
arrived  at  the  shears  a  short  piece  was  cut  off  and  marked  with  its  identity;  the  bottom- 
end  piece  was  burned  off  immediately  after  the  last  billet-length  had  been  sheared. 


202 


MATERIALS 


Chemical  and  Physical  Requirements:  Specifications  required  chemical  analy- 
ses, physical  tests  and  the  Preece  test  to  be  made  on  the  material.  Chemical  analyses 
consisted  of  ladle  and  the  check.  Physical  tests  comprised  tension  and  wrap  tests.  The 
Preece  test  was  a  test  for  gauging  thickness  of  zinc  coating. 

For  chemical  requirements,  specifications  set  limits  for  carbon,  phosphorus  and 
sulfur.  On  ladle  analysis,  the  percentage  of  carbon  could  not  exceed  0.8  5 ;  phosphorus, 
0.04;  and  sulfur,  0.04.  On  check  analysis,  which  was  to  be  made  on  any  portion  of  the 
steel  suspected  of  being  segregated,  the  carbon  could  not  be  more  than  10%  above  the 
limit  set  for  it  on  ladle  test;  and  in  the  case  of  phosphorus  and  sulfur,  not  more  than 
25%  above  this  limit. 

With  respect  to  physical  properties,  specifications  required  tests  to  be  made  on  both 
bright  and  galvanized  wire.  These  tests  consisted  of  tension  tests  (for  strength,  yield 
point  and  elongation)  and  bend  or  wrap  tests.  For  the  bright  wire,  no  tension  tests  had 
to  be  made  but  it  had  to  be  capable  of  coiling  cold  without  sign  of  fracture  around  a 
rod  1  l/i  times  its  own  diameter.  This  test  had  to  be  made  on  10%  of  the  coils.  For  the 
galvanized  wire,  both  the  tension  test  and  the  wrap  test  were  required  but  of  these  the 
wrap  test  and  that  for  yield  point  had  to  be  made  on  only  10%  of  the  coils. 

The  Preece  test  and  a  wrap  test  were  the  means  by  which  the  quality  of  the  zinc 
coating  had  to  be  determined.  In  the  latter  test,  which  was  required  on  10%  of  the 
coils,  the  wire  had  to  be  wrapped  around  a  mandrel  1  l/z  in.  in  diameter,  and  undergo 
this  operation  without  its  coat  flaking  or  showing  cracks  visible  to  the  naked  eye.  In 
practice,  however,  this  wrap  test  was  rarely  applied  because  the  galvanizing  withstood 
the  more  severe  test  of  wrapping  the 
wire  around  a  rod  1  l/z  times  its  own 
diameter,  or  the  test  for  determining 
ductility  of  the  steel  after  galvaniz- 
ing. For  the  copper  sulphate  or  Preece 
test,  four  one-minute  immersions 
were  prescribed.  This  test  had  to  be 
made  on  at  least  5  %  of  the  coils  in  any 
lot  of  wire.  If  tests  of  any  coils  failed 
to  meet  the  requirements,  every  coil 
in  the  lot  had  to  be  tested.  During  this 
investigation,  if  less  than  20%  of  the 
coils  failed  to  pass  the  test  then  only 
the  failures  were  to  be  rejected,  but  if 
20%;  or  more  failed,  the  entire  lot  had 
to  be  rejected. 

Results  of  Tests:  Of  the  various 
tests  required  on  the  wire,  results  of 


THE     GOLDEN      GATE  BRIDG 


OS  Tt-  -t" 
m    N  H 

O    O  O 


K    N  \0 
<N  i— 

odd 


\D  N  K 
<N    <N1  ' 

odd 


l\  «"*S  O 
N    N  N 

odd 


OS  i— <  so 
<N    (N|  i— ' 

odd 


os  os  o 

m  N  N 
O    O  O 


o  o  o 
odd 


—    -<J-  N. 

Tj-     <"<-v  <N 

o  o  o 


In. 

c-i  fsi 
o  o  o 


o  o  o 
odd 


o  o  o 


o  o  o 


o  o  o 


U 


pr,    <NI  i— 1 

o  o  o 


i— i  >—>  OS 
Tj-    <NI  i-< 

o  o  o 


9\  vn  rt 
N  N  (N 
O    O  O 


O    O  O 


O    O  O 


SO  rl 

W-l     <NI  <N| 

o  o  o 


o  o  o 


*       O  O 

ni  cm  <s 

o    o  o  o 

o    d  d  d 


so  so  so 

IN.    SO  ^ 

odd 


o  o  o 


(3\    M  ^ 

so  so  vo 
odd 


o  o  o 


u 


OS  oo  In. 
odd 


os  (ni  so 
oo  oo  in. 


o  o  o 


i— I  OO 

oo   og  K 


O   o  o 


OO    OO  in. 


IN.    <-^\  O 

odd 


t  ^ 

r*S     C-l  i-" 

odd 


rj  r-4  >-< 
odd 


oo  «1  oo 
C-4    CM  i-> 


OO     r*S  OS 

<ni  (M  i-i 
odd 


OO  O 
(M    N  N 


I —  OO  fS 
fA     N  N 

o  o  o 


-f   In  tJ- 

n-i    CM  JN1 

o    o  o  o 


-4- 
o 


m  <ni  <n 
o  o  o 


-h    OS  so 

»»S    <N!  <N! 

o  o  o 


o  o  o 


o  o  o 


O  oo  K 
^  (N  M 
O    O  O 


o  o  o 


so  o 

c\  N  N 
O    O  O 


OS  ^  o 
(ANN 
O    O  O 


oo  so  t*\ 
<S    (v|  <NI 

o  o  o 


m  00  Ti- 
ro <N1  (N 
O    O  O 


O    O  O 


O   o  o 


OO  Tj-  O 
N  M  (S 
O    O  O 


O    O  O 


G 


os  so 

IS    VO  i« 

odd 


^  k  K 
in.  so  >^ 

odd 


so    OO  -H 

In.  so  so 
odd 


OO  SO 

In.    so  so 

odd 


o  o  o 


U 


o  o  o 


t  H  00 
OO    OO  In. 


fS    i-H  OS 

OO     OO  IN. 


o  o  o 


o  oo 
oo    oo  In, 

odd 


<NI  —  OS 
^   ^  <4- 

d  d  d 


M3 


Cl, 
OO 


> 

< 


a, 
co 


%  £  .3 

s  <  s 


'5  * 


a, 

CO 


<5 


<43 


a, 

CO 


<5 


J3  .hi 

u  ^ 


a>  <l> 
7     5  £  N 


c 


1  C 

O  o 


£  Q  p5  ^ 


£  £  £ 


6C  S 
C  IT 


204 


MATERIALS 


TABLE  9.— AVERAGE  PHYSICAL  PROPERTIES  OF  THE  CABLE  WIRE 


Ten.  Str., 
lbs.  per 
sq.  in. 


Yield  Point, 

lbs.  per 
sq.  in.*  (1) 


Elong. 
in  10", 
per  cent 


Diameter, 
inches 


Specified  

Maximum  (4) 

Average*  *  _ 

Minimum  (4) 


220,000  min.  (2) 
243,500 
235,600 
225,300 


160,000  min. 
188,000 
182,600 
176,000 


4.0  min. 
6.9 
6.3 
5.7 


0.192  (3) 
0.1955  (5) 


*Based  on  gross  section  which  equals  actual  cross-section  including  galvanizing. 

(1)  Yield  Point  defined  as  the  point  where  elongation  of  specimen  between  gauge  points,  originally  10  in.  apart,  is  0.70  of 
one  per  cent. 

(2)  Any  12  consecutive  tests  had  to  show  a  minimum  average  of  225,000  lbs.  per  square  inch. 

(3)  Nominal  ungalvanized  diameter  which  was  permitted  a  variation  of  plus  or  minus  0.003  in.  Average  bright  wire 
diameter  found  to  be  0.1916  in.  from  measurement  of  at  least  20  coils  per  melt. 

(4)  Average  of  a  melt. 

**Results  of  22,816  Yield  Point  tests  (two  per  coil)  representing  the  73  5  melts. 

( 5 )  Galvanized  diameter. 

chemical  and  tension  tests  only  are  recorded  in  this  report.  The  chemical  properties  of 
the  wire  steel  are  given  in  Table  8,  the  results  of  the  tension  tests  made  on  the  finished 
material,  in  Table  9. 

Check-analyses  results  for  the  wire  steel  were  derived  from  top  and  bottom  samples 
of  ingots.  The  samples  were  drilled  out  with  either  a  %  -in.  or  7/& -in.  tool  from  the  exact 
center  in  the  cross-section  of  the  short  pieces  of  2  by  2-in.  billets,  or  on  the  billet's 
longitudinal  center  line,  the  region  where  segregation  occurs.  In  Table  8,  which  covers 
not  only  cable  wire  but  also  rope  and  wrapping  wire  steel,  two  checks,  one  top  and  one 
bottom,  were  made  on  every  melt. 

For  the  cable  wire  results  in  Table  8,  two  methods  of  selecting  samples  were 
followed.  In  every  tenth  melt  both  samples  were  secured  from  the  same  ingot,  while 
in  the  remainder,  one  sample  was  taken  from  the  top  of  one  ingot  and  one  from  the 
bottom  of  another. 

In  connection  with  the  results  in  Table  9,  which  are  based  on  the  yield  point  tests, 
the  condition  of  the  specimen  as  cut  from  the  coil  had  to  be  considered  in  determining 
test  procedure.  The  specimen  had  an  arc  of  about  30 -in.  radius  from  being  coiled  on  a 
5 -ft.  take-up  block.  Experiments  disclosed  the  fact  that,  with  a  specimen  2  5  in.  in 
length,  the  12 -in.  to  14-in.  central  portion  could  be  made  straight,  as  measured  with  a 
straight-edge,  by  subjecting  the  specimen  to  a  load  of  about  700  to  750  lb.  in  tension. 
Based  on  these  data,  and  the  desire  to  keep  the  initial  or  straightening  load  to  a  minimum 
in  order  that  a  maximum  amount  of  the  stretch  defining  the  yield  point  might  be 
measured,  the  length  of  the  specimen  was  specified  to  be  25  in.  and  the  initial  load, 
860  lb.  This  load  was  assumed  to  produce  a  stretch  of  0.1  %  in  a  10-in.  gauge-length  for 
wire  diameters  in  the  specified  range,  the  stretch  being  based  on  a  modulus  of  elasticity 
of  28,750,000  lb.  per  sq.  in.  which  had  been  derived  from  tests. 

The  small  portion  of  wire  spliced  at  the  wire  plant  and  shipped  to  the  bridge  site 


205 


THE      GOLDEN      GATE  BRIDGE 


amounted  to  2424  coils  and  was  distributed  over  243  reels.  Specifications  prescribed 
for  the  splice  a  minimum  efficiency  of  95%  to  be  based  on  the  average  galvanized 
diameter  of  the  wire  and  its  specified  minimum  average  tensile  strength.  The  latter 
was  22  5,000  lb.  per  sq.  in.,  the  former,  0.195  5  in.,  resulting  in  a  minimum  breaking  load 
of  6420  lb.  for  the  splice.  Of  the  2181  joints  made  at  the  mill,  214,  or  about  one  in  every 
ten,  were  cut  out  for  test.  If  a  specimen  failed  to  develop  the  specified  load,  operations 
were  halted  and  the  splice-making  apparatus  readjusted,  but  before  resuming  the  work 
of  splicing,  each  of  three  consecutive  splices  had  to  develop  a  strength  of  at  least  6420 
lb.  The  average  breaking  load  in  the  regular  tests  proved  to  be  6920  lb.  In  the  5  tests 
which  failed  to  meet  the  requirements,  the  lowest  load  was  5  8  5  0  lb. 

The  sleeve,  in  this  splice  work,  was  pressed  on  the  wire  ends.  In  the  operation,  the 
wire  ends,  which  had  been  threaded  with  pressure  dies  for  a  length  of  about  7/$  in.  and 
made  slightly  oval-shaped,  were  inserted  into  the  sleeve,  which  had  ends  tapped  for  a 
length  of  about  %  hi.,  and  the  assembly  then  squeezed  in  a  three-part  die.  As  a 
consequence  of  this  pressing  action,  the  galvanized  sleeve,  which  could  not  exceed 
13/32  in.  in  diameter  according  to  specifications,  increased  in  length  from  2  7/16  in. 
to  about  2  J/2  in.  and  decreased  in  diameter  from  about  0.41  in.  to  about  0.39  in. 

ROPES:  Three  kinds  of  ropes  are  used  in  the  structure,  viz.,  suspender  ropes,  hold- 
down  ropes  and  hand  ropes.  The  suspender  and  hold-down  ropes  are  somewhat  unusual 
in  design  in  that  they  have  a  strand  center  instead  of  an  independent  wire  rope  center. 
However,  both  kinds  have  a  socket  on  each  end.  The  hand  ropes  are  1-in.  diameter 
strands  socketed  at  both  ends  and  composed  of  one  center  wire  0.208  in.  in  diameter 
and  two  layers  totaling  18  wires  of  0.196-in.  diameter. 

Manufacture:  The  material  for  making  the  wire,  all  produced  in  acid  open-hearth 
furnaces,  went  through  the  same  manufacturing  process  as  did  cable  wire.  Some 
exceptions  occurred  arising  from  the  fact  that  wires  of  several  different  sizes  were 
needed  for  making  the  ropes.  The  size  of  the  rods  varied  as  did  also  the  number  of  drafts 
in  reducing  these  sections  to  the  desired  wire  diameter. 

The  work  of  manufacturing  the  ropes  consisted  of  three  principal  steps,  (1) 
forming,  (2)  pre-stressing,  and  (3)  socketing.  The  manufacturer  followed  common 
practice  in  forming  or  constructing  the  rope  but  varied  from  it  by  using  butt  welds 
for  splicing  wires  instead  of  brazing  means.  To  produce  the  three  different  kinds  of 
ropes  in  the  required  number  of  lengths,  29  lengths  of  suspender  ropes  were  made,  each 
about  7100  ft.  long;  one  length  of  hold-down  rope,  1870  ft.  long;  and  9  lengths  of 
hand  rope,  each  3600  ft.  long.  These  lengths  are  known  as  manufactured  lengths  and 
contained  in  most  cases  more  than  one  member.  For  such  lengths  of  ropes,  splicing  of 
wire  coils  became  necessary  and  for  the  work  the  manufacturer  used  the  butt-welding 
method.  A  comparison  of  the  results  from  tests  made  on  butt-welded  and  brazed  joints 
gave  a  slight  advantage  to  the  work  in  the  use  of  the  former.  In  strength,  the  two  kinds 
were  practically  equal,  or  about  50%  of  the  wire  strength.  In  uniformity  of  section 


206 


MATERIALS 


at  the  splice,  however,  the  welded  joint  was  considered  superior  because  it  had  a 
continuity  that  is  difficult  to  attain  consistently  in  brazed  joints. 

The  pre-stressing  operations,  required  for  the  purpose  of  giving  ropes  the  elastic 
properties  desired,  involved  the  two  factors  of  time  and  load.  For  suspender  ropes  a  load 
of  2  50,000  lb.  was  maintained  for  14  hours  as  a  general  practice  though  in  some  cases 
the  time  period  was  extended  to  16  hours.  For  hold-down  ropes  the  load  was  3  50,000  lb. 
during  a  stressing  period  of  1 2  hours.  The  hand  ropes  were  held  in  tension  for  one-half 
hour  under  a  load  of  110,000  lb.  For  measuring  the  needed  length  of  each  piece, 
suspender  ropes  were  subjected  to  a  load  of  92,000  lb. ;  hold-down  ropes,  87,000  lb. ;  and 
hand  ropes  3  6, 5  00  lb. 

The  socketing  operation  was  a  simple  one.  After  the  ropes  had  been  cut  to  length, 
the  ends  were  spread  into  brushes  and  cleaned  of  zinc,  oil  and  dirt.  The  ends  so  prepared 
were  inserted  into  sockets  and  sealed  in  place  with  zinc. 

Chemical  and  Physical  Requirements:  The  requirements  for  composition  and 
physical  properties  of  individual  wires  were  the  same  as  those  for  cable  wire.  Specifi- 
cations required  physical  tests  on  the  suspender  and  hold-down  ropes  only.  These  tests 
had  to  be  made  for  the  purpose  of  determining  the  ultimate  strength  and  the  elastic 
behavior  of  each  type.  The  strength  tests  consisted  of  two  kinds;  in  one,  called  the 
double-part  test,  the  specimen  had  to  be  stressed  while  looped  over  a  sheave;  in  the 
other,  or  single-part  test,  the  specimen  had  to  be  stressed  in  direct  tension.  From  each 
manufactured  length  of  rope  one  specimen  for  each  kind  of  test  had  to  be  cut.  If,  after 
three  or  more  double-part  tests  had  been  made,  it  was  found  that  the  ratio  of  the  rope's 
strength  in  single-part  to  its  strength  in  double-part  was  constant,  the  double-part  tests 
could  be  omitted.  In  such  a  case  the  specified  strength  for  a  straight  rope  was  to  be 
considered  as  having  the  same  ratio  to  the  specified  strength  over  a  sheave  as  the  ratio 
established  by  the  preceding  tests.  Samples  for  both  kinds  of  tests  had  to  have  attached 
to  them,  sockets  from  among  the  extra  ones  provided  for  use  in  the  bridge. 

Suspender  ropes,  in  double-part  tests,  had  to  develop  a  total  strength  in  both  parts 
of  not  less  than  1,100,000  lb.;  and  hold-down  ropes  1,300,000  lb.  The  minimum 
efficiency  of  the  former  in  double-part  was  found  to  be  approximately  91  per  cent. 
Based  on  this  value,  a  strength  of  606,000  lb.  in  single-part  was  necessary  to  develop  the 
specified  minimum  double-part  strength.  The  corresponding  load  in  single-part  for  the 
hold-down  ropes  was  not  needed  because  no  single-part  tests  were  made  for  the  purpose 
of  gauging  its  strength  in  double-part. 

Ropes  tested  straight,  or  in  single-part,  had  to  have  strain  measurements  made  in  a 
gauge  length  of  100  in.  to  determine  their  elastic  behavior.  The  stretch  in  100  in.  from 
an  initial  load  of  5  000  lb.  to  a  load  of  190,000  lb.  could  not  exceed  0.5  in.  for  rope  not 
previously  stressed,  nor  0.3  in.  for  rope  having  been  subjected  to  repeated  loading  up 
to  190,000  lb.,  and  the  stretch  of  any  rope  could  not  vary  more  than  10%  from  the 
average  stretch  of  all  ropes  tested.  The  initial  load  of  5000  lb.  for  the  strain  test  was 


207 


THE      GOLDEN      GATE  BRIDGE 


increased  to  20,000  lb.  because  the  smaller  load  had  proved  insufficient,  in  the  first  tests, 
for  straightening  specimens  of  such  large  rope.  This  change  accordingly  led  to  a 
proportioned  reduction  of  the  maximum  amount  of  stretch  from  0.3  in.  to  0.2757  in. 
for  pre-stressed  rope. 

Results  of  Tests:  The  average  chemical  properties  for  wires  used  in  all  the  ropes 
are  given  in  Table  8,  together  with  the  requirements.  The  average  physical  properties 
are  recorded  in  Table  1 0  for  wires  incorporated  in  suspenders.  The  results  of  double-part 
tests  for  suspender  and  hold-down  ropes  are  shown  in  Table  11,  while  the  results  of 
single-part  tests  on  suspender  ropes  are  shown  in  Table  12,  together  with  the  require- 
ments in  each  case. 

In  the  various  tables  giving  results  of  tests  made  on  individual  wires,  the  testing 
procedure  was  the  same  as  that  used  in  connection  with  cable  wire  except  for  the  amount 
of  initial  load.  This  had  to  be  varied  to  suit  the  nominal  diameter  of  wires  so  that  the 
load  for  the  same  modulus  of  elasticity  found  for  cable  wire  would  produce  a  stretch 
of  0.1%  in  a  10-in.  gauge-length. 

The  double-part  tests  in  Table  1 1  were  made  over  a  sheave  having  about  the  same 
diameter  and  elliptical  shape  as  the  cable  band  groove.  The  sheave  conformed  to  the 
smallest  circumferences  or  worst  condition  that  would  be  found  in  service. 


TABLE  10.— AVERAGE  PHYSICAL  PROPERTIES  OF  THE  VARIOUS  WIRES  IN  THE 
2  11/16"  DIAMETER  SUSPENDER  ROPES 


Diameter*  in  in 

ches 

Tensile  Test  Results*  * 

Nominal 

Bright 

Galvanized 

Ten.  Str., 
lbs.  per 
sq.  in. 

Yield  Point, 
lbs.  per 
sq.  in. 

Elong. 
in  10", 
per  cent 

No.  of 
Tests 

0.203 

0.2000 

0.2038 

232,500 

178,800 

6.4 

14 

0.179 

0.1759 

0.1802 

243,500 

183,800 

6.3 

94 

0.154 

0.1511 

0.1549 

250,500 

189,900 

6.3 

230 

0.153 

0.1502 

0.1542 

252,200 

190,100 

6.2 

64 

0.136 

0.1332 

0.1369 

232,500 

182,300 

6.4 

570 

0.131 

0.1284 

0.1320 

237,500 

185,100 

6.4 

324 

0.117 

0.1142 

0.1174 

249,500 

179,600 

6.4 

288 

0.114 

0.1111 

0.1147 

234,800 

170,400 

6.7 

76 

0.103 

0.1000 

0.1037 

246,000 

178,100 

6.5 

70 

0.098 

0.0954 

0.0985 

255,800 

188,100 

6.5 

48 

*  Average  bright  wire  diameter  based  on  measurement  of  at  least  20  coils  per  melt;  and  galvanized  diameter,  on  Yield  Point 
tests  or  10%  of  the  coils. 

**A11  averages  based  on  Yield  Point  tests. 

208 


MATERIALS 


The  single-part  tests  in  Table  12  are  listed  in  the  order  in  which  manufactured 
lengths  were  made.  It  will  be  noted  that  two  tests  for  each  of  the  first  three  lengths  are 
given.  The  additional  tests  resulted  from  the  fact  that  in  all  these  pre-stressing  operations 
each  manufactured  length  had  to  be  cut  in  half  and  each  half  then  stressed  separately. 
One  test  for  each  pre-stressed  length  was  made  at  the  beginning  of  the  work  to  gauge 
the  uniformity  of  operations. 

All  single-part  tests  of  suspender  ropes  shown  in  Table  12  were  made  without  any 
more  stressing  than  that  performed  in  the  pre-stressing  operation.  However,  the 
specimen  of  the  test  noted  (b)  in  the  table  was  subjected  to  a  second  stressing  in  the 
testing  machine. 

WRAPPING  WIRE:  The  specifications  called  for  a  soft  annealed  wire  with  the 
chemical  and  physical  properties  indicated  in  Tables  8  and  13,  respectively.  No  test  for 
yield  point  was  required  but  the  physical  tests  for  other  properties  had  to  be  made  as  on 
other  wires. 

The  manufacture  of  this  material  followed  the  steps  generally  to  be  found  in  con- 
nection with  other  wires.  The  steel  was  made  in  acid  open-hearth  furnaces  although 
this  kind  of  material  is  usually  produced  by  the  basic  process.  The  rods  had  a  smaller 
diameter  and  received  a  different  number  of  drafts  in  drawing  the  wire  because  the 
finished  diameter  had  to  be  0.148  in.  The  rods  were  not  patented  but  the  bright  wire 
was  heat-treated  before  being  put  through  the  galvanizing  unit. 


TABLE  11.— RESULTS  OF  THE  DOUBLE-PART  TESTS  MADE  ON  PRE-STRESSED 
SUSPENDER  AND  HOLD-DOWN  ROPES 


Suspender  Ropes 
2  11/16"  Diameter 

Hold-Down  Ropes 
2%"  Diameter 

Manufactured 
Length, 
No. 

Ultimate 
Strength, 
pounds 

Manufactured 
Length, 
No. 

Ultimate 
Strength, 
pounds 

Specified 
Min. 

1,100,000 

Specified 
Min. 

1,300,000 

1 

1,315,200 

1 

1,472,400 

2 

1,327,400 

3 

1,338,800 

Average 

1,327,100 

2,09 


THE     GOLDEN     GATE  BRIDGE 


TABLE  12.— RESULTS  OF  THE  SINGLE-PART  TESTS  MADE  ON  2  11/16"  DIAMETER 

PRE-STRESSED  SUSPENDER  ROPES 


Manufactured 

T                     1  XT 

Length,  No. 

T  Tl  * 

Ultimate 
Strength 

Total 
Elong.  in  100", 
inches"" 

Specified 

606,000  min. 

0.2757  max. 

1  (a) 

718,600 

0.2596 

1 

738,800 

0.2602 

2 

656,200 

0.2667 

2  (a) 

726,000 

0.263  5 

3  (a) 

658,200 

0.2743 

3 

664,200 

0.2723 

4 

700,200 

0.2542 

5 

702,800 

0.2558 

6 

723,400 

0.2489 

7 

725,200 

0.2653 

8 

730,200 

0.2673 

9 

698,800 

0.2630 

10 

706,800 

0.2565 

11 

715,800 

0.2601 

12 

673,400 

0.2663 

13 

715,800 

0.2662 

14 

705,000 

0.2662 

15 

659,000 

0.285  5 

16 

686,800 

0.2659 

17 

689,000 

0.2822 

18 

690,600 

0.2716 

19 

681,400 

0.2742 

20 

679,600 

0.2786 

20 

0.2698  (b) 

21 

727,600 

0.2540 

22 

694,200 

0.25  50 

23 

728,000 

0.2524 

24 

725,400 

0.2523 

25 

725,600 

0.2572 

26 

722,600 

0.2589 

27 

692,000 

0.2576 

28 

710,600 

0.2589 

29 

691,000 

0.2559 

Average 

702,900 

0.2638 

Between  loads  of  20,000  and  190,000  pounds. 

(a)  Specimen  cut  from  manufactured  length  at  point  adjacent  to  double-part  specimen  of  corresponding  number  in  Table  11. 

(b)  Not  included  in  average;  see  text. 


2IO 


MATERIALS 


TABLE  13.— AVERAGE  PHYSICAL  PROPERTIES  OF  THE  WRAPPING  WIRE 


Specified  

Maximum  (3). 

Average**  

Minimum  (3) 


Tensile  Strength, 
lbs.  per  sq.  in.* 


85,000-100,000  (1) 
93,700 
92,200 
91,000 


Elong.  in  10' 
per  cent 


10.0  min. 
15.4 
14.8 
13.7 


Diameter, 
inches 


0.148  (2) 
0.1515  (4) 


*  Based  on  gross  section  which  equals  actual  cross-section  including  galvanizing. 

( 1 )  Any  12  consecutive  tests  had  to  show  a  minimum  average  of  90,000  lbs.  per  sq.  inch. 

(2)  Nominal  ungalvanized  diameter  which  was  permitted  a  variation  of  plus  or  minus  0.003  in.  Average  bright  wire 
diameter  found  to  be  0.148  in.  from  measurement  of  at  least  20  coils  per  melt. 

(3  )  Average  of  a  melt. 

**Resultsof  188  tests  (one  per  coil)  representing  the  11  melts. 
(4)  Galvanized  diameter. 

CAST  STEEL 

Steel  castings  used  in  the  structure  serve  a  number  of  purposes.  Saddles  on  top  of 
the  towers  provide  support  for  the  cables;  strand  shoes  are  the  means  by  which  the  cables 
are  connected  to  the  anchorages;  while  the  cable  bands  serve,  among  other  things  as  the 
method  for  attaching  suspender  and  hold-down  ropes  to  the  cables.  Cast  steel  is  also 
employed  at  points  in  the  towers  and  pylons  where  the  suspended  structure  is  hinged 
to  them.  Here  it  has  been  shaped  into  sleeves  for  the  rocker  links;  into  slotted  castings 
for  the  lateral  bracing  system;  and  into  expansion  shoes  for  roadway  members.  Miscel- 
laneously, cast  steel  is  used  for  such  members  as  pin  nuts.  All  castings  in  the  bridge  total 
1573  tons  in  weight  of  which  1545  tons,  or  nearly  all  of  the  material,  consists  of 
equipment  for  cables. 

Obviously  the  utility  of  these  castings  necessitated  members  of  various  sizes  and 
shapes.  Each  cable  saddle  is  made  of  three  segments  bolted  together  to  form  a  unit  with 
extreme  dimensions  of  21  ft.  7  in.  in  length,  10  ft.  0  in.  in  width  and  10  ft.  6%  in.  in 
height.  It  weighs  about  150  tons. 
A  complete  band  has  a  bore- 
diameter  of  3  5  15/16  in.  and  a 
length  ranging  from  1  ft.  72  in., 
for  those  used  in  attaching  hand 
ropes  to  the  cables,  to  6  ft.  3  in. 
for  the  longest  suspender  rope 
bands.  The  smallest  band  weighs 
about  one-half  ton,  and  the  larg- 
est about  4  tons.  A  strand  shoe 
has  extreme  dimensions  of  2  ft. 
by  3  ft.  1  l/z  in.  by  7%  in.  and 


Cable-saddle  segment  before  the  heads  and  the  runner  at  the  left  had  been 
removed.  Molten  metal  was  poured  into  the  mould  through  this  runner 


Segments  of  a  cable- 
saddle  ready  for 
shipment 


THE      GOLDEN      GATE  BRIDGE 


weighs  about  820  pounds.  These  three  types  of 
members  constitute  the  bulk  of  the  cable  fittings. 
None  of  the  remaining  castings  is  more  compli- 
cated in  shape. 

Of  all  the  castings,  cable  bands  proved  to  be 
the  hardest  to  produce.  The  difficulty  encountered 
in  their  production  pertained  not  to  properties  of 
the  steel,  nor  to  machine  work  but  arose  in  con- 
nection with  soundness  of  members.  The  defects 
that  developed  in  the  course  of  the  work  occurred 
not  only  in  the  cable  bands,  most  of  which  had  to 
be  replaced  before  final  acceptance,  but  also  in  the 
saddles,  two  segments  of  which  had  to  be  made 
over,  and  even  in  the  pin  nuts  and  rocker  link 
sleeves,  both  types  of  which  had  to  be  replaced  in 
their  entirety. 

Since  the  process  employed  in  producing  cable 
bands  is  the  same  as  that  for  making  other  mem- 
bers, an  outline  of  cable-band  manufacture  is 
given  below.  In  addition,  the  machine  work  on 
the  saddles  is  briefly  described  because  it  was  a 
special  process. 


MATERIALS 


Manufacture:  Seven  manufacturers  produced  all  castings  for  the  bridge.  Six  supplied 
the  cable  bands,  and  the  seventh  made  the  other  castings.  Naturally,  different  methods 
of  manufacture  were  followed  on  similar  members,  and  in  addition,  different  types  of 
furnaces  were  used  for  melting  the  steel.  Nevertheless,  founding  operations  were 
conducted  along  customary  lines. 

In  producing  a  steel  casting,  three  main  operations  are  employed.  The  first  is 
molding;  the  next,  casting,  or  pouring  the  metal;  and  the  last,  annealing.  The  mold  is 
constructed  of  sand  prepared  in  different  ways  and  into  it  molten  metal  is  poured.  After 
the  steel  has  solidified  the  resultant  member  is  cleaned  of  sand  and  subjected  to  some 
form  of  annealing  process.  The  method  used  in  making  the  mold  determines,  to  a  great 
extent,  the  soundness  of  the  casting;  the  other  operations  or  making  of  steel  and  heat- 
treatment,  control  the  chemical  and  physical  properties  of  the  metal. 

Molding  procedure  varies  in  different  plants  and  even  in  the  same  plant  dissimilar 
methods  are  employed  for  different  castings.  It  includes,  among  other  things,  provisions 
for  introducing  molten  metal  into  the  mold  as  well  as  means  of  supplying  hot  metal  to 
the  casting  during  the  period  of  solidification.  As  already  stated,  the  cable  bands  were 
made  by  several  manufacturers,  yet  in  the  four  plants  where  any  appreciable  number 
of  the  same  type  member  were  produced  three  distinctly  different  methods  of  molding 
and  casting  were  employed.  In  Fig.  8  are  three  sketches  which  indicate  the  basic  means 
employed  in  successfully  feeding  the  cable  band  castings  by  the  use  of  "heads."  In  all 
these  schemes  the  metal  was  introduced 
into  the  mold  at  its  lowest  point,  or  in 
the  standard  way.  However,  in  the  case 
of  Plan  No.  3  the  mold  was  turned  up- 
side down  immediately  after  it  had  been 
filled  with  molten  metal. 

These  molding  systems  were  devel- 
oped after  much  time  and  material  had 
been  lost  in  an  attempt  to  produce  ac- 
ceptable castings.  The  two  kinds  of 
defects  for  elimination  of  which  the 
manufacturer  strove  successfully  con- 
sisted of  cavities  and  cracks.  Cavities 
occurred  in  the  heavier  sections  of  the 
castings,  particularly  in  those  parts 
which  were  at  some  distance  from  the 
head  or  source  of  hot  metal.  They  were 
found  generally  in  the  region  of  the  bolt 
housings.  Cracks  or  tears  were  found  on 
the  bore  side  of  the  band  and  in  the  sus- 
pender-rope grooves.  This  type  of  de- 


PLAN  NO.  2 


rvff 

1  

PLAN  NO.  3 

Fic.  8 — Three  methods  of  molding  cable  bands 


213 


Half  cable-band  before  heads  had  been  removed 


feet  was  not  readily  apparent  until  the 
surface  metal  had  been  removed  by  ma- 
chine work;  nor  were  cavities  in  bolt 
housings  and  in  parts  of  other  castings, 
until  opened  by  means  of  a  drill.  To 
eliminate  waste  of  material  through  the 
machining  method,  and  to  insure  solid- 
ity in  all  parts  of  the  castings,  various 
methods  of  moldings  were  tried  in  con- 
nection with  the  bands  until  sample 
castings,  cut  up  into  sections,  proved 
the  method  to  be  successful.  The  method 
of  producing  satisfactory  cable  band 
castings  should  have  been  proved  by 
destructive  exploration  of  trial  castings 
before  attempting  to  manufacture  for 
the  order.  For  proving  soundness  of  such 
members  as  pin  nuts  and  rocker  sleeves, 
sample  ones  were  machined  before  pro- 
duction of  the  remainder  of  the  replace  castings  got  under  way. 

Chemical  and  Physical  Requirements:  The  cast  steel  members  had  to  be  manufactured 
in  accordance  with  the  specifications  for  Class  B  steel  castings  of  the  American  Society 
for  Testing  Materials  (Designation  A-27-24)  with  exceptions  as  noted  in  Table  14. 

The  required  number  of  tests  varied  with  the  size  of  the  castings.  One  tension  and 
bend  test  had  to  be  made  for  each  melt  and  annealing  charge  or  at  least  two  such  tests 
per  melt  where  castings  weighed  under  500  pounds  apiece.  Each  of  the  heavier  castings 
had  to  be  tested  by  means  of  one  tension  and  one  bend  specimen.  In  the  case  of  the 
heaviest  castings  (the  saddle  segments)  each  of  which  required  two  melts  for  its 
production,  two  tension  tests  and  one  bend  test  had  to  be  made  for  each  member. 

Results  of  Tests:  The  average  chemical  (ladle)  and  physical  properties  of  each  of  the 
three  kinds  of  steel  of  which  the  castings  are  made  are  listed  together  with  specified 
requirements,  in  Table  14.  The  specimens  used  to  determine  physical  properties  were 
machined  from  coupons  cast  integrally  with  the  castings.  The  coupon  had  cross-sec- 
tional dimensions  of  about  1 5/g  by  4  in.  for  all  castings  except  the  saddle  segments.  For 
the  latter,  the  coupon's  dimensions  were  made  about  2  l/g  by  4  in. 

Machine  Work  on  Cable  Saddles:  The  work  of  machining  surfaces  of  the  cable 
saddles  took  place  in  three  steps.  In  the  first,  the  ends  and  base  of  each  segment  were 
planed;  in  the  second,  the  cable  way  was  machined  out  after  the  three  segments  com- 
prising a  saddle  had  been  bolted  together;  and  in  the  last  step,  the  base  was  planed  to 
obtain  an  even,  finished  surface. 


214 


THE     GOLDEN      GATE  BRIDGE 


The  first  and  third  steps  were  performed  on  planers.  The  second  one  required  special 
apparatus  to  shape  the  cable  trough  and  the  grooves  at  its  bottom.  The  arrangement  for 
this  work  consisted  of  a  milling  machine  mounted  on  a  track  which  had  been  built  to 
such  a  radius  that  the  machine  could  travel  along  the  track  and  at  the  same  time  cut 
out  the  individual  grooves  to  the  required  radius. 


TABLE  14.— AVERAGE  CHEMICAL  AND  PHYSICAL  PROPERTIES  OF  THE  ANNEALED  CAST 
STEEL— DETERMINED  FROM  LADLE  ANALYSES  AND  FOUNDRY  TESTS 


Specified 


Process  of  Manufacture 


Acid 
Open 
Hearth 


Acid 
Electric 


Basic 
Open 
Hearth 


Grand 
Average 


Carbon    

Manganese  

Phosphorus: 

Acid  

Basic  

Sulfur  

Silicon  

Ten.  Str.,  lbs.  per  sq.  in  

Yield  Point,  lbs.  per  sq.  in  

Elongation  in  2",  per  cent 
Reduction  of  Area,  per  cent 

No.  of  Melts  

No.  of  Tests  


0.06* 
0.05* 
0.05* 


65,000** 
3  5,000** 

20** 

30** 


0.28 
0.66 

0.03  5 

0.037 
0.36 
72,700 
3  8,400 
28.1 
42.4 
166 
509 


0.21 
0.69 

0.023 

0.036 
0.42 
69,600 
41,400 
28.4 
41.5 
140 
381 


0.27 
0.63 


0.019 
0.034 
0.42 
70,900 
37,900 
24.9 
37.3 
54 
96 


0.25 
0.67 
0.028 


0.036 
0.40 
71,100 
39,500 
27.9 
41.6 
360 
986 


''Maximum. 
**  Minimum. 


FORGED  STEEL 

Steel  forgings  occur  in  various  parts  of  the  structure.  They  are  used  for  rollers,  pins, 
bolts,  rope  sockets  and  rope  collars.  The  rollers  are  located  on  top  of  each  tower  between 
cap  plate  and  cable  saddle.  The  pins  serve  as  connections  between  members  in  the 
anchorages,  between  ends  of  stiffening  trusses  and  rocker  links,  and  between  rocker 
links  and  pylons  or  towers.  Other  pins,  of  relatively  small  diameter,  occur  at  the  pylons 
and  towers  or  where  the  suspended  structure  is  hinged  with  respect  to  these  two  points. 
The  bolts  join  together  the  halves  of  cable  bands  and  splay  castings.  A  socket  is  attached 
to  either  end  of  suspender  and  hold-down  ropes.  The  rope  collars  are  riveted  to  top 
chords  of  the  stiffening  trusses  at  each  point  where  the  suspender  rope  leads  down 
through  the  cover  plate.  The  above  members  have  been  machined  all  over  except  in  the 
case  of  the  rope  collars  which  had  practically  no  finished  surfaces  and  in  the  case. of  the 
bolts  which  had  nearly  all  surfaces  finished. 


216 


MATERIALS 


These  members  have  been  grouped  here  because  their  manufacture  was  essentially 
the  same.  The  work  performed  on  them  may  be  divided  into  three  main  steps:  forging, 
heat-treating  and  machining.  In  the  first  step  the  pins  were  forged  from  ingots  into 
multiple-length  pieces;  the  rollers  and  the  sockets,  from  blooms  into  multiple  lengths 
also;  the  suspender  rope  collars  were  drop-forged  from  flats;  while  in  the  case  of  the 
bolts,  ends  of  rods  were  upset  by  forging  methods  to  form  heads  of  bolts.  The  heat- 
treatment  to  which  each  group  of  members  was  subjected  fell  under  one  or  another  of 
the  three  following  methods,  viz.,  quenching  and  drawing,  annealing,  and  normalizing. 
The  latter  treatment  was  applied  only  to  the  nuts  for  the  bolts. 

For  ascertaining  the  properties  of  all  forgings  excepting  the  suspender-rope  collars, 
test  specimens  were  selected  with  respect  to  location  in  the  ingot. 

Identification  of  cuts  required  no  special  work  to  be  performed  except  in  the  case 
of  bolts.  The  pins,  rollers  and  sockets  required  little  attention  in  the  way  of  identi- 
fication because,  aside  from  heat-treating,  there  were  no  operations  performed  on  them 
after  forging  from  ingot  or  bloom  before  they  were  ready  for  testing.  The  bolts,  on  the 
other  hand,  required  millwork  and  other  operations  to  be  performed  on  them  and, 
therefore,  had  to  be  followed  rather  closely  through  the  manufacturing  procedure. 
These  members  only  are  treated  below  in  some  detail  with  respect  to  manufacture  and 
identification.  The  chemical  and  physical  requirements  of  pins,  rollers  and  sockets  are 
given  in  the  accompanying  table;  the  others  are  taken  up  in  connection  with  require- 
ments and  results  only. 

The  forged  materials  are  treated  under  the  following  divisions:  Cable  Band  Bolts; 
Cable  Anchorage  Pins;  Stiffening  Truss  Rocker  Link  Pins;  Tower  Saddle  Rollers; 
Suspender  Rope  Sockets;  Allegheny  Metal;  and  Suspender  Rope  Collars. 

CABLE  BAND  BOLTS:  Cable  band  bolts  amount  to  3978  in  number.  Some 
differences  occur  in  their  detailed  dimensions  but  3602  are  alike.  The  remainder  are 
similar  except  for  their  length.  The  larger  lot  of  bolts  has  a  2%  in.  diameter  and  2  ft. 
55/g  in.  length,  the  others  a  diameter  of  2l/z  in.  but  lengths  varying  from  2  ft.  75/g  in. 
to  3  ft.  2Ys  in.  under  the  head.  The  nut  and  head  are  hexagonal.  Each  bolt  is  finished  all 
over  except  on  the  flats  and  top  side  of  head  and  nut.  These  members  are  made  of 
quenched  and  drawn  carbon  steel  except  for  the  nuts  which  are  made  of  normalized 
carbon  steel.  All  material  is  of  basic  open-hearth  manufacture. 

Manufacture:  In  addition  to  the  main  steps  of  forging  and  heat-treating  mentioned 
before,  the  material  for  the  bolts  had  to  pass  through  rolling  operations  similar  to  those 
used  in  producing  structural  steels.  In  this  procedure  the  ingot  was  made  into  blooms, 
the  blooms  into  billets,  and  the  latter  into  rods  which  were  sheared  into  short  lengths. 
On  each  of  these  short  pieces  a  head  was  forged.  These  bolt-blanks  were  then  heat- 
treated  in  a  continuous  furnace. 

Identification:  For  the  larger  number  of  bolts  the  manufacturer  used  four  melts, 
three  of  which  furnished  material  for  the  bolts,  and  the  other,  for  the  nuts.  Up  to  the 


217 


THE      GOLDEN      GATE  BRIDGE 


billet-mill  stage  this  material  was  kept  separate  by  melts  like  any  structural  steel,  but 
beyond  this  point  the  manufacturer  handled  the  top,  bottom  and  intermediate  cuts  of 
each  melt  in  groups  and  used  a  more  definite  means  of  marking  the  pieces  which  resulted 
from  subsequent  operations.  The  billets  from  each  cut  were  hot-stamped  with  the  melt 
number  every  24  in.  and,  in  addition,  were  painted  on  the  ends  to  distinguish  the  cut. 
After  they  had  been  rolled  into  rods,  the  long  melt  numbers  were  replaced  with  single 
digits  for  intermediate  cuts  and  with  letters  for  other  cuts.  During  the  process  of 
cutting  the  rods  into  short  lengths  the  operator  stamped  each  of  these  with  the  mark  of 
the  larger  piece.  From  this  point,  the  nut-blanks  needed  no  further  identification.  The 
other  small  pieces  were  separated  into  groups  having  the  same  identifying  mark  and  then 
headed  with  separate  dies  which  had  been  engraved  in  order  to  raise  the  identifying 
number  or  letter  on  the  head.  These  pieces  were  retained  in  groups  for  the  heat-treating 
operation  but  after  the  blanks  had  been  heat-treated  they  were  piled,  in  the  order 
treated,  into  lots  of  51,  except  in  the  case  of  the  top  and  the  bottom  cuts  the  number 
of  which  did  not  produce  full  lots.  To  each  lot,  which  now  contained  blanks  from  the 
same  melt  and  kind  of  cut,  was  assigned  a  number  which  was  steel  stamped  on  the  head 
of  each  bolt.  Each  finished  bolt  then,  by  means  of  the  markings  on  the  head,  could  be 
identified  with  respect  to  melt,  location  in  the  ingot  and  heat-treatment  lot. 

Chemical  and  Physical  Requirements:  Specifications  required  a  ladle  analysis  for 
composition  and  tests  for  physical  properties.  The  requirements  are  given  in  Tables  1 5 
and  1 6,  respectively. 

To  determine  physical  properties,  tension  tests  on  both  small  and  full-sized 
specimens  had  to  be  made.  One  tension  and  one  bend  test  using  standard  0.505-in. 
diameter  specimens  had  to  be  made  from  each  heat-treated  lot  of  50  bolts.  Full-sized 

TABLE  1 5 . — AVERAGE  *  CHEMICAL  PROPERTIES  OF  THE  HEAT-TREATED  CABLE 
BAND  BOLTS— DETERMINED  FROM  LADLE  AND  CHECK  ANALYSES 


Specified  (max.): 

Ladle  

Check  


Ladle 


Check: 
Top: 

Quarter-Point. 

Center  

Bottom: 

Quarter-Point. 

Center  


C 


0.55 
0.605 

0.49 


0.52 
0.56 

0.51 
0.50 


Mn 


0.53 


0.54 
0.56 

0.55 
0.55 


0.04 
0.05 

0.012 


0.015 
0.015 

0.012 
0.013 


0.05 
0.063 

0.029 


0.033 
0.037 

0.031 
0.031 


*3  Melts. 


2l8 


MATERIALS 


tests  had  to  be  made  in  sufficient  number  to  provide  a  check  on  values  determined  from 
specimen  tests. 

Results  of  Tests:  The  average  results  of  chemical  analyses  are  given  in  Table  1 5  and 
of  physical  tests  in  Tables  16  and  17. 


TABLE  16.— AVERAGE-"  PHYSICAL  PROPERTIES  OF  THE  HEAT-TREATED  CABLE 
BAND  BOLTS— DETERMINED  FROM  MILL  TESTS** 


Ten.  Str., 

Yield  Point, 

Elong. 

Red.  of 

lbs.  per 

lbs.  per 

in  2", 

Area, 

sq.  in. 

sq.  in. 

per  cent 

per  cent 

Specified  (min. )  

95,000 

60,000 

21.0 

45.0 

Maximum  

111,000 

74,500 

27.5 

64.5 

Average  

101,300 

69,300 

24.6 

62.4 

Minimum     

95,500 

62,800 

22.0 

58.5 

*80  Tests. 

**Specimens  taken  midway  between  center  and  outside  of  bolt. 


TABLE  17.— RESULTS  OF  THE  FULL-SIZED  TESTS  MADE  ON  HEAT-TREATED 

CABLE  BAND  BOLTS 


2y8"  Diameter 

2l/z"  Diameter 

Tensile 

Yield 

Tensile 

Yield 

Test  No. 

Strength, 
lbs.  per 

Point, 
lbs.  per 

Test  No. 

Strength, 
lbs.  per 

Point, 
lbs.  per 

sq.  in. 

sq.  in. 

sq.  in. 

sq.  in. 

Specified 

Specified 

Min.  * 

95,000 

60,000 

Min.  * 

95,000 

60,000 

1  (T) 

107,200 

80,400 

1 

114,600 

84,100 

2  (B) 

98,600 

76,000 

2 

109,500 

80,500 

3  (T) 

107,300 

82,100 

3 

103,100 

79,300 

4  (B) 

103,200 

74,500 

4 

109,600 

86,300 

5 

,  104,300 

85,100 

5 

105,200 

81,700 

6 

107,900 

79,300 

6 

107,800 

83,600 

7 
8 

112,000 
114,400 

83,200 
84,800 

9  (T) 

105,900 

77,700 

10 

114,000 

63,400 

11 

110,600 

83,800 

12 

111,000 

83,200 

Average 

108,300 

79,500 

Average 

108,300 

82,600 

''Based  on  cross-sectional  area  at  root  of  thread. 
T — indicates  top. 
B — indicates  bottom. 


219 


THE      GOLDEN      GATE  BRIDGE 


The  chemical  properties  were  determined  from  ladle  and  check  analyses.  For  the 
latter,  samples  were  taken  by  means  of  a  7/%-\n.  diameter  drill  at  center  and  quarter 
points  of  the  cross-section  from  two  short  pieces  of  the  5  %  in.  square  billets  repre- 
senting a  top  and  a  bottom  cut  of  the  melt. 

The  test  results  recorded  in  Table  16  were  derived  from  the  0.505-in.  specimen  tests 
of  the  2  3/g -in.  diameter  bolts  only  because  the  2  5-4 -in.  diameter  members  were  accepted 
on  the  basis  of  full-sized  tests.  Results  of  the  latter  appear  in  Table  17  together  with 
those  of  the  2% -in.  diameter  bolts.  With  few  exceptions  the  bolt  or  test-material  was 
chosen  at  random  from  each  lot.  The  exceptions  occurred  when  lots  contained  some 
bolts  treated  in  unusual  manner.  In  this  connection  two  special  procedures  were 
employed  to  straighten  bolts  and  to  fill  out  their  heads:  ( 1 )  cold-straightening  and  then 
strain-relieving  by  heat;  (2)  reforging  followed  by  regular  heat-treatment,  cold- 
straightening  and  then  strain-relieving. 

CABLE  ANCHORAGE  PINS:  These  pins,  of  which  there  are  704  in  both  anchor- 
ages, are  either  10  in.  or  1 1  l/z  in.  in  diameter,  the  latter  size  occurring  in  the  connections 
between  eye-bars  and  girders.  In  length,  they  vary  from  1 6  */g  m-  to  3  8  %  in.  Those  used 
in  connection  with  the  strand  shoes  have  threaded  ends  while  the  remainder  have  blank 
ends.  The  pin-material  is  a  basic  open-hearth  chrome-nickel  steel,  quenched  and  drawn. 
The  lomas  nuts  are  made  of  cast  steel. 

Chemical  and  Physical  Requirements:  The  prescribed  chemical  and  physical  properties 
were  the  same  as  those  for  the  heat-treated  cable  band  bolts.  They  may  be  found  in 
Tables  18  and  19  respectively.  The  number  and  method  of  selecting  test  specimens  of 
this  material  had  to  be  in  accordance  with  specifications  for  quenched  and  tempered 
forgings  of  the  American  Society  for  Testing  Materials  (Designation  A18-30) . 

Results  of  Tests:  In  Table  18  are  recorded  the  results  of  the  ladle  and  check  analyses; 
in  Table  1 9,  the  average  physical  properties. 


TABLE  18.— AVERAGE  CHEMICAL  PROPERTIES  OF  THE  HEAT-TREATED  CABLE 
ANCHORAGE  PINS— DETERMINED  FROM  LADLE  AND  CHECK  ANALYSES 


C 

Mn 

P 

S 

Si 

Ni 

▼ 

Cr 

Specified  (max.) : 

Ladle  

0.55 

0.04 

0.05 

Check  

0.605 

0.05 

0.063 

Ladle*  

0.37 

0.68 

0.020 

0.022 

0.18 

2.04 

0.52 

Check:** 

Maximum   

0.39 

0.87 

0.031 

0.022 

0.29 

3.39 

0.64 

Average  

0.36 

0.71 

0.018 

0.021 

0.24 

2.04 

0.47 

Minimum  

0.32 

0.64 

0.013 

0.017 

0.19 

1.36 

0.17 

*  5  Melts. 
**10  Tests. 


220 


MATERIALS 


TABLE  19.— AVERAGE  *  PHYSICAL  PROPERTIES  OF  THE  HEAT-TREATED  CABLE 
ANCHORAGE  PINS— DETERMINED  FROM  MILL  TESTS** 


Ten.  Str., 

Yield  Point, 

Elong. 

Red.  of 

lbs.  per 

lbs.  per 

in  2", 

Area, 

sq.  in. 

sq.  in. 

per  cent 

per  cent 

Specified  (min.)    

95,000 

60,000 

21.0 

45.0 

Maximum   

106,000 

71,000 

27.5 

62.3 

Average  

100,200 

67,800 

23.3 

56.4 

Minimum     

95,000 

62,500 

21.0 

46.8 

'76  Tests. 

** Specimen  taken  midway  between  center  and  outside  of  forging. 


STIFFENING  TRUSS  ROCKER  LINK  PINS:  There  are  24  pins,  two  at  each  end 
of  each  truss.  One  of  the  pins  connects  the  truss  to  the  rocker  link,  and  the  other 
connects  the  latter  to  tower  or  pylon  as  the  case  may  be.  They  have  a  central  diameter 
of  1 3  ^2  in.  while  one  end  is  13  Vi6  in.  and  the  other  13%6  in.  in  diameter.  They  are 
about  four  and  one-half  feet  long  and  are  threaded  at  both  ends.  The  material  is  a 
quenched  and  drawn  chrome-nickel  steel,  part  of  which  was  made  by  the  basic  open- 
hearth  process  and  the  remainder  by  the  acid  process.  The  nuts  are  carbon  steel  forgings 
the  material  for  which  originated  in  both  kinds  of  furnaces. 

Chemical  and  Physical  Requirements:  For  the  pin  material,  the  chemical  and  physical 
requirements  were  the  same  as  for  the  heat-treated  cable  band  bolts  and  cable  anchorage 
pins.  For  the  nuts,  a  material  made  in  accordance  with  the  specifications  of  the  American 
Society  for  Testing  Materials  (Designation  A18-30)  Class  F  forgings,  was  prescribed. 

Results  of  Tests:  The  average  chemical  properties  of  the  link  pins  are  given  in  Table 
20 ;  the  physical  properties,  in  Table  2 1 . 

TOWER  SADDLE  ROLLERS:  There  are  136  rollers.  These  members  are  8  in.  in 
diameter  and  9  ft.  8  %  in.  long.  They  are  made  of  carbon  steel  which  originated  in  both 
acid  and  basic  open-hearth  furnaces. 

Chemical  and  Physical  Requirements:  The  requirements  were  those  specified  by  the 
American  Society  for  Testing  Materials  (Designation  A 18-30)  for  Class  F  annealed 
forgings. 

Results  of  Tests:  The  average  chemical  and  physical  properties  of  the  material, 
together  with  specified  requirements,  are  given  in  Tables  22  and  23,  respectively. 

SUSPENDER  ROPE  SOCKETS:  Sockets  are  attached  to  the  ends  of  the  suspender 
and  hold-down  ropes.  Those  for  the  former  are  8  in.  in  diameter  and  14  in.  long  while 
the  others  are  8%  in.  in  diameter  and  18  in.  long.  The  interior  of  these  members  is 
machined  away  to  provide  a  conical-shaped  hole  into  which  the  rope  has  been  spread 
and  then  fixed  in  place  with  cast  zinc.  The  sockets  are  made  of  basic  open-hearth  steel. 


211 


THE      GOLDEN      GATE  BRIDGE 


Chemical  and  Physical  Requirements:  Specification  requirements  were  those  pre- 
scribed by  the  American  Society  for  Testing  Materials  (Designation  A18-30)  for 
Class  C  annealed  f  orgings. 

Results  of  Tests:  Together  with  specified  requirements,  Table  24  records  the  average 
chemical  properties  of  the  material;  Table  25,  the  physical  properties. 

TABLE  20.— AVERAGE  CHEMICAL  PROPERTIES  OF  THE  HEAT-TREATED  ROCKER  LINK 
PINS— DETERMINED  FROM  LADLE  AND  CHECK  ANALYSES 


C 

Mn 

P 

S 

Si 

Ni 

Cr 

Specified  (max.) : 

Ladle  

0.55 

0.04 

0.05 

Check  

0.605 

0.05 

0.063 

Ladle*  . 

0.34 

0.69 

0.028 

0.029 

0.19 

1.34 

0.69 

Check:** 

Maximum  

0.41 

0.78 

0.034 

0.034 

0.24 

1.45 

0.80 

Average  

0.37 

0.68 

0.030 

0.030 

0.22 

1.35 

0.68 

Minimum  

0.33 

0.60 

0.022 

0.018 

0.21 

1.13 

0.63 

*9  Melts. 
h*  1 5  Tests. 


TABLE  21.— AVERAGE*  PHYSICAL  PROPERTIES  OF  THE  HEAT-TREATED  ROCKER  LINK 

PINS— DETERMINED  FROM  MILL  TESTS** 


Ten.  Str., 
lbs.  per 
sq.  in. 


Yield  Point, 
lbs.  per 
sq.  in. 


Elong. 
in  2", 
per  cent 


Red.  of 
Area, 
per  cent 


Specified  (min. ). 

Maximum  

Average  

Minimum  


95,000 

112,500 
102,300 
95,000 


60,000 

76,000 
68,800 
67,000 


21.0 

26.0 
22.8 
21.0 


45.0 

64.7 
56.5 
49.1 


»  1 5  Tests. 

**Specimen  taken  midway  between  center  and  outside  of  forging. 


222 


MATERIALS 


TABLE  22.— AVERAGE  CHEMICAL  PROPERTIES  OF  THE  ANNEALED  TOWER  SADDLE 
ROLLERS— DETERMINED  FROM  LADLE  AND  CHECK  ANALYSES 


C 


Mr 


Si 


Specified 
Ladle* .... 


Check: 

Maximum 

Average 

Minimum... 


0.45 

0.51 
0.45 
0.37 


0.40  to  0.80 
0.70 

0.81 
0.71 
0.62 


0.05  max. 
0.020 

0.039 
0.016 
0.011 


0.0  5  max. 
0.028 

0.041 
0.028 
0.022 


0.25 

0.42 
0.25 
0.14 


*8  Melts. 
**2S  Tests. 


TABLE  23.— AVERAGE*  PHYSICAL  PROPERTIES  OF  THE  ANNEALED  TOWER  SADDLE 
ROLLERS— DETERMINED  FROM  MILL  TESTS** 


Ten.  Str., 
lbs.  per 
sq.  in. 

Yield  Point, 
lbs.  per 
sq.  in. 

Elong. 
in  L  , 
per  cent 

Red.  of 
Area, 
per  cent 

Specified   ...   

80,000  min. 

92,500 
86,100 
82,500 

l/z  T.  S.  min. 

51,000 
46,300 
43,500 

1,725,000 
Ten.  Str. 
(a) 

28.0 
25.5 
23.0 

2,640,000 
Ten.  Str. 
(b) 

52.0 
42.8 
31.5 

Maximum  

Average    

Minimum    

*25  Tests. 

** Specimen  taken  midway  between  center  and  outside  of  forging. 

(a)  Min.,  19%. 

(b)  Min.,  31%. 


TABLE  24.— AVERAGE*  CHEMICAL  PROPERTIES  OF  THE  ANNEALED  SUSPENDER  ROPE 
SOCKETS— DETERMINED  FROM  LADLE  ANALYSES 


C 

Mn 

P 

S 

Si 

Specified      

0.40  to  0.80 
0.60 

0.05  max. 
0.019 

0.05  max. 
0.028 

Average    

0.23 

0.20 

*3  Melts. 


22  3 


THE     GOLDEN     GATE  BRIDGE 


TABLE  2  5. — AVERAGE*  PHYSICAL  PROPERTIES  OF  THE  ANNEALED  SUSPENDER  ROPE 
SOCKETS— DETERMINED  FROM  MILL  TESTS 


Ten.  Str., 

Yield  Point, 

Elong. 

Red.  of 

lbs.  per 

lbs.  per 

in  2", 

Area, 

sq.  in. 

sq.  in. 

per  cent 

per  cent 

Specified    

60,000  min. 

x/i  T.  S.  min. 

1,700,000 

2,700,000 

Ten.  Str. 

Ten.  Str. 

(a) 

(b) 

Maximum  

67,000 

42,000 

35.5 

63.5 

Average  

66,200 

36,400 

31.9 

53.2 

Minimum  

65,000 

33,600 

27.0 

41.9 

*10  Tests. 

(a)  Min.,  2  5%. 

(b)  Min.,  38%. 


ALLEGHENY  METAL:  The  lateral  bracing  system  of  the  suspended  structure  is 
connected  to  the  towers  and  pylons  by  means  of  pins  made  of  Allegheny  metal.  These 
lateral  pins,  which  are  rectangular  in  cross-section,  vary  in  sectional  dimensions  from 
9  in.  by  1 1  in.  to  13  in.  by  18  in.,  and  in  length  from  three  to  three  and  one-half  feet. 
Other  pins  made  of  Allegheny  metal,  about  4  in.  or  less  in  diameter,  are  also  used  in  the 
structure.  In  connection  with  these  pins,  rolled  plate  washers,  also  of  Allegheny  metal, 
are  used.  The  material  originated  in  a  basic  electric  furnace  and  was  heat-treated. 

Chemical  and  Physical  Requirements:  The  chemical  composition  of  the  material  had 
to  be  in  accordance  with  that  outlined  in  Allegheny  Steel  Company's  Bulletin  33 
(1927) .  The  physical  properties  had  to  conform  to  specifications  of  American  Society 
for  Testing  Materials  (Designation  A 1 8-30)  for  Class  F  forgings. 

Results  of  Tests:  Because  of  the  limited  number  of  tests  involved,  all  results  of  physical 
tests  and  check  analyses  have  been  recorded  in  Table  26,  together  with  the  requirements. 

SUSPENDER  ROPE  COLLARS:  Each  of  the  two  pieces  forming  a  collar  is  1  ft. 
1 1 1/2  in.  long,  4l/4  in.  wide  and  Al/z  in.  high.  The  half -collars  are  made  from  basic  open- 
hearth  carbon  steel. 

Chemical  and  Physical  Requirements:  The  material  was  specified  to  be  in  accordance 
with  specifications  of  American  Society  for  Testing  Materials  (Designation  A18-30) 
for  Class  C  annealed  forgings. 

Results  of  Tests:  The  average  physical  properties  together  with  the  specified  physical 
requirements  are  given  in  Table  27.  The  forgings  were  produced  from  two  melts  of 
steel  of  the  following  average  ladle  analysis:  Carbon,  0.27;  manganese,  0.44;  phosphorus, 
0.015;  and  sulfur,  0.031. 


224 


MATERIALS 


c 


u 


o 
-6 

Pi 


a, 


in'  ^ 

2  OJ 


■<!-  Tj"  Tj- 

0  0 


SO  ©  vs 
(N    CM  o 


o  o  o  o  o  o  o 


o  o 

m    <s|  i- i 

r<^  ■<? 


r«N     m  (N| 


\C  SO  "a 
N  N 


o  o  o  o 


^"      ^"      M      CT\      VS      >A  rH 

fM    <N    (N    fN    >—  >— i 

o  ©  ©  ©  o  o  © 
©©'©'©'©©© 


»  O    0\    \C  V 

i— i    <—    <N  i— i    ©  © 
©©©©©©© 
©    ©'©'©"©'©  © 


ON  oo  oo  ON  ©  ©  <N 
c«N  ^-    tJ-    ^-  ^- 

©'©'©'©©©© 


© 

<N  rH 


<^  SO 


ON  K 

©  © 
©  © 


oo  so 

©  © 
©  © 


c*N  c«N 
©  © 


© 
© 


© 
© 


© 
© 


o 
© 


o 


00    oo    oo  oo 

©  ©  ©  © 


<ni   ©  oo 

1-fl      1-H  © 


OS 


©©©©©©© 


m    t    t    m    O    OO  \d 

so   so  so   so   i^-v  so  so 


-tf-  ©  1^ 

OO     Tj-  i— 1 

so    w~   N.  K 


"t  °°. 

©'  oo  © 
K   so   so  t\ 


>y-.    ©     ©  O 


N    N    N    N  N 


-<f  «~  © 
<N    (N  n-> 


©©©©©©© 
©©©©©©© 
©  ©  ©  ©  ©  ©  © 


©  © 
©  © 
so  so 


©  © 
©  © 
Is.  oo 


In.  oo 


©  ©  fx 
r\  is.  rt- 


©  © 

so  K 


\0  h  (\| 
OO     SO     SO  l\ 


©  ©  ©  © 

©  ©  ©  © 

OO  vs  SO 

■t  ^"  «  K 


© 
© 
© 


©©©©©©© 
©©©©©©© 

^  ©    ©    ©    ©  © 

OO    OO  OS    >-*n    so  OS 

ON    OS    OS    ON    OO    oo  OS 


©  ©  © 
©  ©  © 

©    Is.  OS 


00  ^  <S| 
ON     O0  OO 


©  ©  ©  © 

©  ©  ©  © 

©  hs  Is.  S0_ 

r-T  r-T  ©"  ©" 

ON  ON  ON  ON 


f-H  pq  H  pq  H  eo 


-o 

sC 


a. 


oo 

SO 

r»S 

V 

'-5 

OS 

oo 

-3  -5  v 

K  (N  ^ 


«AS 
J* 


225 


\ 

THE     GOLDEN      GATE  BRIDGE 


TABLE  27.— AVERAGE^  PHYSICAL  PROPERTIES  OF  THE  ANNEALED  SUSPENDER  ROPE 
COLLARS— DETERMINED  FROM  MILL  TESTS 


Ten.  Str., 

Yield  Point, 

Elong. 

Red.  of 

lbs.  per 

lbs.  per 

in  2", 

Area, 

sq.  in. 

sq.  in. 

per  cent 

per  cent 

Specified                 ...  _. 

60,000  min. 

'/2  T.  S.  min. 

1,700,000 

2,700,000 

Ten.  Str. 

Ten.  Str. 

(a) 

(b) 

Maximum  

71,000 

42,600 

36.0 

61.2 

Average  

68,400 

40,000 

33.8 

56.6 

Minimum  

66,000 

38,500 

31.0 

52.8 

*7  Tests. 

(a)  Min.,  2  5%. 

(b)  Min.,  38%. 


226 


MATERIALS 


OTHER  MATERIALS 

Among  the  different  materials  used  in  the  bridge  may  also  be  found  cast  bronze, 
rolled  brass,  rolled  aluminum,  cast  zinc,  cast  iron  and  malleable  iron.  Bronze  is  used 
principally  for  bushings  and  wearing  plates;  brass,  for  washers;  aluminum  for  expan- 
sion joint  covers;  cast  zinc,  mainly  for  fillers  between  cable  strands  and  for  fixing  rope 
ends  in  sockets;  cast  iron,  for  plugs  and  fillers;  and  malleable  iron  for  wedges. 

TABLE  28.— MATERIALS  IN  THE  MAIN  STRUCTURE,  IN  TONS 


Materials 


Anchorages 


Tower 


Pylon 


Cable 


Tower 


Cables 


Suspended 
Structure 


Structural  Steel: 

Carbon  

Silicon  


Eye-bars   

Pins: 

Steel  

Allegheny  Metal— 

Cable  Band  Bolts  

Rollers  

Cast  Steel  

Sockets  &  Collars  

Cable  Wire  

Suspender  Rope5"  

Hold-Down  Rope** 

Hand  Rope  

Wrapping  Wire  

Bronze  

Aluminum  

Cast  Zinc  

Malleable  Iron  

Railing  

Field  Ri vets  &  Bolts  (b) 


215 


330 


1,199 


2,520 


198 


27,378 
14,655 


117 
(a) 604 


!80 


30 


102 

941 
111 
21,597 
1,211 
14 
29 
334 


43 
2 


14,311 
9,010 


20 


518 
272 


Totals. 


215 


336 


3,923 


43,649 


24,414  24,15 


*12.0  lbs.  per  ft. 
(a)  Cable  Saddles. 


**1  5.7  lbs.  per  ft. 

(b)  For  anchorages  included  in  carbon  steel 


227 


FABRICATION.  MEMBERS  OF  UN- 
PRECEDENTED SIZE  BUILT  WITH 
EXTRAORDINARY  PRECAUTION 
INSURED  SUCCESSFUL  EXECUTION 
OF  THE  WORK  IN  ACCORD  WITH 
THE  DESIGN. 


2,2,9 


THE      GOLDEN      GATE  BRIDGE 


The  tower  legs  and  the  stiffening  trusses,  aside  from  the  divisions  of  tower  brac- 
ing, are  the  only  components  of  the  structure  that  had  to  be  treated  as  units  in  the 
process  of  shop  fabrication.  The  divisions  of  tower  bracing,  because  of  their 
simpler  construction  and  comparatively  smaller  dimensions,  were  readily  assembled  at 
the  shop  as  units.  But  such  complete  assembly  of  members  either  for  a  leg  or  a  truss  was 
impracticable  on  account  of  the  length  of  these  particular  units.  Even  though  facilities 
had  been  available  for  assembling  a  leg  in  full  length,  such  work  would  have  involved 
great  difficulties  because  of  its  make-up.  A  leg  has,  between  individual  members,  not 
only  horizontal  splices  but  also  vertical  joints,  the  horizontal  splices  being  spaced  in  such 
a  manner  that  members  interlock  with  each  other.  How  fitness  of  leg-members  and 
truss-members  was  secured  by  assembling  operations  conducted  on  the  parts  of  each 
unit  is  described  on  the  following  pages.  In  addition,  a  section  has  been  provided  in  this 
report  for  reviewing  the  shop  painting  operations  because  of  the  unusual  procedure 
that  had  been  prescribed  for  doing  this  work. 

TOWER  LEGS 

A  tower  leg  is  made  up  of  plates  and  angles  which  have  been  combined  to  form  a 
cellular  design.  Each  cell  is  42  in.  square,  with  five  exceptions;  one,  42  in.  by  126  in. 
in  size;  and  four  others,  each  42  in.  by  84  in.  Considering  the  larger  ones  as  multiples  of 
the  unit,  there  are  at  the  base  103  cells  of  which  44,  on  the  periphery  of  the  leg,  reach  a 
height  of  about  23  ft.  while  others  top  off  at  various  elevations  until  the  number  is 
reduced  to  2 1  near  the  top  of  the  leg. 

The  cells  in  a  tower  leg  cross-section  were  grouped  for  purposes  of  construction 
into  combinations  of  two  or  more,  each  resultant  type  being  detailed  by  short  length  or 
column  sections.  The  short  outside  combinations  were  known  as  the  X-group.  Those 
making  up  the  remainder  of  the  cross-section  were  designated  by  other  letters  as  indi- 
cated in  Fig.  9.  The  column  sections  of  which  the  cell-groups  are  composed  vary  in 
length  from  22  ft.  9  in.  to  44  ft.  1 1  in.  Cell-groups  have,  with  one  exception,  two  kinds 
of  splices.  One  has  been  called  the  horizontal  splice.  It  is  the  connection  between  sections 
in  a  cell-group  and  is  staggered  with  respect  to  splices  in  other  groups.  ( See  Fig.  10.)  The 
other,  or  vertical  joint,  has  been  termed  the  seam  splice  and  it  is  the  connection  between 
cell-groups.  The  X-group,  the  exception,  has  only  one  splice  or  that  along  the  vertical 
joints. 

Fabrication  of  column  sections  took  place  in  two  shops.  In  both  shops,  however,  the 
same  general  procedure  was  followed  although  details  of  the  performance  necessarily 
differed  because  of  dissimilarity  in  equipment.  The  one  main  difference  occurred  with 

230 


FABRICATION 


THE      GOLDEN      GATE  BRIDGE 


I   I  II 


■4Z' Girder  (b) 


Same  as  Jed/on  on  the  left 


\  T  T  1  '       Mr  T  T  n 

l*- (a)             \*-  4Z"  Girder  (a) -*\ 
IL  li  U  Jl  "  J  L....t  i  A  J  | 


Li,  U  U  4 

IZ6"Girdei 


L  =t  J] 

84' Girder  (a)  j 


h — -r-H 

^      J  -J 


84' Girder  Q>)- 


T-hoies 


dot  torn  faceUee  note) 


J 


T-holes 


r  i 

r  ~m~ 

L  J 

L 

f     f  =y=" 


84"Girder(a)- 


(Cf)- 


M 


T-hoies 


Full- sue  Method 


Sub-punch  Method 


NOTE 
Each  type  of  column 
section  built  up  from  bottom 
face  or  that  towards  bottom 
of  sketch. 


Fig.  10. — Two  methods  of  boxing  column  sections 
232 


FABRICATION 


Cap  Plate-^ 
f/ev.639'-6m  I 


Jtrut  No  I 


Jtrut  NaZ 


Strut  No  3 


Jtrut  No.  4- 


"J 


Elev.  0 


^ 


1 


- 


s 


-Jacking  Post 


XNAAPd Z 
SECTION  A-A  OF  FIG.  9 


respect  to  the  method  of  providing  holes  for  shop- 
riveted  connections.  In  one  shop  these  holes  were  either 
sub-punched  or  sub-drilled,  while  in  the  other,  many 
of  them  were  drilled  full  size  to  template.  Another 
difference  occurred  in  that  the  latter  shop  used  tack- 
welds  for  holding  parts  together  in  fitting  and  boxing 
operations.  The  way  of  performing  the  work  in  one 
will  be  called  the  sub-punch  method;  in  the  other,  the 
full-size  method. 

For  the  purpose  of  this  report,  the  fabricating  pro- 
cedures which  were  followed  have  been  divided  into 
three  principal  operations:  Fitting,  Boxing,  and  As- 
sembling. These  three  divisions  can  easily  be  recognized 
from  a  study  of  cell-group  cross-sections  shown  in  Fig. 
1 0  and  their  lengths  indicated  in  Fig.  1 1 .  Under  fitting 
operations  is  taken  up  the  construction  of  the  column 
section's  composite  parts;  under  the  boxing  operation, 
the  work  in  connection  with  combining  these  parts 
into  members  or  column  sections;  and  under  assem- 
bling operations,  the  work  that  took  place  in  connection 
with  making  horizontal  and  vertical  joints.  Before  pro- 
ceeding with  a  description  of  these  operations,  however, 
there  should  be  noted  the  work  done  in  connection 
with  templates  because  it  influenced  the  details  of 
fabrication. 

Metal  templates  were  made  principally  for  use  in 
drilling  field-rivet  holes  in  seam  splices  but  the  fabri- 
cator used  them  also  in  making  shop-riveted  connec- 
tions. Originally,  the  seam  splice  holes  were  specified  to 


3:; 


H 


Hp 

_4_|_ 

J  L 

1  i 

— -  r 

r 

44- 

i 

SECTION  B-B  of  FIG.  9 


Fig.  1  1. — Elevation  of  tower  leg  showing  horizontal  splices  and  vertical  seams 


^33 


THE      GOLDEN      GATE  BRIDGE 


be  reamed  or  drilled  with  members  assembled  at  the  shop  or  with  members  in  place  in 
the  structure.  But  before  work  commenced  on  the  towers,  decision  was  made  to  drill 
the  seam  splice  holes  to  full  size  through  metal  templates.  The  number  of  templates  and 
consequently  the  amount  of  work  involved  in  their  setting  would  have  been  enormous 
had  not  special  rules  been  instituted  for  preparing  detailed  drawings  of  the  members. 

So  that  the  amount  of  shop  work  on  the  seam  splice  connections  could  be  reduced, 
standard  rivet  spacing  and  exceptionally  large  templates  (See  Fig.  12)  were  used.  The 
spacing  of  holes  in  the  vertical  direction  was  made  3  l/z  in.,  or  multiples  thereof,  from 
the  base  of  the  leg  to  its  top.  Some  exceptions  occurred  in  detail  material  and  at  points 
near  the  top.  Horizontal  distances  between  gauge  lines  were  made  alike  for  each  cell- 
side.  In  other  words,  if  a  template  had  been  constructed  as  long  as  the  leg  and  wide 
enough  to  fit  over  a  cell-side,  it  could  have  been  set  on  any  cell-boundary  for  drilling  or 
reaming  both  shop  and  field  connections.  Furthermore,  any  portion  of  its  length  could 
have  been  applied  to  a  cell-side  because  the  spacing  of  rivet  holes  in  both  directions  was 
constant. 

The  working  templates  were  made  from  a  master  template.  They  ranged  in  thick- 
ness from  3/g  in.  to  %  hi.;  in  length,  from  about  22  ft.  to  46  ft.;  and  in  width,  from  that 
which  covered  one  seam  splice  to  that  which  extended  over  all  seam  splices  in  a  column 
section  three  cells  wide.  The  master  or  full-sized  template  was  l/z  in.  thick  and  45  ft.  6 


Fig.  12 — View  in  assembly  shed  showing  two  assemblies  of  center-span  stiffening  trusses.  Drilling  operations  are 
proceeding  on  one  while  the  other  is  being  assembled.  Starting  panels  for 
these  assemblies  are  at  the  ends  in  the  background 


FABRICATION 


in.  by  1 1  ft.  8  in.  in  out-to-out  hole  dimensions,  or  large  enough  to  cover  the  longest 
section  and  the  widest  one.  Its  accuracy  was  checked  by  means  of  the  first  full-sized 
working  templates  struck  from  it.  These  plates  had  been  drilled  while  stacked  and  this 
fact  was  utilized  in  the  checking  procedure  by  building  up  another  stack  with  the 
same  unbushed  plates  after  turning  them  different  ways  in  order  to  magnify  errors  in 
matching  of  holes.  As  they  came  from  the  original  stack,  one  plate  was  laid  on  level 
skids;  the  next  one,  "flopped  over"  on  the  opposite  side;  the  third,  turned  end  for  end; 
and  the  fourth,  turned  likewise  but  also  flopped  over.  After  this  stack  had  been  pinned 
through  perfectly  matched  holes,  a  full-sized  pin  (about  1  /64  in.  smaller  than  diameter 
of  holes)  was  tried  in  every  hole.  The  number  into  which  the  pin  would  not  enter 
without  being  forced  was  practically  negligible. 

The  possibility  of  distorting  the  working  templates  through  bushing  and  handling 
operations  also  underwent  investigation.  After  insertion  of  bushings,  no  appreciable 
amount  of  creep  in  the  templates  could  be  found  by  longitudinal  and  diagonal  measure- 
ments made  with  a  steel  tape.  Before  putting  them  into  use,  they  were  reinforced  with 
angles  or  small  I-beams  and  in  some  cases  fitted  with  eye-bolts  so  that  they  could  be 
handled  by  special  lifting  apparatus  in  as  flat  a  condition  as  possible.  After  one  tower 
had  been  completed,  the  templates  were  checked  to  determine  the  effect  of  handling 
operations  on  their  accuracy.  The  test  consisted  of  matching  holes  in  two  members, 
those  in  one  member  drilled  through  a  wide  template  and  those  in  the  other  through  a 
narrow  template  which  contained  holes  for  only  one  splice.  The  result  showed  that  mis- 
matching occurred  in  5  %  of  the  holes  and  amounted  to  a  maximum  of  about  1/32  in. 

FITTING  OPERATIONS:  The  composite  parts,  fitted  or  otherwise  prepared  for 
the  boxing  operation,  were  plates,  girder-like  pieces  and  horizontal  diaphragms.  Plates 
are  of  one-,  two-  or  three-cell  width;  some  have  detail  and  reinforcing  material  at- 
tached to  them.  The  work  of  preparing  these  parts  for  the  next  step  in  fabrication  was 
confined  principally  to  punching  and  drilling  operations.  The  girder-like  pieces  are 
also  of  one-,  two-  or  three-cell  width  and  are  referred  to  as  42-in.,  84-in.  and  126-in. 
girders. 

It  is  apparent  from  the  design  that  a  column  section  had  to  have  accurately  made 
field  connections  as  well  as  abutting  joints  if  it  were  to  interlock  with  adjacent  ones  in 
a  way  that  would  require  no  extra  work  in  the  field.  The  section,  therefore,  had  to  be 
straight  and  square,  and  also  correctly  dimensioned  in  respect  to  separation  of  webs  and 
location  of  field  holes.  Because  fitness  of  a  column  section  depended  upon  the  dimen- 
sions of  its  composite  parts,  the  fabricator  strove  to  obtain  true  horizontal  diaphragms, 
and  girders  with  exact  depth  and  straight  parallel  flanges. 

Fitting  42-in.  and  84-in.  Girders:  The  fabricator  employed  jigs  for  making  these  parts 
straight  and  true.  The  make-up  of  some  girders  prevented  their  fabrication  in  such  a 
form,  but  those  which  served  to  control  the  "packing-out"  feature  in  cross-sectional 
dimensions  passed  through  the  apparatus.  Typical  examples  of  the  first-mentioned  parts 


235 


FABRICATION 


are  noted  as  (a)  and  the  others  as  (b)  in  Fig.  10.  The  jig  was  used  for  fitting  the  web 
plate  and  flange  angles. 

The  jigs  (one  for  each  size  of  girder)  had  to  be  constructed  so  as  to  permit  manu- 
facture of  girders  which  differed  in  depth  between  flange  angles  on  account  of  the 
cell-side  thickness  and  the  presence  of  what  may  be  termed  cover  plates.  A  jig  in  its 
simplest  form  consisted  of  two  lines  of  stops  (one  along  each  girder  flange)  attached 
to  level  skids  which  had  a  separation  of  three  or  four  feet.  One  type  of  jig  (Fig.  13)  had 
two  planed  beams  for  stops,  the  planed  surfaces  of  which  provided  contact  for  girder 
flanges;  the  other  (Fig.  14)  had  individual  uprights  welded  to  each  skid.  In  the  first- 
mentioned  scheme,  one  beam  could  be  moved  for  altering  the  girder-depth.  In  the  other, 
the  jigs  had  fixed  widths  for  the  deepest  girders  so  that  fillers  had  to  be  used  along  one 
side  for  controlling  the  member's  depth. 

Fitting  126-in.  Girders:  Location  of  angles  on  the  plate  was  an  important  considera- 
tion in  fabrication  of  the  girders  because  the  position  of  angles  affected  the  width  of  cells 
which  had  to  be  square.  With  this  in  view,  the  fabricator  set  up  corresponding  rows  of 
U-shaped  clamps  on  skids  in  such  a  way  that  when  angles  were  dropped  into  them  the 
distance  between  sets  of  angles  was  correct.  The  concluding  step  of  the  operation  con- 
sisted of  placing  the  plate  on  the  angles  and  fastening  the  parts  together. 

Horizontal  Diaphragms:  These  diaphragms,  being  the  parts  upon  which  depended 
the  squareness  of  column  sections,  were  planed  or  milled  on  the  web  edges.  To  obtain 
their  maximum  efficiency,  which  occurred  when  the  web  was  pulled  to  bearing  with 
the  cell-side,  the  connection  angles  were  set  back  slightly  from  the  milled  edge. 

BOXING  OPERATIONS:  The  boxing  operations  consisted  of  assembling  the  com- 
posite parts  of  a  column  section  (See  Fig.  15),  squaring  the  section  and,  finally,  riveting 
the  parts  together. 

In  Fig.  1 0  two  methods  of  boxing  sections  are  shown.  One  was  followed  under  the 
sub-punch  method  and  the  other  under  the  full-size  method.  In  the  latter  scheme,  holes 
of  shop-riveted  connections  marked  "T"  were  made  full  size  from  templates.  In  these 
connections  the  holes  in  the  84-in.  girders  were  drilled  through  a  template,  two  cells 
wide,  set  in  relation  to  the  flange  angles;  in  the  42 -in.  girders  they  were  drilled  from  a 
narrow  template  or  one  as  wide  only  as  the  flange.  The  latter  template  required  special 
care  in  setting  operations  because  of  sweeps  in  both  template  and  girder.  To  avoid  in- 
accuracies that  might  arise  from  this  combination  of  factors,  template  center-line  was 
made  to  coincide  with  web  center-line  by  adjusting  set-screws  which  had  been  attached 
to  both  edges  of  the  template. 

The  important  matter  of  squareness  in  cells  of  column  sections  was  controlled  by 
the  use  of  required  and  "dummy"  diaphragms  as  well  as  jacks.  To  gain  full  advantage  of 
the  regular  diaphragms,  or,  in  other  words,  to  obtain  the  best  possible  bearing  between 
diaphragms  and  cell-side,  the  diaphragm  angles  were  brought  into  full  contact  with 
the  cell-web  by  means  of  complete  bolting.  At  both  ends  of  a  section,  where  diaphragms 


237 


View  of  column-sections  at  boxing  skids.  One  column-section  has  been  riveted  and  is  ready  for  the  milling 
operation;  the  other  is  in  the  reaming  and  drilling  stage 

had  not  been  provided,  temporary  plates,  squared  by  means  of  a  planer,  were  used  as 
well  as  jacks.  Trammeling  operations  for  the  purpose  of  checking  intersections  of  cell- 
web  center-lines  on  ends  of  sections  took  place  before  the  member  was  riveted  and  again 
before  it  was  milled. 

ASSEMBLING  OPERATIONS:  Two  kinds  of  assemblies  took  place  during  the 
course  of  the  work.  One  was  a  line  assembly  of  each  cell-group  (Fig.  11),  the  other,  an 
assembly  of  each  leg  top  with  part  of  the  cap  plate. 

Cell-Group  Assemblies:  With  respect  to  assembly  of  column  sections  for  a  tower  leg, 
specifications  originally  provided  that  the  horizontal  splices  be  reamed  or  drilled  with 
parts  assembled  at  the  shop,  and,  as  already  stated,  that  the  seam  splices  be  reamed  or 
drilled  either  at  the  shop  with  parts  assembled  or  in  the  field  after  the  members  had  been 
erected.  The  requirement  relating  to  the  method  of  making  the  seam  splices,  however, 
was  modified  by  the  Engineer.  Under  this  modification  the  fabricator  was  to  make 
these  joints  by  means  of  metal  templates  at  the  shop;  the  accuracy  of  results  from  the 
entire  procedure  had  to  be  checked  by  means  of  a  trial  erection  of  at  least  60%  of  the 
cell-groups  of  the  base  tier  of  one  leg.  This  demonstration  of  the  sufficiency  of  methods 
was  required  to  be  done  before  continuing  with  fabrication  of  other  cell-groups. 


238 


FABRICATION 


The  program  for  the  assembling  operations  required,  therefore,  the  work  of  as- 
sembling horizontal  splices  for  drilling  and  reaming,  and  that  of  drilling  the  seam 
splices.  Fig.  1 1  shows  the  typical  lines  of  cell-groups  that  were  assembled.  A  line  started 
with  the  base  section  and  continued  until  it  topped  out  or  merged  with  another  as  in 
the  case  of  the  P-lines  which  became  two.  Assemblies  consisted  of  three  to  eight  column 
sections  in  a  line.  In  the  sub-punch  method  the  column  sections  were  completed  to  such 
an  extent  before  assembling  that  after  they  were  placed  in  the  assembly  line  only  the 
horizontal  splices  had  to  be  reamed  to  complete  reaming  and  drilling  operations.  The 
full-size  method  followed  a  scheme  in  which  most  of  the  seam-splice  holes  had  to  be 
drilled  with  members  assembled. 

For  setting  seam-splice  templates  the  same  procedure  was  followed  in  both  the  sub- 
punch  and  full-size  methods.  All  templates  were  set  with  respect  to  the  milled  joints, 
the  elevations  of  which  (distance  from  base  of  leg)  were  recorded  as  a  part  of  the 
procedure. 

In  the  sub-punch  method  all  field  holes,  excepting  those  in  horizontal  splices,  were 
drilled  before  assembling  the  members.  The  seam-splice  holes  noted  as  holes  "H"'  in 
Fig.  1 1 ,  or  those  occurring  in  the  horizontal  splices,  were  reamed  or  drilled  through  a 
template  with  joints  assembled.  This  template,  called  a  "jumper"  template,  was  doweled 
to  some  of  the  full-sized  seam- 
splice  holes  (noted  as  holes  "S" 
in  Fig.  1 1 )  which  had  been  prev- 
iously drilled  on  either  side  of  the 
milled  joints. 

In  the  full-size  method  most 
of  the  seam-splice  drilling  took 
place  on  assembled  members. 
Only  those  seam-splice  holes  in 
the  bottom  side  of  the  member, 
or  that  face  which  rested  on 
skids  in  the  assembled  line,  were 
drilled  either  before  splicing  or 
after  disassembling.  This  se- 
quence of  handling  the  bottom 
face  affected  the  method  of  set- 
ting jumper  templates  for  holes 
"H".  When  the  work  of  drilling 
holes  "S"  was  done  before  as- 
sembling them,  the  template  was 
doweled  to  these  holes,  but  when 
holes  "S"  had  to  be  drilled  after 
disassembling  them,  the  jumper 


Trial  erection 
assembly 


THE      GOLDEN      GATE  BRIDGE 


template  was  set  with  respect  to  the  milled  joint.  In  the  latter  case  holes  "H"  as  drilled 
through  the  jumper  template  were  checked  when  the  full-size  template  was  applied  to 
bottom  face  of  member. 

Jacking  Post  Assemblies:  Each  of  these  assemblies  consisted  of  the  four  column  sec- 
tions which  form  the  top  of  the  leg,  the  jacking  posts  (which  were  temporary  members 
required  in  connection  with  adjustment  of  the  cable  saddles)  and  parts  of  the  cap-plate 
unit.  Before  assembling  these  parts,  the  column  sections  had  been  completed  except  for 
drilling  holes  in  the  cap-plate  and  jacking  post  connections.  In  the  meantime  also  the 
jacking  posts'  composite  parts  had  been  fitted,  and  the  cap-plate  unit  had  been  com- 
pleted. The  reason  for  making  the  assemblies  was  three-fold;  (1)  to  insure  flushness 
between  post  shelf  and  column  top,  (2)  to  obtain  good  bearing  between  bottom  end 
of  post  and  column  side,  and  (3)  to  locate  accurately  the  holes  in  connection  of  cap- 
plate  unit  to  leg  top. 

Attainment  of  requirements  in  connection  with  jacking  posts  necessitated  a  pro- 
gram wherein  the  posts  could  be  fitted  by  assembling  their  composite  parts  on  the 
column  section.  By  this  arrangement  the  parts  of  the  posts  were  adjusted  to  the  desired 
position  both  with  respect  to  bearing  at  the  cap-plate  and  at  the  section's  side.  To 
obtain  good  bearing  at  the  latter  point,  grinding  of  both  post  and  column-section  parts 
was  required  in  some  cases.  After  the  requirements  had  been  met,  and  before  removing 
a  post  from  the  assembly,  its  parts  were  tack  riveted  together  so  that  they  would  not 
lose  their  relation  with  respect  to  each  other  during  the  disassembling  operations. 


Tower  cap-plate  completely  assembled  in  the  shop 


View  of  assembled  tower-leg  top  showing  a  jacking  post  on  either  side  and  the  fillers  of  a  cap-plate 


STIFFENING  TRUSSES 

The  stiffening  trusses  are  of  the  Warren  type  and  are  used  in  spans  of  deck  construc- 
tion. Both  the  center-  and  side-span  trusses  are  cambered.  At  each  end  they  connect,  by 
means  of  a  pin,  to  a  rocker  link  which  in  turn  is  pinned  to  tower  or  pylon  as  the  case 
may  be.  Between  centers  of  pin  holes  in  the  center-span  trusses  there  is  a  distance  of 
4143  ft.  11^8  in.,  or  166  panels  of  24  ft.  11  9/16  in.;  the  like  dimension  in  the  side- 
spans  is  1097  ft.  5%  in.,  or  44  panels  of  24  ft.  11  5/16  in.  The  trusses  are  suspended 
from  the  cables  (at  alternate  panel  points)  by  means  of  ropes  which  pass  through  the 
top  chord  and  connect  to  verticals. 

In  the  work  of  making  the  individual  truss  members  the  fabricator  had  to  assemble 
them.  He  followed  this  course  not  only  for  obtaining  accurately  made  field  connec- 
tions but  also  for  securing  proper  adjustment  of  the  members'  detail  parts.  This  way  of 
fabricating  members  proved  to  be  a  very  convenient  one  because  it  eliminated,  before 
assembly,  the  work  of  making  otherwise  identical  members  distinctive  by  a  small  bevel 
in  field  connections  brought  about  because  of  the  camber,  and  thereby  avoided  the 
errors  with  consequent  delay  and  loss  of  material  that  could  have  arisen  from  placing 
members  in  wrong  locations  in  the  assembly.  Such  a  procedure  also  permitted  the 
fabricator  to  defer  attachment  of  detail  parts  until  the  member  had  been  placed  in  the 
assembly  when  this  material  could  be  set  with  assurance  of  correctness  in  the  fit. 


241 


THE      GOLDEN      GATE  BRIDGE 


Because  of  the  program  adopted  for  their  fabrication,  the  truss  members  before 
assembly  consisted  of  little  more  than  their  principal  elements.  No  complicated  opera- 
tions were  involved  in  their  fabrication  because  the  sections  were  simple.  Since  the 
assembling  operations  governed  chiefly  the  work  of  making  accurately  fitted  members, 
they,  as  well  as  the  measuring  operations  are  described  below. 

ASSEMBLING  OPERATIONS:  All  members  and  the  details  needed  to  make  each 
one  complete  were  brought  together  in  the  assembly.  These  details  occurred  at  the  top- 
chord  splice  joints  and  at  the  bottom-chord  end  of  each  vertical.  On  the  top-chord  they 
consisted  of  gussets,  angles  and  small  plates,  most  of  which  were  eventually  shop-riveted 
to  the  chords;  on  the  bottom-chord,  of  similar  material  and  brackets  in  addition,  most 
of  which  had  to  be  attached  to  the  verticals.  The  details  for  the  verticals  were  tack- 
riveted  while  assembled  in  order  to  maintain  their  true  relations.  Other  details,  such  as 
those  at  the  top-chord  splice  and  some  at  the  bottom-chord  splice,  were  left  loose 
because  they  had  to  be  removed  and  then  cleaned  before  riveting  them  to  members.  All 
these  details,  however,  could  not  be  assembled  at  once  because  some  pieces  had  to  be  left 
off  to  permit  the  making  of  camber  measurements,  and  others,  such  as  brackets,  could 
not  be  set  until  holes  which  they  had  obstructed  had  been  drilled. 

Assembling  work  was  begun  at  one  end  of  a  truss  and  continued  to  the  other  in  a 
succession  of  assemblies.  Specifications  required  at  least  eight  panels  to  constitute  an 
assembly  and  that  the  last  two  panels  (consisting  of  at  least  two  chord  sections,  two 
verticals  and  three  diagonals)  be  held  intact  or  reassembled  in  exact  condition  for 
starting  another  assembly.  The  fabricator  used  longer  assemblies  because  space  for  the 
work  permitted  the  extensions.  Also,  he  depended  on  intact  starting  assemblies  for  con- 
tinuations. In  the  case  of  two  side-span  trusses  the  space  was  sufficient  to  continue  with 
assemblies  in  succession  without  moving  back  any  starting  panels.  Each  of  the  other  two 
were  assembled  under  conditions  which  required  only  one  retracement  of  the  starting 
panels.  The  center-span  trusses  were  assembled  in  units  of  nine  panels  and,  therefore, 
required  forty  assemblies  for  the  two  trusses.  The  starting  panels  in  all  cases  were 
checked,  before  and  after  relocation,  with  steel  tapes  by  means  of  points  center- 
punched  on  the  two  chords. 

The  trusses  were  assembled  with  the  roadway  side  as  the  top  face  because  most  of 
the  work  took  place  on  it.  At  the  top-chord  panel  points,  templates  had  to  be  set  for 
floorbeams  and  lateral  bracing  connections;  at  bottom-chord  panel  points,  for  knee 
brace  connections.  The  bottom  face,  or  that  side  in  contact  with  the  skids,  required 
little  template  work. 

MEASURING  OPERATIONS:  The  trusses  which  extend  from  pylon  to  pylon  and 
are  supported  on  the  suspender  ropes,  have  been  designed  to  follow  a  curve,  the 
chord  of  which  could  be  passed  through  the  end  panel  points  at  the  shore-ends.  In 
fabricating  the  trusses  to  the  desired  curvature,  the  assumption  was  made,  of  course, 
that  their  supports  would  be  located  at  the  specified  elevations. 

242 


THE      GOLDEN      GATE  BRIDGE 


In  the  assembling  work,  configuration  of  the  truss  was  determined  by  ordinates 
from  the  chord  of  the  curve.  To  simplify  these  operations,  measurements  were  made 
from  a  line  laid  down,  parallel  to  the  chord,  on  each  assembly.  This  base  line  was  estab- 
lished, by  means  of  elevations,  from  the  end  of  panel  points  of  an  assembly.  One  end 
was  fixed  at  the  lower  panel  point  and  the  other  was  located  to  the  same  elevation  by 
dropping  down  a  distance  equal  to  the  difference  in  elevation  between  the  two  panel 
points.  Since  the  truss-verticals  had  to  be  set  perpendicular  at  the  chord  line,  the  base 
line  was  made  as  one  side  of  a  rectangle  which  had  a  length  of  at  least  8  panels  and  from 
which  accurate  right-angle  measurements  could  be  made. 

The  procedure  for  bringing  an  assembly  into  proper  configuration  was  one  of  trial 
and  error,  but  it  consisted  of  the  following  fundamental  steps:  After  the  splices  had 
been  made  tight  and  the  web  members  loosely  bolted  in  place,  the  panel  points  were 
established  on  top  and  bottom-chords.  The  two  ends  of  the  base  line  were  then  fixed, 
as  stated,  and  a  piano  wire,  stretched  by  hanging  weights  on  both  ends,  was  set  over 
them  and  high  enough  to  clear  assembled  members  between  the  two  panel  points.  The 
curve  of  the  top-chord  was  first  made  to  conform  to  the  theoretical  ordinates  between 
wire  and  alternate  panel  points,  or  those  where  splices  occur.  The  bottom-chord  was 
next  brought  into  line  with  respect  to  the  top  chord  by  maintaining  the  required  depth 
of  truss.  At  this  stage  of  the  work,  the  verticals  which  had  on  them  the  suspender  rope 
connections  were  set  so  that  in  each  case  the  connection  had  the  correct  relation  to 
panel  point.  After  the  curve  of  the  top-chord  and  the  depth  of  truss  had  been  assured, 
the  location  of  the  base  line  was  scribed  at  each  vertical,  the  wire  moved  to  the  bottom 
of  the  truss  and  made  parallel  to  the  base  line  and  this  location  of  the  wire  then  scribed 
at  each  vertical.  Holding  these  parallel  lines  as  two  sides  of  a  rectangle  the  other  two 
sides  were  established  by  dividing  the  rectangle  into  two  smaller  ones  and  then  making 
their  diagonals  equal  in  length.  From  a  short  side  of  the  rectangle,  panel  lengths  were 
measured  along  both  long  sides  of  the  rectangle.  Through  the  two  points  thus  estab- 
lished at  each  vertical,  a  chalk  line  was  snapped  across  the  truss'  depth.  This  line  provided 
a  reference  for  setting  the  vertical  and  also  permitted  a  check  on  the  relation,  length- 
wise of  truss,  between  top-chord  and  bottom-chord  panel  points.  After  completion  of 
measurements,  templates  for  drilling  field  connections  were  set  in  relation  to  panel 
points  and  the  various  lines. 

SHOP  PAINTING 

Shortly  after  fabrication  of  members  for  the  suspended  structure  had  gotten  under 
way,  specifications  relative  to  paint  and  painting  procedure  were  completely  revised. 
Prior  to  the  change,  one  coat  of  paint  composed  of  twenty-five  pounds  of  red  lead  to  a 
gallon  of  linseed  oil  was  applied  to  members.  For  the  remainder  of  the  work,  or  on  mem- 
bers for  the  suspended  structure,  specifications  required  from  one  to  three  coats  of  a 
paint  made  up  with  32%,  synthetic  vehicle  and  68%  red  lead.  The  one  coat  of  this  paint 
was  specified  for  only  the  top  flange  of  those  stringers  under  the  roadway  curbs  and 


244 


FABRICATION 


for  field  connections;  two  coats  for  all  other  parts  of  members;  and  a  third  coat  for 
inside  surfaces  of  box-like  members.  The  field  connections  had  to  have  this  one  coat  of 
synthetic-vehicle  paint  covered  with  one  of  a  preparation  known  as  blue  lacquer.  No 
surfaces  shop-riveted  into  contact  had  to  be  painted. 

Before  the  work  of  painting  could  be  commenced  under  the  newer  requirements, 
about  50%  of  the  suspended-structure  material  had  been  fabricated  but  not  painted. 
This  material  was  stored,  and,  in  the  interim,  a  heavy  coat  of  rust  had  accumulated 
and  the  scale  had  become  loose  over  large  areas.  The  work  of  cleaning  the  members, 
therefore,  became  a  major  operation,  in  fact  it  involved  more  labor  than  did  the  actual 
work  of  applying  the  paint. 

Cleaning  Operations:  At  the  start  of  cleaning  operations  the  ordinary  scraper  and 
wire  brush  were  used  for  cleaning  surfaces.  This  method  was  effective  though  time- 
consuming.  To  speed  the  work,  the  fabricator  devised  special  cleaning  tools.  These  tools 
consisted  of  circular  wire  brushes  inserted  in  hand-controlled,  high-  and  low-speed 
machines.  The  high-speed  ones  were  used  generally  on  flat  surfaces  or  areas  free  of 
rivet  heads  and  open  holes  because  these  details  tore  bristles  from  the  brushes,  and  there- 
fore, rapidly  reduced  the  tool's  efficiency.  The  low-speed  machines  proved  to  be  a  satis- 
factory means  of  cleaning  areas  involving  these  details  although  hand  scrapers  and  hand 
brushes  were  employed  as  well. 

The  cleaning  procedure  in  general  was  conducted  along  the  same  lines  on  all  mem- 
bers. The  members  were  dampened  or  sprayed  with  solvent  to  loosen  dirt  and  scale, 
buffed  with  brushes,  subjected  to  an  air-blast  and,  finally,  wiped  with  waste  that  had 
been  dampened  with  solvent. 

Painting  Operations:  Requirements  permitted  the  use  of  both  the  spray  and  the 
brush  for  applying  the  paint.  However,  at  the  very  beginning  of  the  paint  work, 
different  procedures  in  applying  the  paint  to  rivet  heads  and  surrounding  areas  were 
tried  because  of  difficulties  which  arose  in  properly  covering  these  surfaces.  After  a 
comparison  of  results  had  been  made,  the  following  painting  procedure  was  adopted: 
(1)  rivet  heads  brushed  with  priming  coat,  (2)  surfaces  sprayed  with  same  coat,  (3) 
sprayed  with  second  coat,  and  (4)  sprayed  or  brushed  with  third  coat.  In  the  case  of 
miscellaneous  or  small  members,  both  the  spray  and  the  brush  were  used  in  the  last  three 
steps  of  application. 

Results:  From  the  standpoint  of  appearance  of  the  paint  work,  the  results  proved 
to  be  very  satisfactory  but  not  without  first  overcoming  the  inefficiency  of  the  spray- 
method  for  applying  the  paint.  Poor  workmanship  resulted  generally  on  this  account 
around  rivet  heads,  in  confined  spaces  and  on  surfaces  which  were  not  sprayed  in  a 
downward  direction.  Directing  the  spray  upward  never  produced  satisfactory  results, 
and  not  always  when  directed  horizontally,  because  the  operator,  on  account  of  the  fog 
set  up,  could  not  follow  easily  the  results  of  his  work,  particularly  at  ends  or  edges  of 
materials.  As  a  result,  the  operator  tended  either  to  flood  or  barely  cover  surfaces  with 


245 


THE     GOLDEN      GATE  BRIDGE 


sprayed  paint.  The  disadvantages  which  were  revealed  during  the  course  of  spraying 
operations  were  overcome  by  brushing  as  a  preliminary  step  before  spraying,  by  turning 
members  to  permit  downward  spraying  and  by  developing  ways  of  applying  this  paint 
with  a  spray.  For  example,  in  the  case  of  some  floorbeams  and  chord  sections  which  pre- 
sented surfaces  for  upward  spraying  operations  because  the  members  could  not  be 
turned  conveniently,  such  underside  surfaces  were  brushed  either  partly,  as  around 
rivet  heads,  or  completely,  before  being  sprayed  with  a  like  coat.  On  members  which 
presented  vertical  surfaces  for  spraying,  a  technique  consisting  of  two  steps  was  finally 
developed  which  produced  excellent  results.  In  the  first  step  the  surface  received  a  light 
spray.  By  the  time  the  surface  was  covered,  the  quick-drying  quality  of  the  paint  per- 
mitted the  operator  to  take  the  second  step,  or  to  spray  the  surface  a  second  time.  This 
routine  allowed  the  operator  to  cover  surfaces  thoroughly  without  piling  up  the  paint. 


246 


PLATE  I 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  CAL. 


PROJECT  REPORT  OF  CHIEF  ENGINEER 
SEPTICMBER  30,  1937 


MAIN  BRIDGE 
PLAN  AND  ELEVATION 

SCALE  IN  FEET 

100         0     900   WOO 


PLATE  II 


so'-o 


Section  'B_B' 


nie  concrete  for  fender  to  £/er.  *5.Q 

/  for  fier  to  C/er.  -35.0'. 

other  concrete  poured  in  the  dry . 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  CAL. 


PROJECT  REPORT  OF  CHIEF  ENGINEER 
SEPTEMBER  30,  1937 


SAN  FRANCISCO  PIER 
GENERAL  PLAN  AND  SECTIONS 


TuuuuJ 


SCALE  IN  FEET 
to 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  CAL. 


PROJECT  REPORT  OF  CHIEF  ENGINEER 
SEPTEMBER  30,  1937 


CABLE  ANCHORAGE 
CABLE  BAND  &  STRAND  SHOE 

SCALE  IN  FEET 
10  o  to  to  io  40  ao 

I  I  I  I  I  I  I 


PLATE  IV 


■I'J 

Section  ,r_r'  ,  View's- 6" 


Elevation 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  CAL. 


PROJECT  REPORT  OF  CHIEF  ENGINEER 
SEPTEMBER  30,  1937 


StW  ffnclvrmlarhn  sktl.  ualiu 

^triyhc  nehd- 

th  -l'*CACt0l as ne/af. 


CABLE  TIE-DOWN  AT  PYLONS 
ASSEMBLY  AND  DETAILS 


SCALE  IN  FEET 


PLATE  IV 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  CAL 


Socket  End  of  Rod 


DETAIL  of  TIE  DOWN  GIRDER  a  JACKINS  BEAM 


PROJECT  REPORT  Of  CHIEF  ENGINEER 
SEPTEMBER  .V).  1937 


Ocncivm-  Note  - 


>.F.  PUBLIC  LIBRARY^' 


■gWJfrxWA'V  Mr/,  —it* 


CABLE  TIE-DOWN  AT  PYLONS 
ASSEMBLY  AND  DETAILS 


V  (si  ^ 

U  "         1-7-7     1  A 


1-3? 


-I-Pl.a.i 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  CAL. 


-v  PROJECT  REPORT  OF  CHIEf  I  \(.IM  1-  It 

^    .     i.  SEPTEMBER  30,  IW 

-/-Pi  17.1 


MAIN  TOWERS 
SECTIONS  SHOWING  MATERIAL 


SCALE  IN  FEET 


rvrrrnr 


PLATE  VI 


| 

— 1 

■<-iu.i 

I 

jl-flH.i' 

Hi 

^iJiUt 

M 

I 

4ftu.t 

SECTION  f\-l 


^iJsUt 
SECTION 

Dimeraiono  and  material  same  a 
for  SKJian'A'.cjtcepr  03  sAoatj 


4-rlvi. 


f-nuX,  frmX 


SECTION  B-l' 

 tt'-9<» 


tn. 


^iafsUt 


SECTION  B-Z 


_  3^i 

r  

5l 

'  lot  shaft 

SECTION  B ' 


i-rlnX 


\Cnd  of  diaphragm  josl  helot* 
''—yop  row  of  home1"1 
Sec/ion  C. 


shaft 

SECT/ON  'El 


Dolled mattnal l0  aoove 7  ^iotshaff 

i  ^v^^       section  a  ■ 


rl-ri.tiX 


1-U.t.i- 

l-rto.r 


sect/on  'd-i  ' 


-i-rfu.i' 
rhrteX 


3 


i9/15£"  SECT/ON 


nll  ljya'jjtl — sections  shown  anr  symmetrical ohoot  ioth 

For  ttind at material  and  location  at  sections,  are  sheet /V.  OS 
nil  L'a.e.i', except  03  noted 
nil  Fls  lihick  .except  o,  noted 
Main  marmot  only  13  onown . 


S.F.  PUBLIC  L!31~;AR V 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO.  CM. 


PROJECT  REPORT  OF  CHIEF  ENGINEER 
SEPTEMRER  30,  l<M7 


of  shaft 

SECT/ON  E-Z' 


MAIN  TOWERS 
SECTIONS  SHOWING  MATERIAL 


SCALE  IN  FEET 


PLATE  VII 


View'B-B" 


S.F.  PUBLIC  LIBRARY 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  GAL 


PROJECT  REPORT  OF  CHIEF  ENGINEER 
SEPTEMBER  30,  I W7 


eral  Notes: - 

material  marhcd  s  -  Structural  Silicon  sttel 

Material  marked  c  —Structural  Carion  steel. 

7amr  cell  nebs  spaced  S'i'c.tuc 

Ladder*  full  height  ot  each  cell,  except  ateteratar  shaft 

Cast  shall  et San 


MAIN  TOWERS 
DETAILS  OF  TOWER  BASES 


SCALE  IN  FEE  I 


PLATE  VIII 


 r  jof avfih.lilfim.iMM  SAN  FRANCISCO,  CAL. 


PROJECT  REPORT  OF  CHIEF  ENGINEER 
SEPTEMBER  30,  19.17 


Beneral  Notes:- 


r-r 


RAPY 


Mafena/fnarfad  3- sinxlvral  Silicon  $fal. 
tfa/tnalmari«J  c  -  Slruclural  Carbon  Sletl 
Totrer  <rt//*rfo  spacta"  3li  e  If  c 
la&krs  loll  tmqkloltach  ceil, ttcxplal 
tteralor  shall 

Slrvf  enclosure  is  nol  shoiyn  on  Ih/s  drawing 
Cosl  Shall ol San  Francisco  Tbtvtr  shown. 


MAIN  TOWERS 
DETAILS  AT  STRUT  NO.  3 


SCALE  IN  FEET 


PLATE  VUI 


View  'A  A" 


Sccton'P-P*  matJi'-^ 

«       Secto*'  f-T" 


rfj'.-i  V-Mrtf.lt  *|  Sector  R-R  , 
kxrrcw'N-N'  i"*^  "5  * 


5ecTo-j'L-L* 


3CCTO/3-3'  3ccrttx'V-V 


^^^^^ 

£~  4  l/tMlK  )           tit  *»  / 

THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO.  CAL 


PROJECT  REPORT  <>y  CHUB  ENGINEER 
si  I'll  Mill  li  Ml,  1«7 


Bottom  Cmoro  -  Section  T~  F' 


S.F.  PUBLIC  LIBR  *  HY  " 


Oc*wm.  Notes. - 

-XIhiWiMhAc' 

MM 


MAIN  TOWERS 
DETAILS  AT  STRUT  NO.  3 


SCALE  IN  PBBT 


Qeneral  Note: 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  CAL. 


Afa/ena/  rfrudoraf  $11  icon  j/rr/, 
Ctui  Sha/hf ton 


PROJECT  RKPORT  OF  CHIEF  ENGINEER 
SEPTEMBER  30,  1937 


MAIN  TOWERS 
DETAILS  OF  TOWER  TOPS 


SCALE  IN  FEET 


I 


/./'S  W  L-  I       BeJyveen  all 


Center  5/rot 


THE  GOLDEN  GATE  BRiDGE 

SAN  FRANCISCO,  CAL, 


f^**&r//>L-  GS  denote.  Carbon  skri 
VETS     1%  aknt"^"  Si/icon  5/eel. 


PROJECT  REPORT  OF  CHIEF  ENGINEER 
SEPTEMBER  30,  19.17 


°€H  HOLESr  g'* 

T5k^tnTs  ^mt*  CROSS  -  SECTION 

^t^Zf^z^  SHOWING  TYPICAL  FLOORBEAM 


S<  \  I  E  i\  ill  i 


I-S-9S 


PI- ATK  X 


SECTION  /)-/)' 


SECTION  D-D 


FLOOR  BEAM  AT  POINTS  d9  a  50 

Paris  nol  snnyrt  surre  as  fr  7tf*cal  fow  3carr> 


PLATE  XI 


/LJi'it'i  C.S.  Cut  0.3  leg  ot  fS° 
rl-Pl.B'l&S. 


6f  Si 


Drill  'i'^boka  for  privets 


'-Tie  P/,313  *i  C.S. 


"Till 
ft 


%  drilled  holes  for  f  bolts 

Surface  grind  for 
rrmaml  of  fins. 


Sorfotze  grind  for 
rrmoml  of  fins. 


<~~3potfoct  for  bo/f  heads  amis 


_J-'OiRod. 

—  Dio.  to  suit 
Suspender  Rope 


rZ-L>  r&'T&'l  S.S. 


SPLIT  COLLAR 

Orop  Forging 


member  U53-L5t"" 
2- IS  h  SI.  9  1 
Tie  Pis.  36'%.  rC.S. 

o.L.H>li  J 


it  5 


1  "I 

r  <^  *i  ™3  5 
•  ;  *.     a>  i.- 


^  V 


Li"""5 

^  ( Diaphragm 
<t-Ls7'd-g' 
4-eS'3i'i  ,  i 
l-Web  PI.3ZS.I 
Z-Fills  Ifi'l 


—c.s. 


Chp  0.5.  leq  45° 

Suspender  Connection 
2-L*g>4"fTop  1 
8ShffLs  S,4,§  ! 

Z-L'S'6'%Bo+t.  j 


Contractor  to  furnish  such 
shims  as  are  required  for' 
proper  adjustment  for  stiffening  truss 


For  detoil  see  sheet  No.B73 


SECTION  B-B 


17- *bolt 

section  c-c  V-p<-  '"LD-  p'Pe 

GENERAL  NOTESr 

For  knee  brace  conn,  to  verticols  and  bottom  chord  see  sheet  No.  873 

Truss  to  be  detailed  to  moke  honqers  ond  posts  vertical  under  full  dead  lood  and 

normol  temperature 
Splices  at  U47toU67  inch  some  as  shown  fbr  U53  except  for  fills 

~    LIB  to LiB  incl.  some  as  shown  for  L5Z 
ffaterial 

S.S.  denotes  Silicon  Steel. 
C.S.      ■■  _      Corbon  Steel 

Rivets  I  *  except  g  *  in  Si  legs  of  verticols  ond  laced  leqs  of  dioqonols 
Open  holes  Ifc*  except  as  noted 

Hoximum  pitch  of  rivets  not  shown  in  chords  and  verticols  to  be  6' 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  CAL. 


PROJECT  REPORT  OF  CHIEF  ENGINEER 
SEPTEMBER  30,  1937 


STIFFENING  TRUSS 
TYPICAL  PANEL  OF  CENTER  SPAN 


-l-PI.  26'i  C.S. 


SCALE  IN  FEET 

■  > 


PLATE,  M 


Drill  for  £  *  turned  bolts  t  ttqhr  dnvmq 


Ctak.tchipt*ih"**»«<web\  |  Ctskachipneors.de  HtO*i/t 

or*  fler.ee  t!  f 

1/1     H  .  /'PI.  JO-/  S.J. 


Sp  CO  *  0*!  U47+oU67  met.  <J#  jAotw)  <%r  f  JJ  eicep*  for  f'lls 

•    14B  toLid  mcl.  soma  OS  sno*nfbr  LX 

3J.  denotes  Silicon  Steal 
CS.       •  Carbon  Steal 

\pt  $'*  in  3k  teas  *f  varticolM  and  toced  'cos  of 
Open  holes  ',%'* except  as  noted 

ffoMtmvm  pitch  of  rivets  not  snoivn  m  cnordj  and  rerticols  -to  be  t 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  CAL. 


S.F.  PUBLIC  LIBRARY  r 


PROJECT  REPORT  OF  CHIEF  ENGINEER 
SEPTEMBER  SO.  1937 


STIFFENING  TRUSS 
TYPICAL  PANEL  OF  CENTER  SPAN 


SCALE  IN  FEET 
!       I  ' 


jEBfVff 


PLATE  XII 


Side  5pa, 


S.F.  PUBLIC  LIBRARY 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO,  CAL. 


PROJECT  REPORT  OF  CHIEF  ENGINEER 
SEPTEMBER  30,  1937 


ROADWAY  AND  LATERAL  JOINTS 
AT  THE  MAIN  TOWERS 


SCALE  IN  FEET 


PI, A  I  f.  XII 


ROADWAY  AND  LATERAL  JOINTS 
AT  THE  MAIN  TOWERS 


Section '□-[}' 


Section  'B  B' 

Xclton  'C'C'fmtkr 


SUPPLEMENT  TO  THE 

FINAL  REPORT   OF   THE   CHIEF  ENGINEER 

SEPTEMBER,  1937 


By 

CLIFFORD  E.  PAINE 


P  U  B  1  I  S  ] 

GOLDEN  G A 
AND  HIGHWJ 


SIDGE,  HIGHWAY  AND 
'ATION  DISTRICT 

MB  ER   19  7  0 


This  edition  of  the  "Report  of  the  Chief  Engineer  to  the  Board  of  Directors  of  the 
Golden  Gate  Bridge  and  Highway  District"  has  duplicated  in  every  detail  the  original 
work  written  by  Joseph  Strauss  upon  completion  of  the  Golden  Gate  Bridge  and 
published  in  January,  1938.  One  third  of  a  century  later,  the  District  is  reprinting  the 
Report  so  that  public  libraries,  technical  reference  works,  consultants,  and  others  with 
a  need  to  know  the  District's  history  and  highlights  of  the  span's  structural  design 
may  have  copies  available.  The  5000  copies  originally  printed  have  been  depleted  for 
many  years,  and  originals  are  virtually  unobtainable. 

In  addition  to  the  Chief  Engineer's  Report,  this  edition  contains  supplementary 
information  on  modifications  to  the  structure  since  opening  day.  On  December  1, 
1951,  unusual  and  severe  winds  caused  the  bridge  to  be  closed  to  traffic.  Subsequent 
inspection  and  analysis  performed  under  the  direction  of  Clifford  E.  Paine,  Consulting 
Engineer,  resulted  in  the  major  structural  modifications  designated  as  the  Bottom 
Lateral  Bracing  System. 

Mr.  Paine  was  Principal  Engineer  with  Joseph  Strauss  during  the  bridge's  design 
and  construction,  and  has  been  closely  associated  with  the  Bridge  District  during  the 
intervening  years.  He  was  retained  by  the  District  to  document  these  changes  in  the 
Supplement  which  is  bound  within.  His  position  and  experience  make  him  pre- 
eminently qualified  to  do  so. 

For  the  Board  of  Directors, 

William  Moskovitz 
President 


December  1,  1970 


(S  (D    "5P  S  SS 


Page  No. 

Introduction 

9 

History 

ii 

Inspection  and  Damage 

18 

Recommendations 

23 

Character  of  Problem 

24 

Improvements  Considered 

26 

Section  Model  Tests 

3i 

Bottom  Lateral  System 

39 

Center  Stays 

44 

Traveling  Scaffolds 

46 

Plates 

SI  Bottom  Lateral  System  —  Plan 

SII  Bottom  Lateral  System  —  Sections 

SHI  Traveling  Scaffolds 


Since  the  Golden  Gate  Bridge  was  completed  and  opened  to  traffic  in  1937 
there  have  been  very  few  important  changes  in  or  additions  to  the  structure. 
It  is  the  purpose  of  this  supplement  to  point  out  and  discuss  these  changes 
and  additions. 

The  failure  of  the  Tacoma  Narrows  Bridge  in  1940  focused  attention  on  certain 
important  structural  requirements  of  a  cable  suspension  bridge  beyond  its  ability 
(1)  to  carry  live  load  on  its  roadway  and  (2)  to  withstand  static  wind  loads  impressed 
on  its  exposed  surfaces. 

Wind  storms  of  note  occurred  on  February  9,  1938;  on  February  11,  1941;  and  on 
December  1,  1951. 

A  Bottom  Lateral  System  was  added  in  1954  in  all  suspended  spans. 

Traveling  Scaffolds  were  added  in  1955.  One  set  of  scaffolds  was  placed  in  each 
side  span  and  two  in  the  main  span. 


GENERAL  HISTORY 


FAILURE  OF  THE  TACOMA  NARROWS  BRIDGE  IN  1940.  The  cable  suspension 
bridge  over  the  Tacoma  Narrows  which  was  opened  to  traffic  on  July  1,  1940  and 
failed  on  November  7,  1940,  comprised  a  central  span  of  2800  ft.  and  two  side  spans 
of  1100  ft.  each.  Its  two  cables,  each  about  17  inches  in  diameter  and  spaced  39  ft. 
center  to  center,  passed  over  tower  tops  450  ft.  above  low  water. 

The  suspended  structure  with  stiffening  girders  8  ft.  deep  carried  a  reinforced  con- 
crete roadway  26  ft.  wide  and  two  5  ft.  sidewalks  resting  directly  upon  five  lines  of 
steel  stringers  framed  into  transverse  floorbeams  which  were  spaced  25  ft.  center  to 
center.  The  floorbeams  were  framed  into  the  stiffening  girders  which  were  39  ft.  apart 
in  the  planes  of  the  two  main  cables  from  which  they  were  suspended. 

A  lateral  bracing  system  was  provided  in  a  plane  about  2  ft.  above  the  bottoms  of 
the  stiffening  girders. 

The  suspended  structure  described  above  may  be  classified  as  one  having  cross  - 
section  with  two  sides  and  bottom  closed  leaving  the  top  open.  The  construction 
could  not  have  accommodated  a  second  lateral  frame.  For  maximum  torsional  resistance 
the  cross-section  should  be  closed  on  all  four  sides  as  is  obtained  by  employing  two 
stiffening  trusses,  one  on  each  side,  and  two  lateral  systems,  one  in  the  plane  of  the 
top  chords  and  one  in  the  plane  of  the  bottom  chords. 

Immediately  after  being  put  into  service  the  Tacoma  Bridge  frequently  developed 
undulations  of  the  roadway  so  severe  as  to  cause  discomfort  to  the  users  of  the  bridge. 
Vertical  oscillations  having  waves  with  double  amplitudes  of  five  feet  were  not  un- 
common. Sometimes  wind  velocities  of  four  miles  per  hour  would  produce  pronounced 
waves  while  at  other  times  no  waves  were  produced  at  wind  velocities  of  thirty  miles 
per  hour. 

On  the  morning  of  November  7,  1940  a  southerly  wind  with  velocity  recorded  at 
forty-two  miles  per  hour  was  striking  the  bridge  at  a  quartering  angle.  The  wind  had 
continued  for  several  hours  prior  to  9:30  A.M.  at  which  time  the  main  span  was 
vibrating  with  a  frequency  of  36  cycles  per  minute  and  a  double  amplitude  of  about 
three  feet.  The  roadway  was  not  twisting  at  this  time.  The  cables  were  vibrating  in 
phase  with  one  another. 

Shortly  after  10:00  A.M.  there  was  a  change  in  the  mode  of  vibration  at  which  time 
the  main  span  vibrated  in  two  segments  with  a  node  at  mid-span  and  a  frequency  of 
14  cycles  per  minute.  Then  the  cables  began  vibrating  out  of  phase  with  one  another 
resulting  in  a  twisting  motion  of  the  roadway,  one  side  going  down  as  the  other  side 
came  up. 

A  little  later  the  frequency  changed  from  14  to  12  cycles  per  minute.  Motion  pic- 
tures show  a  tilting  of  the  bridge  deck  amounting  to  more  than  30  degrees  eac  h  way 


1 1 


THE     GOLDEN     GATE  BRIDGE 


from  the  horizontal.  The  double  amplitude  of  the  waves  probably  attained  a  maximum 
of  28  feet.  The  main  span  began  to  break  up  just  before  11:00  A.M. 

The  Tacoma  Narrows  Bridge,  built  at  a  cost  of  $6,469,770.00,  was  insured  for 
$5,200,000.00.  This  insurance  was  divided  among  twenty-two  insurance  companies. 

The  Narrows  Bridge  Loss  Committee  representing  the  twenty-two  original  insur- 
ers of  the  bridge,  on  November  9,  1940  engaged  Clifford  E.  Paine,  Consulting  Engi- 
neer, Chicago,  111.  to  investigate  and  report  on  the  cause  of  the  failure  and  the  extent 
of  the  loss. 

In  February,  1941,  at  Mr.  Paine's  suggestion,  four  other  engineers  were  named  to 
advise  and  collaborate  with  him  and  to  comprise  with  him  a  Board  of  Consulting 
Engineers.  The  Engineers  thus  named  were  as  follows: 

Hardy  Cross,  Professor  of  Civil  Engineering  at  Yale  University;  Shortridge  Har- 
desty,  Consulting  Engineer  of  New  York  City;  Holton  D.  Robinson,  Consulting 
Engineer  of  New  York  City;  Wilbur  M.  Wilson,  Research  Professor  of  Structural 
Engineering  at  the  University  of  Illinois. 

Mr.  John  M.  Carmody,  Administrator,  Federal  Works  Agency,  appointed  a  Board 
of  Engineers  to  investigate  and  report  on  the  failure.  This  Board  consisted  of  Othmar 
H.  Ammann,  Consulting  Engineer  of  New  York  City;  Theodore  von  Karman,  Director 
of  the  Daniel  Guggenheim  Aeronautical  Laboratory  at  the  California  Institute  of 
Technology,  Pasadena,  California;  and  Glenn  B.  Woodruff,  Consulting  Engineer  of 
San  Francisco,  California.  The  report  of  this  Board  entitled  "The  Failure  of  Tacoma 
Narrows  Bridge"  is  dated  March  28,  1941. 

A  few  days  after  his  engagement  by  the  Loss  Committee  the  writer  was  joined  in 
Seattle  by  his  assistant,  Mr.  Charles  H.  Clarahan,  Jr.  The  two  worked  together  making 
analytical  studies  of  the  ill-fated  span's  construction  and  its  behavior.  The  objective 
of  this  phase  of  the  study  being  (1)  to  find  its  weaknesses  and  (2)  to  find  how  the 
behavior  of  the  span  could  be  corrected  by  changing  its  design.  (The  scope  of  their 
investigation  was  much  broader  than  is  here  indicated  but  the  other  phases  of  the  study 
are  not  included  here  because  they  would  not  contribute  to  the  purpose  for  which 
this  discussion  is  included  in  the  Supplement.) 

One  did  not  have  to  look  far  to  find  several  examples  of  cable  suspension  bridges 
with  suspended  spans  similar  in  construction  to  the  Tacoma  Bridge  having  plate 
girder  stiffening  members  with  a  single  plane  of  lateral  bracing  and  having  a  history 
of  unsatisfactory  behavior.  Most  had  vertical  oscillations  of  such  magnitude  as  to 
require  corrective  treatment.  Some  had  torsional  oscillations  in  which  the  deck  tilted 
alarmingly.  The  analytical  studies  placed  the  Tacoma  Narrows  Bridge  in  the  lead  so 
far  as  this  misbehavior  was  concerned. 

It  was  concluded  that  the  suspended  structure  of  the  Tacoma  Bridge  could  have 
been  improved  in  design  by  modifying  it  as  follows: 

1.  Employ  trusses  instead  of  plate  girders  for  the  stiffening  members. 

2.  Put  a  top  lateral  system  in  the  plane  of  the  top  chords  and  a  bottom  lateral  system  in 


12 


GENERAL  HISTORY 


the  plane  of  the  bottom  chords. 
3.  In  conjunction  with  the  above 
have  cross-frames  at  intervals  to 
maintain  a  rectangular  cross- 
section. 

A  design  which  embodied  the  above 
changes  was  developed  and  for  con- 
venience in  reference  was  named  "The 
Tacoma  Fully  Braced  Design." 

The  report  to  the  Narrows  Bridge 
Loss  Committee  states  "The  compara- 
tive effectiveness  of  suspension  bridge 
designs  to  resist  irregular  and  turbu- 
lent wind  forces  is  reflected  by  their 
torsional  deformations  under  assumed 
asymmetric  loads  and  torsion.  The  de- 
sired behavior  is  attained  when  such 
loads  cause  comparatively  little  twist- 
ing of  the  suspended  structure. 

In  their  report  on  the  failure  of  the  Tacoma  Narrows  Bridge,  Messrs.  Ammann,  Joseph  B.  Strauss.  Chid 
von  Karman  and  Woodruff  made  comparison  of  the  twisting  or  tilting  of  the  bridge  cam" 'p']! ^ 
floors  of  several  designs  under  two  different  conditions  of  loading."  The  comparison  Principal  Engineer,  arc 
which  is  to  be  discussed  herein  is  based  on  one  of  these,  namely  on  the  tilting  of  the  inspection  of  the  bridge 
floor  resulting  from  an  asymmetric  load  of  100  lbs.  per  ft.  applied  on  the  near  cable  as  "  u  aeuini 

.  .  completion  in  this 

from  the  tower  to  mid-span  and  a  similar  load  applied  on  the  far  cable  from  mid-span  1937  photograph 
to  the  other  tower. 

They  made  several  modifications  of  design  of  the  Tacoma  Narrows  Bridge  to  com- 
pare how  the  various  changes  in  design  should  affect  their  behavior.  The  results  in 
terms  of  tilting  were  reported  as  follows: 

1.  Bridge  as  built  except  unstiffened.  Tilting  is  over  5%. 

2.  Bridge  as  built.  Tilting  is  a  little  over  5%. 

3.  With  weight  increased  10%.  Tilting  about  4.6%. 

4.  With  16  ft.  stiffening  trusses.  Tilting  about  4.2%. 

5.  With  24  ft.  stiffening  trusses.  Tilting  about  3.8%. 

6.  With  32  ft.  stiffening  trusses.  Tilting  about  3.3%. 

7.  With  100%  increase  in  weight  and  cables  spread  to  53  ft.  Tilting  about  2.()rr. 

8.  With  100%  increase  in  weight,  24  ft.  stiffening  trusses  and  cables  spread  to  53  ft. 
Tilting  about  1.8%. 

Looking  over  the  results  of  the  eight  modifications  of  the  Tacoma  design  as  reported 
by  Messrs.  Ammann,  von  Karman  and  Woodruff  it  is  seen  that  the  minimum  tilting 
they  attained  for  the  asymmetric  loading  assumed  was  in  design  modification  No.  8 


13 


THE     GOLDEN     GATE  BRIDGE 


in  which  the  weight  of  the  bridge  was  increased  100%,  stiffening  trusses  24  ft.  deep 
added  and  the  cables  were  spread  to  53  ft.  center  to  center.  This  yielded  a  tilting  of  1.8%. 

Studies  made  by  Mr.  Clarahan  and  the  writer  showed  that  the  most  effective  means 
of  obtaining  torsional  stiffness  in  the  suspended  structure  was  to  use  stiffening  trusses 
with  top  laterals  between  the  top  chords  and  bottom  laterals  between  the  bottom 
chords.  This  produces  a  "closed"  cross-section,  that  is  to  say  all  four  sides  of  the  cross- 
section  are  braced.  This  construction  was  previously  referred  to  as  the  "Tacoma  Fully 
Braced  Design."  The  tilt  of  this  design  with  stiffening  trusses  25  ft.  deep  and  with 
lateral  bracing  top  and  bottom,  with  no  change  in  weight  or  change  in  spacing  center 
to  center  of  cables,  was  about  0.4%.  This  is  less  than  one  quarter  of  the  tilt  obtained 
with  design  No.  8  described  above. 

It  follows  that  any  cable  suspension  bridge  having  a  suspended  structure  with 
cross-section  closed  on  two  sides  by  stiffening  trusses,  on  top  by  deck  and  top  lateral 
bracing  but  open  on  the  bottom  can  obtain  a  great  increase  in  torsional  stiffness  by 
the  addition  of  a  bottom  lateral  system  in  conjunction  with  effective  cross-frames  at 
intervals  sufficient  to  maintain  a  rectangular  cross-section. 

The  torsional  stiffness  of  the  suspended  structure  in  the  "Fully  Braced  Design"  was 
sufficient  to  force  the  cable  on  the  unloaded  side  to  deflect  downward  at  the  quarter 
point.  Hence  a  very  substantial  part  of  the  load  on  the  load  cable  was  transferred  to 
the  unloaded  cable. 

It  should  be  noted  that  when  a  cable  suspension  bridge  is  vibrating  all  parts  of  the 
structure  including  the  towers  participate  in  the  motion  to  some  degree.  During  part 
of  the  cycle  some  energy  of  motion  (kinetic  energy)  is  built  up  and  transformed  into 
energy  of  position  (potential  energy).  In  the  other  part  of  the  cycle  the  potential 
energy  is  converted  back  to  kinetic  energy.  Some  energy  is  lost  through  structural 
damping  and  windage  but  also  sometimes  the  wind  continues  to  feed  energy  into  the 
vibrating  structure.  As  the  amplitude  of  the  waves  increases  so  also  does  the  struc- 
tural damping  per  cycle.  Generally  structural  damping  in  trusses  exceeds  that  in  plate 
girders.  The  strain  in  steel  members  produces  heat  which  is  one  form  of  energy  lost 
in  every  cycle  of  vibration.  Slippage  at  joints  adds  further  to  the  loss  of  energy  and  so 
contributes  to  structural  damping. 

EARLY  STORMS.  The  first  severe  wind  at  the  Golden  Gate  Bridge  occurred  on 
February  9,  1938.  Westerly  winds  reached  velocities  which  made  it  impossible  for  a 
man  to  stand  erect  on  the  sidewalk.  No  instrumental  observations  were  made  of  the 
movements  of  the  bridge  during  the  storm,  but  witnesses  reported  undulations  of 
appreciable  amplitude. 

The  next  severe  storm  came  on  February  11,  1941  when  a  fairly  high  wind  from 
the  southwest  struck  at  an  angle  of  about  45  degrees  with  the  axis  of  the  bridge.  The 
longitudinal  axis  of  the  bridge  bears  S  5° -26'  E.  The  wind  continued  for  over  three 
hours  with  gusts  reaching  an  intensity  of  60  miles  per  hour.  It  is  reported  that  the  bridge 
deflected  laterally  4.9  feet  and  that  the  maximum  vertical  movement  at  the  quarter 


14 


GENERAL  HISTORY 


point  of  the  main  span  was  2  feet  and  the  frequency  lxk  cycles  per  minute.  The  report 
made  no  mention  of  torsional  movements. 

INSTRUMENTAL  INSTALLATIONS  AND  OBSERVATIONS.  In  1942  a  recording  an- 
emometer was  installed  at  the  center  of  the  main  span.  This  instrument  records  the 
velocity  and  horizontal  angle  of  the  wind. 

A  target  was  installed  at  mid-span  so  that  lateral  movement  of  the  roadway  could 
be  read  directly  with  the  aid  of  a  transit  set  up  at  the  San  Francisco  Tower.  At  this 
time  also  there  was  installed  on  the  sidewalk  at  the  center  of  the  main  span  an  acceler- 
ometer  to  measure  the  vertical  oscillations  at  that  point. 

Additional  accelerometers  were  installed  in  1945  and  1946,  so  that  from  that  time 
until  after  the  storm  of  December  1,  1951  there  is  a  continuous  record  of  wind  veloci- 
ties and  directions  at  the  center  of  the  main  span  and  of  vertical  movements  of  the 


bridge  floor  at  the  ten  stations  where  accelerometers  were  installed.  The  stations  are 
located  on  both  sides  of  the  roadway  at  the  centers  of  all  three  spans  and  at  the  south 
quarter  point  of  the  main  span.  Instruments  are  also  stationed  on  the  west  side  of  the 
roadway  only  at  the  three-eights  point  and  at  the  north  quarter  point  of  the  main  span. 

The  drum  speed  on  these  recording  accelerometers  has  proved  to  be  too  slow.  As 
a  result  the  graph  recording  the  vibrations  is  not  spread  out  sufficiently  to  show 
clearly  the  individual  waves  when  the  amplitudes  of  the  motion  are  large  and  over- 
lapping. 

A  study  of  the  vibration  charts  together  with  the  wind  charts  recorded  over  the 
six  years  following  the  installation  of  the  instruments  leads  to  some  general  conclu- 
sions as  follows: 


!5 


THE     GOLDEN     GATE  BRIDGE 


South  winds  as  high  as  30  to  50 
miles  per  hour  and  of  several  hours 
duration  are  not  uncommon.  These 
winds  cause  little,  if  any,  motion  to 
the  bridge.  For  example  on  February 
6,  1949  there  was  a  south  wind  aver- 
aging 30  to  40  miles  per  hour  for  a 
period  of  six  hours.  Vibrations  reached 
a  double  amplitude  of  only  11  inches. 
The  highest  double  amplitude  record- 
ed with  a  south  wind  was  14  inches 
on  January  16,  1950.  This  was  built 
up  during  a  period  of  eight  hours  with 
wind  velocities  averaging  30  to  40 
miles  per  hour  and  gusts  reaching  40 
to  50  miles  per  hour. 
No  considerable  motion  has  been  recorded  by  winds  making  an  angle  of  less  than 
45  degrees  with  the  longitudinal  axis  of  the  bridge. 

Winds  over  30  miles  per  hour  from  an  easterly  quarter  making  an  angle  of  more 
than  45  degrees  with  the  longitudinal  axis  of  the  bridge  are  rarely  recorded  and  none 
has  caused  any  noteworthy  motion. 

The  greatest  movement  recorded  prior  to  the  December  1,  1951,  storm  occured  on 
June  6,  1950  when  a  double  amplitude  of  45  inches  was  attained  at  the  middle  of  the 
main  span.  The  wind  was  from  the  west  with  a  peak  velocity  of  56  miles  per  hour.  The 
main  span  vibrated  as  a  single  segment  at  a  frequency  of  8  cycles  per  minute.  For  brief 
periods  this  motion  combined  with  torsional  vibrations  of  the  first  asymmetric  mode 
(double  segment). 


The  box-like  suspended  structure  comprises  a  top  provided  by  the  floor  deck,  two  vertical 
sides  provided  by  the  stiffening  trusses  and  a  bottom  provided  by  the  Bottom  Lateral  System. 
The  vertical  hangers  tying  the  transverse  struts  to  the  floor  beams  above,  combined  with  the 
kneebraces  of  the  original  construction,  all  lying  in  vertical  planes  comprise  an  effective  cross- 
frame  at  each  panel  point.  The  main  requisites  for  good  torsional  resistance  have  thus  been  met. 


THE  STORM  OF  DECEMBER  1.  1951.  On  December  1,  1951  a  strong  southwest  wind, 
which  had  persisted  through  the  early  part  of  the  day,  increased  in  intensity  until  at 
3:05  P.M.  it  reached  a  velocity  of  50  miles  per  hour  with  frequent  gusts  of  55  miles 
per  hour.  From  4:30  to  5:30  the  velocity  in  general  remained  at  about  50  miles  per  hour 
with  gusts  up  to  64  miles  per  hour.  For  a  period  of  twenty  minutes,  5:40  to  6:00,  the 
velocity  held  at  an  average  of  55  miles  per  hour  with  gusts  of  60  to  69  miles  per  hour. 
The  peak  of  69  miles  per  hour  came  at  5:55.  From  that  time  on  the  wind  velocity 
steadily  diminished  so  that  at  7:00  it  was  reduced  to  a  little  more  than  40  miles  per 
hour  with  gusts  of  50  miles  per  hour  or  less.  At  9:00  the  velocity  ranged  between  30 
and  45  miles  per  hour. 

The  wind  direction  at  3:00  was  southwest.  At  3:30  it  became  22V2  degrees  south  of 
west  and  held  that  direction  fairly  constantly  until  7:00  when  it  gradually  shifted 
westward.  From  8:00  to  9:00  it  was  west. 


16 


GENERAL  HISTORY 


Accelerometer  charts  show  the 
usual  pattern  of  vibrations  during  the 
early  period  of  the  storm.  Random 
vibrations  in  the  main  span  gradually 
built  up  into  a  well  defined  motion  at 
3:00,  at  which  time  the  main  span  was 
vibrating  in  the  first  symmetric  verti- 
cal mode  (single  segment)  with  a  fre- 
quency of  about  8  cycles  per  minute. 
At  5:30  the  frequency  at  mid-span  had 
increased  to  10  cycles  per  minute  and 
at  5:45  to  16.8  cycles.  Possibly  a  cou- 
pling of  the  first  asymmetric  torsional 
mode  with  the  first  symmetric  vertical 
mode  was  developing  during  this 
period.  These  mid-span  oscillations 
attained  a  double  amplitude  of  22 
inches. 

At  5:55,  at  the  peak  of  the  storm  a 
double  amplitude  of  about  130  inches 
is  indicated  at  the  southeast  quarter  point  of  the  main  span.  Due  to  mechanical  trouble 
the  chart  from  the  instrument  at  this  station  is  not  decisive  beyond  this  time.  The  instru- 
ment stationed  at  the  southwest  quarter  point  registered  a  double  amplitude  of  108 
inches. 

At  6:10  the  average  wind  velocity  had  dropped  to  50  miles  per  hour  with  occa- 
sional gusts  of  60  miles  per  hour.  At  that  velocity  the  amplitude  decayed  rapidly.  The 
marked  reduction  started  at  6:12  or  two  minutes  after  the  average  wind  velocity  had 
dropped  to  50  miles  per  hour.  By  6:30  the  amplitude  was  reduced  50%  and  by  7:00  it 
was  on  the  order  of  20  inches.  During  the  time  from  5:15  to  6:12  the  double  ampli- 
tude had  built  up  from  20  inches  to  the  maximum  of  about  130  inches.  Decay  started 
as  soon  as  the  average  wind  velocity  dropped  to  50  miles  per  hour. 

Because  of  the  slow  speed  of  the  chart  the  graph  is  too  compact.  This  fact,  coupled 
with  overlapping  of  graphs,  makes  it  impossible  to  determine  precisely  the  phase 
relationship  between  the  east  and  west  cables.  A  comparison  of  charts  from  the  south- 
east and  southwest  quarter  points  indicates  that  the  cables  were  not  always  moving  la 
phase  with  one  another  and  that  the  difference  varied  from  nothing  up  to  one  half 
cycle. 

The  floor  structure  of  the  main  span  is  freely  suspended  from  the  cables.  Its  ends 
are  held  against  lateral  movement  at  the  towers.  At  normal  temperature  tree  longi- 
tudinal motion  is  provided  to  the  extent  of  18  inches  in  either  direction.  During  tin- 
height  of  the  storm  the  suspended  structure  of  the  main  span  oscillated  Longitudinally 

17 


Public  safety  and  convenience  required  that  as  much  materials  handling  and  erection  as 
possible  be  done  out  of  traffic  and  out  of  sight  of  the  motorist.  The  Bottom  Lateral  Bracing 
System  contract  involved  approximately  $3,500,000,  almost  5,000  tons  of  structural  steel,  and 
a  year  and  a  half  of  time. 


THE     GOLDEN     GATE  BRIDGE 


through  the  full  length  of  travel  provided.  This  motion  possibly  had  something  to 
do  with  the  changing  phase  relationship  of  the  two  cables. 

On  the  day  of  the  storm  the  writer  was  at  his  home  in  Fennville,  Michigan.  He 
received  a  telephone  call  from  Mr.  James  E.  Rickets,  General  Manager  who  gave 
particulars  of  the  storm  which  he  said  was  then  abating.  He  had  stopped  traffic  over 
the  bridge  at  5:55  P.M.  By  the  time  of  the  telephone  call  the  wind  velocity  had 
dropped  to  50  miles  per  hour  and  the  amplitude  of  waves  was  much  reduced.  The 
District's  cars  had  traveled  over  the  roadway  and  found  no  trouble.  Mr.  Rickets 
asked  for  an  opinion  about  resumption  of  traffic.  The  reply  in  effect  was  that  traffic 
could  be  resumed  as  soon  as  drivers  would  have  no  difficulty  in  holding  their  cars  in 
the  traffic  lanes  they  chose  to  occupy. 

Upon  arrival  at  San  Francisco  on  the  following  day  as  requested  by  the  General 
Manager,  the  Board  of  Directors  of  the  District  directed  the  writer,  in  co-operation 
with  the  General  Manager,  to  supervise  the  repair  of  all  damage  caused  by  the  storm. 

INSPECTION  AND  DAMAGE 

GENERAL.  Inspection  of  the  suspension  structure  from  anchorage  to  anchorage 
made  by  the  writer  with  the  aid  of  District  employees  disclosed  only  superficial  injury 
except  at  expansion  joints  where  the  lateral  system  of  the  center  span  connects  with 
the  towers. 

At  the  latter  points  the  sliding  block  joints  were  damaged  so  that  replacement  of 
one  bearing  plate  and  the  block  was  necessary  at  the  San  Francisco  Tower  while  at 
the  Marin  Tower  replacement  of  both  bearing  plates  and  the  block  was  necessary. 
These  various  items  will  be  discussed  in  detail  hereinafter. 

MARIN  PIER.  A  visual  inspection  of  the  Marin  or  North  Pier  shows  no  deteriora- 
tion. This  pier  was  built  on  a  small  island  of  rock.  Excavation  for  the  pier  left  a  rim 
of  this  rock  of  varying  height  around  the  pier  except  at  the  southwest  corner  where 
the  excavation  was  deepened  thirteen  and  one-half  (13V2)  feet  in  order  to  reach  a  solid 
bed.  Small  portions  of  this  rim  project  above  the  water.  Tide  was  out  at  the  time  of 
the  writer's  inspection  and  there  was  no  apparent  change  in  the  visible  part  of  the 
rock.  Unquestionably  the  foundation  is  sound. 

SAN  FRANCISCO  PIER.  The  San  Francisco  or  South  Pier  and  Fender  is  unaffected 
by  the  storm.  There  has  been  no  appreciable  deterioration  here  since  construction. 

ANCHORAGES.  The  Marin  cable  anchorage  was  in  no  way  affected.  It  is  in  perfect 
condition.  An  excellent  job  of  maintenance  has  been  carried  out  on  this  vital  part  of 
the  structure.  Here  there  has  been  no  deterioration  since  the  date  of  its  construction. 

The  Marin  Anchorage  Housing  was  in  no  way  affected  by  the  storm.  However, 
as  has  been  previously  reported  repairs  were  needed  at  floor  stringer  seats  on  the  back 
wall  of  Pylon  Nl  and  on  the  expansion  sides  of  Bents  designated  as  Nos.  3,  6  and  9- 
The  need  for  these  repairs  was  not  related  to  the  storm. 

18 


INSPECTION     AND  DAMAGE 


The  San  Francisco  cable  anchorage  was  in  no  way  affected  by  the  storm  and  is 
in  perfect  condition.  Maintenance  has  been  of  the  same  high  order  as  that  at  the 
Marin  Anchorage. 

PYLONS  Nl  AND  SI.  Pylon  Nl  located  at  the  shore  end  of  the  Marin  side  span 
houses  two  vital  elements  of  the  structure  —  the  cable  tiedowns  and  the  lateral  con- 
nections for  the  side  span.  Also  located  here  are  the  rocker  links  which  maintain  the 
end  of  the  span  at  the  required  elevation.  These  are  all  in  perfect  condition  and  have 
not  been  affected  by  the  storm. 

Dirt  from  the  roadway  accumulates  rapidly  here  and  requires  more  frequent  clean- 
ing and  painting.  No  deterioration  is  evident. 

Sheet  metal  housings  around  the  cables  where  they  enter  the  Pylon  show  result  of 
corrosion  from  the  inside  which  surfaces  are  inaccessible  for  painting.  These  housings 
are  purely  superficial  and  at  the  time  of  this  inspection  nothing  needs  to  be  done. 
They  are  intended  to  be  replaced  when  necessary. 

Pylon  Si,  located  at  the  shore  end  of  the  San  Francisco  side  span  serves  the  same 
purpose  at  the  south  end  of  the  bridge  as  does  Pylon  Nl  at  the  north  end.  The  com- 
ments made  above  for  Pylon  Nl  apply  here  also  except  that  a  very  small  chip 
of  bronze  has  been  broken  off  from  a  rubbing  block  which  is  in  sliding  contact  with 
the  tiedown  cable  band  on  the  east  cable.  This  injury  was  probably  done  during  the 
storm.  It  is  of  no  consequence  and  needs  no  repair. 

CABLES.  Aside  from  a  few  spots  where  paint  was  loosened  or  removed,  the 
cables  were  not  injured  by  the  storm. 

CABLE  BANDS.  Cable  bands  were  not  damaged.  Chafing  of  suspender  ropes  in  the 
grooves  at  a  few  points  near  mid-span,  where  suspenders  are  short,  rubbed  off  some 
paint.  The  restoration  of  paint  is  a  task  of  the  regular  maintenance  force. 

On  the  east  cable  of  the  center  span  the  first  regular  band  south  of  the  Marin  Tower 
showed  evidence  of  a  movement  of  about  one-sixteenth  (1/16)  inch  along  the  cable. 
This  is  unimportant.  There  was  no  movement  of  other  bands  with  respect  to  the  cables. 

SUSPENDERS.  Suspender  ropes  were  not  damaged.  At  a  few  points  the  suspender 
spacing  clamps  just  below  the  cables  were  displaced  upward.  These  have  all  been 
returned  to  their  normal  position. 

At  numerous  points  where  the  suspender  ropes  pass  through  the  top  chord  cover 
plates  the  wire  wrapping  used  to  protect  the  ropes  against  chafing  (or  in  some  cases 
the  steel  shields  added  since  construction  for  this  same  purpose)  were  disturbed  and 
many  new  shields  have  been  added  by  the  District's  maintenance  crew,  or  old  shields 
have  been  adjusted  in  position  so  that  all  points  are  protected.  Much  of  this  has  been 
done  in  the  past  as  a  regular  maintenance  matter. 

SUSPENDED  STRUCTURES.  The  stiffening  trusses,  floorbeams,  stringers,  laterals 
and  handrailing  were  undamaged. 

Sidewalk  concrete  in  a  few  places  along  the  outer  edges  where  railing  posts  p  iss 
through  it  show  bits  of  concrete  cracked  off.  This  in  no  way  affects  the  serviceability 


19 


THE     GOLDEN     GATE  BRIDGE 


of  fhe  sidewalks  and  repairs  of  the  same  are  not  necessary.  Roadway  concrete  was  not 
damaged. 

Concrete  bases  under  lamp  posts  located  350  feet  each  side  of  mid-span  on  the  east 
side,  of  the  roadway  were  broken  when  the  cable  rubbed  against  these  posts.  These 
bases  were  rebuilt  by  the  District's  maintenance  crew. 

TOWERS.  A  thorough  inspection  of  the  towers  with  particular  attention  to  the  tops 
showed  no  damage.  Saddle  castings  and  connections  for  same  to  the  tower  tops  were 
in  perfect  condition.  Connections  of  transverse  top  struts  between  tower  legs  showed 
no  strain  whatever.  Bracing  between  tower  legs  immediately  below  the  roadway 
where  lateral  forces  from  the  suspended  spans  are  unloaded  was  in  perfect  condition. 

Rocker  links  and  bearings  for  the  same  at  both  towers  were  undamaged. 

LATERAL  CONNECTIONS  OF  SUSPENDED  SPANS  TO  TOWERS.  The  lateral  con- 
nections of  side-spans  to  the  towers  in  both  instances  were  undamaged. 

The  lateral  connections  of  center  span  to  the  towers,  however,  suffered  consider- 
able damage.  The  construction  of  this  connection  located  just  beneath  the  bridge  floor 
on  the  longitudinal  center  line  of  the  bridge  is  arranged  so  that  the  lateral  system 
transfers  its  load  through  a  sliding  block  to  a  large  slotted  casting  which  is  fixed  to 
the  tower. 

The  ends  of  the  sliding  block  are  turned  down  to  a  twelve  (12)  inch  diameter  to 
fit  into  bronze  bushings  carried  by  the  lateral  plates.  The  latter  lie  in  horizontal  planes. 
This  permits  angular  motion  of  the  lateral  plates  about  the  vertical  axis  of  the  block 
and  thus  accommodates  the  angular  movements  of  the  end  of  the  span  as  it  deflects 
horizontally. 

The  block  is  in  sliding  contact  with  the  vertical  faces  of  the  bearing  plates  which 
line  the  casting  on  each  side  of  the  slot.  This  gives  freedom  for  longitudinal  move- 
ment of  the  center  span  within  the  limits  of  the  slot  and  also  accommodates  angular 
motion  in  a  vertical  plane.  The  bearing  plates  were  of  bronze  and  the  sliding  block 
of  Allegheny  Metal  33. 

During  the  storm,  the  rapid  movement  of  the  block  along  the  unlubricated  bear- 
ing plates  (pressure  was  against  the  plates  on  the  east  side  of  the  slot)  generated  con- 
siderable heat.  The  edges  of  the  block  cut  into  the  east  bearing  plate  and  actually  shaved 
off  strips  of  the  bronze.  Eventually  portions  of  the  bearing  plate  tore  loose  from  the 
casting.  The  face  of  the  casting  itself  along  the  east  side  of  the  slot  was  worn  away  in 
places  as  was  also  the  block. 

In  general  the  repair  job  at  each  end  of  the  center  span  was  to  remove  the  dam- 
aged bearing  plates;  restore  the  worn  places  on  the  casting;  install  new  bearing  plates 
and  new  blocks. 

To  give  access  to  the  work  the  upper  lateral  plate  was  removed.  The  block  was 
then  lifted  out;  the  damaged  bearing  plate  removed;  the  casting  built  up  by  arc  weld- 
ing; finished  down  to  required  plane;  new  bearing  plate  installed  and  matching  holes 
for  through  bolts  drilled  through  the  casting  to  hold  the  bearing  plates  in  position. 


20 


INSPECTION     AND  DAMAGE 


(The  original  bearing  plates  were  held  in  place  by  tap  screws.)  The  new  block  was 
then  installed  and  the  upper  lateral  plate  was  put  back  in  place.  (At  the  Marin  Tower 
both  bearing  plates  were  replaced.) 

The  above  operations  started  on  December  9,  1951  and  were  completed  at  the  San 
Francisco  Tower  on  January  4,  1952.  Work  at  the  Marin  Tower  was  completed  about 
January  22,  1952.  Much  of  the  work  was  performed  during  a  period  when  high 
winds  and  rainfall  were  far  in  excess  of  normal.  On  many  days  no  work  could  be  done. 

At  the  beginning  of  work  each  day  it  was  necessary  to  remove  the  upper  lateral 
plate  and  the  block.  Each  night  these  parts  were  reassembled.  The  two  center  lanes 
were  blocked  to  traffic  during  working  hours  but  each  evening  the  barricades  were 
removed  so  that  at  night  all  lanes  were  opened  for  traffic. 

In  order  to  effect  repairs  and  restore  normal  functioning  as  early  as  possible,  steel 
bearing  plates  were  installed  and  blocks  of  Forged  Steel  SAE  1040  annealed  were 
used.  In  the  new  detail  provision  has  been  made  for  lubrication  of  the  sliding  surfaces 
and  rounding  off  th*e  edges.  The  materials  used  are  not  so  resistant  to  corrosion  and 
wear  as  the  materials  formerly  employed,  but  they  will  serve  properly  for  a  long  time 
and  until  parts  manufactured  of  the  preferred  materials  can  become  available,  at 
which  time  the  change  over  can  be  made  quickly,  since  the  details  employed  have 
been  designed  with  that  in  mind. 

The  original  sliding  blocks  have  been  carefully  crated  and  marked  for  future 
utilization. 

The  work  was  done  by  the  Judson  Pacific-Murphy  Corporation,  Emeryville,  Cali- 
fornia, under  the  direction  of  the  general  manager  and  the  writer.  Whereas  the  pur- 
pose of  this  report  is  to  cover  the  storm  damage  to  the  Bridge  and  its  repair,  it 
seemed  desirable  to  include  for  the  record  factual  information  regarding  the  storm 
and  the  movements  of  the  Bridge. 


Steel  for  half  of  project 
—  2,500  tons  —  was 
trucked  to  base  of 
Marin  Tower  where 
contractor  maintained 
a  five-day  stockpile. 


RECOMMENDATIONS 


RECOMMENDATIONS 

(From  the  report  of  Clifford  E.  Paine,  January  18,  1952) 
"Repair  of  storm  damage  to  the  Bridge  has  been  practically  completed. 
"For  the  first  time  in  its  fourteen  years  of  service,  the  character,  intensity,  and 
direction  of  the  wind  resulted  in  movements  of  the  bridge  floor  of  important  magni- 
tude. It  is  believed  that  much  can  be  done  to  improve  this  behavior. 

"The  addition  of  a  system  of  lateral  bracing  in  the  plane  of  the  bottom  chords  in 
conjunction  with  cross  bracing  in  vertical  planes  at  regular  intervals  would  be  highly 
beneficial. 

"Other  possibilities  include  the  employment  of  open  grating  floor  in  some  side- 
walk areas  and  the  use  of  damping  devices.  The  field  of  possibilities  is  large  and  should 
be  thoroughly  explored. 

"The  writer  would  participate  in  the  investigation  if  the  Board  so  desires,  on  con- 
dition that  he  be  authorized  to  consult  and  collaborate  with  two  or  more  consulting 
engineers  experienced  in  this  field." 

It  is  therefore  recommended  that: 

1.  The  writer  be  authorized: 

(a)  To  study  the  feasibility  of  adding  a  lateral  bracing  system  in  the  plane  of  the 
bottom  chords  of  the  stiffening  trusses. 

(b)  To  study  the  effects  of  such  a  bracing  system  on  the  behavior  of  the  Bridge  — 
taking  into  consideration  any  net  change  in  weight  of  the  suspended  structure 
and  any  resulting  change  in  the  magnitude  and  distribution  of  impressed 
wind  forces  to  all  parts  affected. 

(c)  To  study  the  feasibility  and  desirability  of  employing  an  open  grating  type  of 
floor  on  some  sidewalk  areas. 

(d)  To  study  the  feasibility  and  desirability  of  adding  damping  devices  to  restrain 
and  cushion  longitudinal  movements  of  the  center  span. 

(e)  To  study  the  feasibility  and  desirability  of  making  any  modifications  of,  or 
addition  to  the  structure  which,  as  the  study  develops,  might  appear  to  be 
necessary  or  advisable. 

(f)  To  engage  (on  behalf  of  the  Golden  Gate  Bridge  and  Highway  District)  two 
or  more  consulting  engineers  of  recognized  standing  and  having  direct  exper- 
ience in  the  problems  involved  to  collaborate  with  the  writer  in  a  review  of 
these  studies  and  the  preparation  of  a  report  setting  forth  the  conclusions  and 
recommendations  jointly  agreed  upon. 

2.  The  District  arrange  with  the  manufacturers  of  vibration  recording  instruments  to 
have  those  on  the  center  span  modified  so  that  the  driving  mechanism  of  the  record- 
ing drum  can  be  instantly  changed  to  increase  the  speed  of  the  chart  to  about  three 
times  the  normal  speed.  This  will  give  graphs  which  can  be  interpreted  with  greater 
certainty. 

iew  taken  Opening  Day  1937,  shows  23 
pearance  of  deck  structure  as  originally 
lilt.  Esthetic  quality  of  structure  remains 
ichanged  by  addition  of  Bottom  Lateral 
acing  System. 


THE     GOLDEN     GATE  BRIDGE 


In  use,  the  instruments  would  operate  normally  as  at  present  but  whenever  the 
vibrations  became  of  important  magnitude  the  shift  would  be  made  (either  automat- 
ically or  semi-automatically).  In  this  way,  the  charts  would  cover  the  same  period  of 
time  as  at  present  except  when  it  becomes  advantageous  to  increase  the  speed  of  the 
drum. 

3.  One  of  the  vibration  recording  instruments  be  moved  from  the  North  side-span 
to  the  North  quarter  point  of  the  center  span  —  east  side. 

ENGINEERING  STUDY  INITIATED.  In  his  report  quoted  above,  the  writer  advised 
that  the  addition  of  a  system  of  bottom  lateral  bracing,  in  conjunction  with  cross 
bracing  in  vertical  planes  at  regular  intervals,  would  be  highly  beneficial.  He  was  au- 
thorized by  the  Board  of  Directors  of  the  Golden  Gate  Bridge  and  Highway  District 
to  proceed  with  the  studies  recommended  in  his  report.  He  developed  the  plans 
therefor  in  preparation  for  their  review  by  two  consulting  engineers  he  had  been 
authorized  to  name  for  the  purpose  of  collaborating  with  him.  On  April  25,  1952,  as 
recommended  by  the  writer,  the  Board  of  Directors  confirmed  the  appointment  of 
Mr.  Othmar  H.  Ammann  and  Charles  E.  Andrew,  Consulting  Engineers,  to  form  with 
the  writer  a  Board  of  Engineers.  The  Board  of  Engineers  thus  constituted  held  its  first 
meeting  in  Seattle,  Washington,  on  May  15,  1952. 


CHARACTER  OF  PROBLEM 

In  considering  ways  and  means  to  improve  the  existing  structure  so  as  to  eliminate 
all  objectionable  motion  under  severest  wind  action,  the  Board  of  Engineers  realized 
that  they  were  confronted  by  a  problem  which  could  not  be  solved  with  mathematical 
certainty. 

The  problem  is  an  extremely  complex  one.  Its  solution  is  dependent  upon  many 
varied  factors,  some  of  which,  such  as  the  nature  of  wind  action  on  the  actual  struc- 
ture and  damping  resistance  of  the  structure,  are  uncertain  and  have  not  as  yet  been 
adequately  explored. 

It  is  largely  due  to  these  uncertain  and  unexplored  factors  that,  despite  volumes 
of  theories  developed  since  the  failure  of  the  Tacoma  Narrows  Bridge  and  of  extensive 
research  work  and  laboratory  experiments  carried  out  in  this  country  and  elsewhere, 
we  are  still  dependent  to  a  large  extent  upon  judgment  based  on  the  comparative  be- 
havior of  existing  similar  structures,  supplemented  by  trends  indicated  by  model 
experiments. 

Moreover,  while  in  the  case  of  a  new  suspension  bridge  various  means  can  be  ap- 
plied so  as  to  give  practical  assurance  of  ample  resistance  against  dynamic  wind  action, 
there  are  limitations  to  the  use  of  similarly  effective  means  in  an  existing  large  struc- 
ture, such  as  the  Golden  Gate  Bridge,  without  involving  changes  of  major  extent  and 
at  exorbitant  cost. 

24  Critical  storage  area  at  the  San  Franciso 

Tower  was  created  by  timber  plarfora 
between  fender  and  pier  to  handle  half  o 
tonnage  of  project.  Steel  via  barge,  15' 
tons  per  load  representing  six  25-fbo 
panels  of  structure,  was  handled  by  true! 
crane  and  stockpiled  on  protective  plank 
ing. 


THE     GOLDEN     GATE  BRIDGE 


It  was  considered  desirable  to  carry  out  a  program  of  so-called  section  model  tests, 
that  is  tests  made  on  a  scale  model  of  a  short  section  of  the  suspended  floor  structure, 
to  supplement  knowledge  which  had  been  derived  from  similar  tests  made  previously. 
Only  limited  information  can  be  obtained  from  such  section  model  tests.  Doubtless 
a  scale  model  of  the  entire  bridge  would  have  permitted  a  somewhat  closer  approach 
to  a  solution.  Even  a  full  model,  however,  has  its  limitations.  It  would  involve  a  rela- 
tively large  expenditure  and  its  construction,  together  with  an  adequate  program  of 
tests  on  the  same,  would  consume  more  than  a  year's  time. 

Despite  the  complexity  of  the  problem  and  the  limited  time  and  means  available 
it  is  the  judgment  of  the  Engineering  Board  that  their  studies,  supplemented  by 
present  knowledge  of  behavior  of  existing  bridges  as  well  as  from  extensive  research 
work  carried  out  here  and  elsewhere,  make  an  adequate  solution  of  the  problem 
possible. 


IMPROVEMENTS  CONSIDERED 

The  following  means  to  improve  the  present  (1953)  condition  of  the  Golden  Gate 
Bridge  have  been  given  consideration  in  this  study.  All  have  been  applied  in  the  con- 
struction of  new  large  bridges  or  in  the  improvement  of  existing  ones  and  certain 
data  are  available  relative  to  their  effect. 

ADDITION  OF  BOTTOM  LATERAL  SYSTEM.  In  his  study  of  the  Failure  of  the  Ta- 
coma  Narrows  Bridge  the  writer  discovered  that  in  any  suspended  structure  having 
trusses  on  two  sides,  lateral  bracing  on  either  top  or  bottom  side  and  with  fourth  side 
open  the  closing  of  the  fourth  side  by  installation  of  a  lateral  bracing  system  was  by 
far  the  most  effective  measure  that  could  be  taken  to  increase  torsional  resistance.  In 
his  report  to  the  Board  of  Directors  of  the  Golden  Gate  Bridge  and  Highway  District 
dated  January  18,  1952  he  therefore  stated  that  "The  addition  of  a  system  of  lateral 
bracing  in  the  plane  of  the  bottom  chords  in  conjunction  with  cross  bracing  in  verti- 
cal planes  at  regular  intervals  would  be  highly  beneficial." 

The  Golden  Gate  Bridge,  like  many  other  suspension  bridges,  was  designed  and 
built  with  a  single  system  of  lateral  bracing  immediately  below  the  roadway  in  the 
plane  of  the  top  chords  of  the  stiffening  trusses.  Use  of  a  single  lateral  system  left  the 
bottom  side  of  the  suspended  structure  open  and  hence  its  torsional  resistance  was  low. 

It  is  evident  from  observations  on  the  Golden  Gate  Bridge,  in  particular  those 
taken  from  the  instruments  on  the  bridge  during  the  storm  of  December  1,  1951,  that 
the  severest  motions  were  distinctly  of  a  torsional  character  combined  with  vertical 
motions. 

This  tendency  towards  torsional  oscillations  is  also  evidenced  by  tests  which  had 
been  made  on  models  of  the  Golden  Gate  Bridge  and  several  other  truss-stiffened 
suspension  bridges,  in  particular  models  of  the  rebuilt  Tacoma  Narrows  Bridge  and 


26 


Exterior  side  scaffold  number  3  appears 
in  this  view  of  the  Marin  Tower  with  San 
Francisco  in  background. 


THE     GOLDEN     GATE  BRIDGE 


of  the  proposed  bridge  across  the  Severn  in  England.  Both  the  latter  bridges  have 
been  designed  with  a  double  system  of  lateral  bracing  to  resist  this  tendency. 

Double  lateral  systems  have  also  been  applied  in  the  design  of  the  Delaware 
Memorial  Bridge  at  Wilmington. 

Neither  the  new  Tacoma  Narrows  Bridge,  completed  in  1950,  nor  the  Delaware 
Memorial  Bridge,  completed  in  1951,  have  so  far  experienced  noticeable  motions 
under  severe  wind  action. 

Tests  made  at  Princeton  University  in  connection  with  the  construction  of  the 
Delaware  Memorial  Bridge  closely  checked  theoretical  calculations  to  the  effect  that 
the  addition  of  a  lower  lateral  system  increased  the  torsional  rigidity  of  the  suspended 
floor  structure  of  that  bridge  about  20  times. 

Similar  calculations  made  for  the  Golden  Gate  Bridge,  as  reported  hereinafter, 
show  that  the  torsional  rigidity  of  the  floor  structure  by  the  addition  of  the  proposed 
lower  lateral  system  increased  about  35  times,  and  that  the  torsional  resistance  of  the 
entire  suspended  structure,  cables  and  floor  structure,  is  2.75  times  the  corresponding 
resistance  without  lower  laterals. 

As  verified  by  the  section  model  tests  hereinafter  reported,  this  stiffening  effects  a 
substantial  increase  of  the  critical  wind  velocity  at  which  torsional  motions  of  the  struc- 
ture will  be  initiated.  This  increased  resistance  to  torsional  motions  is  accompanied 
by  increased  structural  damping  produced  by  the  addition  of  the  lower  lateral  system. 

These  considerations  lead  to  the  reasonable  conclusion  that  the  addition  of  the  bot- 
tom lateral  system  will  so  materially  improve  the  resistance  of  the  Golden  Gate  Bridge 
to  wind  action  that  no  other  improvements  may  become  necessary. 

CENTER  STAYS.  Effective  center  stays  have  the  purpose  of  preventing  the  racking, 
opposite  longitudinal  motions  of  cables  and  floor  structure  which  result  from  asym- 
metric distortions  of  the  oscillating  structure  under  dynamic  wind  action. 

Such  devices  were  introduced  in  the  original  Tacoma  Narrows  Bridge  after  its 
completion  in  an  attempt  to  steady  the  structure.  There  can  be  little  doubt  that  as 
long  as  the  center  stays  remained  intact  they  prevented  the  development  of  the  severe 
torsional  motions  which  led  to  the  ultimate  destruction  of  the  suspended  structure. 
Those  center  stays  and  in  particular  their  connections  to  the  cables  were,  however, 
inadequate  to  resist  the  forces  which  developed.  Moreover  their  influence  in  reducing 
vertical  asymmetric  motions  proved  to  be  limited. 

More  effective  center  stays  were  introduced  in  the  Bronx- Whitestone  Bridge 
which  experienced  oscillations  of  moderate  amplitudes  after  its  completion  in  1939. 
While  they  are  unquestionably  effective  in  preventing  the  development  of  torsional 
motions,  and  have  had  a  noticeably  favorable  influence  on  vertical  oscillations,  the 
latter  influence  alone  did  not  prove  adequate  to  steady  the  structure  satisfactorily 
against  vertical  motions. 

A  very  substantial  system  of  center  stays  has  also  been  made  part  of  the  design  of 
the  new  Tacoma  Bridge.  Their  favorable  influence  was  indicated  by  tests  made  on  the 


28 


Construction  photograph  of  original  deck 
structure  in  1936  shows  floor  beams,  knee 
braces  and  stiffening  trusses. 


THE     GOLDEN     GATE  BRIDGE 


full  model  of  that  bridge,  but  it  would  be  impossible  to  assign  a  quantitative  value 
to  their  effect  in  comparison  to  the  effect  of  other  means  employed  in  that  design  to 
secure  steadiness,  vertically  and  torsionally.  It  is  believed  that,  while  the  influence  of 
center  stays  in  preventing  asymmetric  torsional  motions  is  unquestionably  very  appre- 
ciable, in  fact  positive  so  long  as  they  remain  intact,  they  are  an  additional,  but  not 
necessarily  essential  safeguard. 

The  practicability  of  introducing  center  stays  in  the  Golden  Gate  Bridge  was 
studied  and  it  was  concluded  that  they  should  be  installed  only  as  a  further  step  in 
case  the  addition  of  a  bottom  lateral  system  should  prove  not  entirely  adequate  to 
prevent  objectionable  motions. 

On  the  Bronx- Whitestone  Bridge  and  the  new  Tacoma  Narrows  Bridge,  center 
stays  were  used  in  combination  with  damping  devices  at  each  end  of  the  main  span. 
No  practical  way  was  found  of  applying  such  end  damping  devices  to  the  Golden 
Gate  Bridge  and  it  is  not  now  considered  an  essential  improvement. 

ALTERATIONS  OF  FLOOR  STRUCTURE.  Extensive  experiments  made  with  models 
in  wind  tunnels,  notably  those  made  in  connection  with  the  redesign  of  the  Tacoma 
Narrows  Bridge  have  revealed  beyond  doubt  that  the  form  of  the  suspended  struc- 
ture may  have  a  marked  effect  on  its  behavior  in  wind  and  may  contribute  towards 
its  steadiness. 

The  Tacoma  Narrows  Bridge  tests  revealed  in  particular  that  certain  openings  in 
the  deck  structure  can  be  very  effective  in  this  respect  and  as  a  result  such  openings 
were  provided  in  the  design  of  that  bridge  in  the  form  of  strips  of  open  grating 
flooring  between  solid  concrete  slabs.  These  and  other  model  tests  indicated  that  in 
general  openings  in  the  deck  structure  tend  to  be  beneficial. 

Based  on  these  findings  it  was  believed  that  in  the  case  of  the  Golden  Gate  Bridge 
beneficial  effects  would  be  produced  by  replacing  the  1 1  ft.  wide  solid  deck  footwalks 
partially  or  entirely  by  open  steel  gratings.  The  exploration  of  these  effects  was  the 
principal  reason  for  carrying  out  a  program  of  section  model  tests  by  which  a  measure 
of  influence  of  such  openings  and  other  structural  changes  in  the  floor  structure 
could  be  obtained. 

The  results  of  these  tests  described  hereinafter,  while  indicating  the  possibility  of 
improvement,  were  disappointing  in  that  they  did  not  reveal  under  all  reasonably 
possible  wind  conditions  a  favorable  effect  of  sufficient  magnitude  to  justify  the  ex- 
tensive and  costly  structural  alterations  of  the  deck  structure  before  ascertaining 
whether  other  improvements  such  as  the  addition  of  a  bottom  lateral  system  and 
possibly  center  stays  will  be  adequate. 

Judging  from  the  results  of  the  Tacoma  Narrows  Bridge  tests  it  is  reasonable  to 
assume  that  more  extensive  openings,  including  parts  of  the  roadway  deck,  would  be 
more  effective,  but  such  changes  would  be  difficult  to  accomplish  and  very  costly. 
For  these  reasons  the  program  of  section  model  tests  did  not  include  such  changes. 

If  the  addition  of  bottom  laterals  and  possibly  the  introduction  of  center  stays 


30 


SECTION     MODEL  TESTS 


should  be  inadequate  to  prevent  objectionable  motions,  then  the  expedient  of  opening 
the  sidewalks  and  possibly  other  changes  in  form  should  be  given  further  study. 

OTHER  STAY  SYSTEMS.  In  several  suspension  bridges  which  experienced  excessive 
motions  in  wind,  various  systems  of  diagonal  wire-rope  stays  were  introduced,  con- 
necting the  tower  tops  or  points  along  the  cables  with  points  along  the  floor  struc- 
ture. A  sufficient  number  of  such  diagonal  stays  properly  placed  may  be  effective  in 
steadying  the  structure. 

Such  stay  systems,  however  render  the  entire  suspension  system  very  complex  and 
highly  indeterminate  in  stress  action.  The  design  of  a  long-span  suspension  bridge, 
which  for  economic  reasons  has  to  be  relatively  flexible,  anticipates  complete  freedom 
of  action  for  the  cables  except  for  intended  stiffening  that  results  from  its  connection 
to  the  stiffening  trusses  by  vertical  suspender  ropes. 

It  is  desirable  to  attain  this  freedom  of  action  as  far  as  possible.  The  provision  of 
diagonal  stays  tying  the  cables  to  the  stiffening  trusses  restrains  the  cables  so  that  they 
no  longer  function  in  the  free  and  simple  manner  anticipated  in  the  design.  For  this 
reason  the  need  for  such  stays  must  be  predominating  to  justify  their  use. 

The  degree  of  restraint  exercised  by  such  stays  in  resisting  dynamic  wind  action 
can  only  be  reliably  determined  either  by  trial  on  the  actual  structure  or  by  elaborate 
tests  on  a  full  model  of  the  bridge. 

To  be  effective  in  the  Golden  Gate  Bridge  such  a  system  might  be  very  expensive 
to  install  and  would  adversely  affect  its  good  appearance. 

SECTION  MODEL  TESTS 

As  previously  stated  herein  the  problems  of  determining  what  motions  will  occur 
in  any  suspension  bridge  due  to  dynamic  wind  action  is  a  complex  one.  For  any 
given  structure  certain  influencing  factors,  such  as  period  of  vibration,  characteristics 
of  wave  forms,  etc.,  are  subject  to  mathematical  solution  because  they  depend  only  on 
the  known  elastic  properties  of  the  structure.  Other  factors,  such  as  the  efficiency  of 
the  wind  action  on  the  actual  bridge  and  the  ability  of  the  structure  to  dissipate  ener- 
gy, can  be  evaluated  only  on  assumptions  which  must  be  derived  from  field  observa- 
tions on  and  experience  with  existing  structures  supplemented  by  judgment. 

Fortunately  the  recorded  observations  on  the  Golden  Gate  Bridge  furnish  much 
dependable  information  in  this  regard.  This  knowledge  derived  from  actual  structures 
must  be  supplemented  by  judicious  interpretation  of  experiments  with  models  in 
wind  tunnels. 

TYPES  OF  MODELS.  Two  types  of  models  are  available,  viz;  full  models  and  sec- 
tion models. 

A  full  model  is  one  which  represents  the  full  structure  to  some  scale  and  simu- 
lates it  elastically.  Such  a  model  is  costly,  must  be  tested  in  a  specially  adapted  wind 
tunnel,  and  its  construction  consumes  much  time.  It  has  an  advantage  over  the  section 


3i 


THE     GOLDEN     GATE  BRIDGE 


model  in  that  wind  can  be  applied  over  any  portion  or  all  of  its  length.  Its  periods 
of  vibration  and  all  other  characteristics  of  the  motions  produced  by  wind  can  be 
visually  observed  and  measured.  Parallel  tests  made  on  full  models  and  corresponding 
section  models  have  demonstrated,  however,  that  certain  useful  conclusions  can  be 
derived  from  section  models. 

A  section  model  is  one  which  represents  only  a  portion  of  the  suspended  struc- 
ture and  simulates  the  bridge  to  some  scale  geometrically.  Elastic  similitude  is  obtained 
by  mounting  the  section  model  with  the  aid  of  springs  designed  to  simulate  the  per- 
iods of  vibration  of  the  actual  structure.  The  latter  must  be  computed.  Section  models 
are  mounted  in  the  wind  stream  in  two  manners,  one  is  termed  "torsional  mount" 
and  the  other  "free  spring  mount."  They  are  described  below. 

On  account  of  lack  of  time  and  the  great  cost  involved,  tests  for  the  Golden  Gate 
Bridge  were  confined  to  section  models.  A  scale  of  1  to  75  was  adopted. 

The  program  comprised  tests  on  the  structure  as  built,  tests  on  the  same  structure 
with  a  bottom  lateral  system  added  and  tests  simulating  various  modifications  of  the 
sidewalk  structure  combined  with  the  addition  of  bottom  laterals. 

Following  are  definitions  of  some  conventional  terms  used  in  model  tests: 

A  section  model  with  "free  spring  mount"  is  one  which  is  suspended  with  the 
aid  of  springs  designed  to  impart  to  the  model  the  computed  periods  of  vibration. 
The  springs  are  so  attached  as  to  allow  three  degrees  of  freedom  of  motion,  i.e.,  verti- 
cal, torsional  and  horizontal. 

A  "torsional  mount"  section  model  is  one  in  which  the  springs  are  designed  to 
impart  to  the  model  the  computed  period  of  torsional  vibration.  In  this  case  the 
model  is  pinned  at  its  ends  in  such  a  manner  as  to  allow  only  one  degree  of  freedom 
of  motion,  i.e.,  torsional  about  a  longitudinal  axis. 

"Angle  of  attack"  designates  the  inclination  of  the  wind  current  in  the  horizontal 
plane.  Positive  angles  designate  upward  and  negative  angles  downward  wind  currents. 

"Decrement"  as  used  in  these  tests  is  a  function  which  measures  the  ability  of  the 
structure  to  dissipate  energy  and  damp  out  motion.  Decrement  includes  both  struc- 
tural and  air  damping. 

"Critical  velocity"  is  the  velocity  of  the  natural  wind  at  which  any  particular  type 
of  vibration  is  initiated. 

APPLICATION  OF  MODEL  TESTS  TO  THE  ORIGINAL  AND  MODIFIED  STRUCTURES. 
Any  predictions  of  the  behavior  of  the  actual  structure  of  the  Golden  Gate  Bridge,  as 
built  or  as  modified,  from  the  model  tests  alone  can  only  be  qualitative  and  not 
quantitative  on  account  of  the  previously  mentioned  unknown  factors.  Among  these 
are  the  decrements  of  the  structure  as  originally  built  and  in  the  various  proposed 
modified  forms,  also  the  inefficiency  of  the  wind  in  nature  as  compared  with  the 
almost  perfect  wind  used  in  model  testing. 

In  the  laboratory  a  wind  stream  is  created  which  is  constant  in  velocity  and  in' 
direction  and  uniform  over  the  full  length  of  the  section  model.  In  nature,  however, 

32  A  traveling  safety  net  supported  by  o 

riggers  was  used  for  duration  of  proj< 
Original  painters'  steel  scaffolds  were 

moved  in  sections. 


Chicago  booms  with  a  six-ton,  45-foot  radius  capability  were  mounted  to  a  carrier  operated  on  the 
new,  permanent  rail  system  once  steady  erection  was  under  way.  Carrier  capacity  was  20  tons  at  50 
feet  per  minute  up  to  the  maximum  3%  grade  of  structure.  Two  erection  crews  started,  one  at  each 
tower,  and  worked  toward  midspan.  Side  spans  were  erected  last.  Initial  two  panels  at  towers 
provided  working  platform  for  remainder  of  operation  and  were  lifted  in  place  by  truck  cranes,  on 
bridge  roadway,  with  booms  over  the  side. 

the  wind  is  constantly  changing  in  velocity  over  short  periods  of  time.  It  strikes  the 
structure  at  different  angles  and  with  different  velocities  at  different  locations  through- 
out the  great  length  of  the  bridge.  In  full  model  tests  of  the  Tacoma  Narrows  Bridge, 
in  which  the  angle  of  attack  could  be  changed  on  various  portions  of  the  model  in 
any  one  test,  it  was  clearly  demonstrated  that  such  changes  would  immediately  damp 
out  or  reduce  violent  motions.  A  change  in  velocity  without  change  in  direction  has 
the  same  effect  because  for  each  velocity  the  action  upon  the  structure  is  different.  A 
gusty  wind  therefore  has  a  damping  tendency  and  becomes  less  efficient  in  producing 
motion  than  a  wind  of  constant  velocity  as  used  in  model  tests. 

For  these  reasons  it  must  be  concluded  that  the  critical  wind  velocity  on  the  actual 
structure  is  substantially  higher  than  that  indicated  by  the  results  of  model  tests.  Just 
how  much  this  difference  is  must  be  largely  a  matter  of  judgment. 

In  the  case  of  the  Golden  Gate  Bridge  there  are  certain  actual  occurrances  which 
serve  as  a  guide  to  such  judgment  as  follows:  During  the  storm  of  December  1,  1951, 
which  is  described  under  "History,"  the  center  span  was  oscillating  in  a  somewhat 
mixed  first  symmetric  torsional  motion  with  a  double  amplitude  of  22  inches  at  5:30 


34 


SECTION     MODEL  TESTS 


P.M.  with  wind  velocity  of  50  mph.  and  a  period  of  vibration  of  8  cycles  per  minute. 
Within  a  few  minutes  the  wind  velocity  started  to  increase  and  the  motion  of  the  cen- 
ter span  changed  to  a  mixed  first  asymmetric  motion  (a  coupled  vertical  and  torsional 
motion  in  which  the  main  span  was  twisting  in  two  segments).  Amplitudes  in  this 
motion  increased  rapidly  as  the  velocity  increased  to  69  mph.  at  5:55  P.M.  with  a  per- 
iod of  16.8  cycles  per  minute  and  a  maximum  double  amplitude  of  130  inches.  At  this 
time  the  wind  velocity  started  to  decrease  and  with  it  the  amplitude  until,  a  few 
minutes  after  the  wind  had  reduced  to  50  mph.,  the  double  amplitude  was  about  20 
inches. 

It  is  reasonable  to  conclude  that  for  the  wind  condition  existing  at  approximately 
5:30  P.M.  and  again  at  approximately  6:10  P.M.  the  actual  critical  velocity  for  the  first 
asymmetric  motion  of  the  structure  as  built  is  approximately  50  miles  per  hour. 

Referring  again  to  "History"  in  this  Supplement,  a  storm  on  June  6,  1950  devel- 
oped a  56  mile  wind  from  the  west  causing  a  maximum  amplitude  of  45  inches  at  mid 
span  in  the  first  symmetric  torsional  mode  of  motion.  For  brief  periods  at  this  velo- 
city the  motion  showed  a  tendency  to  change  to  the  first  asymmetric  torsional  form. 
Apparently  the  critical  velocity  in  this  storm  for  the  first  symmetric  torsion  was  56 
mph  instead  of  50  mph,  as  observed  during  the  December  1,  1951  storm,  and  the  ef- 
ficiency of  the  wind  was  accordingly  less. 

From  this  bridge  history  it  seems  logical  to  assume  that  the  critical  velocity  in  the 
first  asymmetric  motion  is  not  less  than  50  mph. 

PREDICTION  OF  CRITICAL  VELOCITY  FOR  THE  MODIFIED  STRUCTURE  WITH  BOT- 
TOM LATERALS.  As  stated  herein  before,  model  tests  can  give  only  qualitative  results 
unless  the  actual  decrement  of  the  structure  in  any  given  form  and  the  efficiency 
factor  of  the  wind  are  known. 

The  problem  of  predicting  the  critical  velocity  for  the  present  bridge  with  bottom 
laterals  depends  upon  the  difference  between  the  decrements  rather  than  the  actual 
magnitude  of  the  decrements.  It  would  therefore  be  simplified  if  we  knew  the  difference 
between  the  respective  decrements  of  the  bridge  as  built  and  that  of  the  bridge  with 
bottom  laterals  added. 

If  we  assume  the  decrement  of  the  bridge  as  built  to  be  the  same  as  that  of  the 
modified  structure,  then  the  degree  of  improvement  of  the  modified  structure  over 
the  original  one  would  be  measured  by  the  difference  in  critical  velocities  of  the  re- 
spective response  curves.  We  can  reliably  assume,  however,  that  the  decrements  of 
the  original  and  the  modified  structure  are  not  the  same  because  of  the  appreciably 
greater  torsional  stiffness  produced  by  the  addition  of  bottom  laterals. 

To  reduce  model  tests  to  quantitative  results  we  must  assume  decrements  whu  h 
in  our  judgment  actually  existed  in  the  original  structure  and  will  exist  in  the  mod- 
ified structure,  as  a  first  step  toward  predicting  the  critical  velocity  of  the  bruise  \\  ith 
bottom  laterals  added.  A  decrement  of  0.0375  has  been  assumed  for  the  original 
structure  and  0.057  for  the  modified  structure,  a  difference  of  0.0195. 


35 


THE     GOLDEN     GATE  BRIDGE 


This  judgment  is  based  on  the  fact  that  the  torsional  stiffness  of  the  suspended 
floor  structure  will  be  increased  by  the  bottom  laterals  approximately  34  times,  the 
torsional  stiffness  of  the  entire  suspended  structure,  including  cables,  will  be  increased 
approximately  2.7  times  and  the  frequency  of  vibration  will  increase  from  7.26  to 
12.6.  Making  the  above  reasonable  assumptions  constitutes  the  first  step  in  approxi- 
mating the  critical  velocity  for  the  modified  structure. 

The  critical  velocity  of  the  section  model  of  the  original  structure  as  derived  from 
the  section  model  test  and  with  a  decrement  of  0.0375  was  found  to  be  24.9  mph.  The 
critical  velocity  of  the  section  model  of  the  same  structure  with  bottom  laterals  added 
as  derived  from  the  section  model  tests  and  with  a  decrement  of  0.057  is  51.4  mph. 
The  difference  between  these  two  critical  velocities  is  26.5  mph.  This  difference  gives 
a  measure  of  the  improvement  gained  by  adding  a  bottom  lateral  system. 

The  inefficiency  of  the  natural  wind  is  a  second  factor  to  be  applied  in  predicting 
the  critical  velocity  for  any  structure  under  actual  wind  from  tests  on  a  section  model 
of  that  structure  in  ideal  wind. 

Appraisal  of  this  factor  is  also  a  matter  of  judgment  based  on  the  past  perfor- 
mance of  the  original  bridge.  The  storms  of  June  6,  1950,  and  December  1,  1951,  clearly 
reveal  the  actual  critical  velocity  in  the  first  asymmetric  motion  developed  in  those 
particular  storms.  These  critical  velocities  were  56  and  50  mph,  respectively,  an  aver- 
age of  53  mph. 

There  is  no  assurance  that  future  storms  will  confirm  these  critical  velocities.  Dif- 
ferent angles  of  attack  and  different  wind  patterns  and  velocities  may  occur  along  the 
bridge  axis  which  will  modify  the  action.  It  may  reasonably  be  expected,  however, 
that  future  severe  storms  will  be  similar  in  character  to  those  experienced  to  date  and 
that  the  critical  velocities  will  not  vary  greatly  from  those  experienced  heretofore. 

It  has  been  conservatively  assumed  that  48  mph  is  the  minimum  actual  critical 
velocity  for  the  original  bridge  (first  asymmetric  motion).  The  corresponding  critical 
velocity  derived  from  the  section  model  is  found  to  be  24.9  mph,  or  23.1  mph  less 
than  the  above  critical  velocity  derived  from  those  observed  on  the  original  bridge. 

By  combining  the  two  factors,  the  one  due  to  added  stiffness  and  the  one  due  to 
wind  inefficiency,  and  applying  them  to  the  results  from  model  tests,  it  is  possible  to 
predict  quantitatively  the  approximate  critical  velocity  for  the  actual  bridge  with  bot- 
tom laterals  added.  Three  different  methods  may  be  used. 

1.  Using  the  critical  velocity  of  24.9  mph  of  bridge  as  built,  which  was  derived 
from  the  model  test  with  decrement  of  0.0375,  adding  thereto  the  above  assumed 
minimum  increase  of  23.1  mph  for  wind  inefficiency  and  the  above  increase  of 
26.5  mph  for  greater  stiffness,  gives  a  critical  velocity  for  the  actual  bridge  with 
bottom  laterals  of  74.5  mph. 

2.  Using  the  critical  velocity  derived  from  the  model  test  with  decrement  of  0.057, 
i.e.  51.4  mph,  and  increasing  this  for  wind  inefficiency,  i.e.  24.9  mph,  gives  76.3 
mph  as  the  critical  velocity  of  the  prototype  with  bottom  laterals. 


36 


SECTION     MODEL  TESTS 


3.  Using  the  average  critical  velocity  of  the  bridge  as  built  which  was  derived 
from  observations  in  the  storms  of  December  1,  1951  and  June  6,  1950,  which 
presumably  reflects  wind  inefficiency,  and  adding  the  effects  of  greater  stiffness 
gives  53.0  +  26.5  =  79.5  as  the  critical  velocity  of  the  actual  structure  with  bot- 
tom laterals. 

It  is  therefore  reasonable  to  expect  that  the  critical  wind  velocity  for  the  first  asym- 
metric mode  of  motion  of  the  present  bridge  with  bottom  laterals  will  be  between 
about  75  and  80  miles  per  hour.  Instantaneous  gusts  varying  from  68  to  85  miles  per 
hour  may  occur  during  storms  of  such  velocities  without  aggravating  the  behavior  of 
the  structure. 

It  is  not  expected  that  adding  a  bottom  lateral  system  will  eliminate  all  movements 
of  the  bridge  in  the  first  asymmetric  mode  of  motion.  Since  the  bridge  was  finished  this 
type  of  motion  has  occured  at  relatively  low  wind  velocities.  Its  maximum  double  am- 
plitude of  45  inches  was  reached  during  the  storm  of  June  6,  1950  when  the  wind 
reached  a  top  velocity  of  56  mph.  At  this  velocity  the  first  asymmetric  motion  ap- 
peared during  brief  periods.  First  asymmetric  motion  of  this  magnitude  is  not  injurious 
to  the  structure  but  is  somewhat  objectionable  in  its  effect  on  traffic. 

The  addition  of  a  bottom  lateral  system  tends  to  decrease  the  amplitudes  of  this 
motion  approximately  in  the  ratio  of  the  periods  of  vibration  of  the  bridge  as  built 
and  of  the  same  with  bottom  laterals  added.  This  ratio  is  9.61  to  11.08  and  the  de- 
crease approximately  15%. 

The  above  findings  justify  the  recommendation  to  add  a  bottom  lateral  system  as  the 
first  step  in  protecting  the  bridge  against  harmful  or  objectionable  motions. 

EFFECT  OF  CENTER  STAYS.  In  case  the  addition  of  bottom  laterals  should  prove 
insufficient,  it  has  been  recommended,  as  a  second  step,  the  incorporation  of  a  system 
of  center  stays  as  described  elsewhere  hereinbefore.  The  effect  of  such  stays  could 
not  be  tested  on  section  models. 

Tests  on  the  full  model  of  the  Tacoma  Narrows  Bridge  demonstrated  that  as  long 
as  center  ties  remain  intact  no  asymmetric  motion  occurred  and  it  is  safe  to  assume 
that  the  same  would  apply  to  the  Golden  Gate  Bridge  with  effective  center  stays. 

EFFECT  OF  OPENING  FLOOR  STRUCTURE.  Model  tests  made  in  connection  with 
the  redesign  of  the  Tacoma  Narrows  Bridge  indicated  clearly  that  opening  up  parts 
of  the  solid  deck  structure  can  materially  improve  the  behavior  of  the  structure  and 
consequently  such  openings  in  the  form  of  longitudinal  strips  of  open  grating  floor- 
ing between  the  lanes  of  traffic  were  used  in  the  new  bridge. 

Having  in  mind  the  practicability  of  providing  such  openings  in  the  Golden  Gate 
Bridge  by  replacing  all  or  part  of  the  solid  slab  sidewalk  with  open  grating  and  of 
making  other  possible  structural  changes  near  the  edges  of  the  floor  structure  which 
would  improve  the  behavior,  a  number  of  section  model  tests  were  made  to  deter- 
mine the  effect  of  such  changes. 

The  tests  indicated  indeed  that  certain  of  such  changes  would  have  a  beneficial  effect. 


37 


BOTTOM     LATERAL  SYSTEM 


One  of  the  structural  conditions  tested,  namely  with  the  entire  sidewalk  slabs  replaced 
by  gratings  and  the  sidewalk  stringers  and  the  curbs  removed,  it  was  indicated  that 
the  critical  velocity  of  the  prototype  with  bottom  laterals  would  be  raised  to  60.7  mph. 

Adding  to  this  the  previously  derived  allowance  of  23.1  mph  for  wind  inefficiency 
one  arrives  at  a  possible  critical  velocity  of  the  actual  structure  with  bottom  laterals 
and  with  the  aforementioned  changes  in  floor  structure  of  60.7  +  23.1  =  83.8  mph. 
Wind  gusts  might  well  be  above  90  mph. 

Such  an  arrangeme/it  would  probably  also  reduce  the  amplitudes  of  motions  in 
the  first  symmetric  mode. 


BOTTOM  LATERAL  SYSTEM 

The  study  relating  to  the  addition  of  a  bottom  lateral  system  had  as  its  objectives 
to  determine  its  feasibility  structurally  and  its  desirability  as  a  means  to  improve  the 
behavior  of  the  bridge. 

The  question  of  feasibility  hinges  primarily  on  the  practicability,  from  a  mechani- 
cal standpoint,  of  installing  an  adequate  system  of  bracing. 

The  question  of  desirability  hinges  on  the  effect  which  the  bracing  will  have  on 
the  behavior  of  the  structure,  on  its  dead  weight  and  on  its  cost. 

DESCRIPTION.  The  general  arrangement  of  the  proposed  bracing  is  shown  on 
Plates  SI  and  SII.  It  will  be  noted  that  a  panel  of  lateral  bracing  is  about  100  ft.  long, 
thus  extending  over  four  25-ft.  panels  of  stiffening  trusses.  Diagonal  bracing  mem- 
bers are  connected  to  bottom  chords  of  stiffening  trusses  at  panel  points  chosen  to 
miss  main  gusset  connections  for  stiffening  truss  diagonals. 

The  lateral  connection  plates  were  placed  directly  against  the  top  and  bottom  sides 
of  the  chords.  A  large  part  of  the, connection  holes  in  the  chords  were  provided  by 
removing  1-in.  dia.  rivets.  A  few  holes  had  to  be  drilled  at  each  connection.  Field 
connections  were  made  by  1-in.  dia.  high  tensile  bolts.  Transverse  struts  made  up  as 
latticed  girders  are  placed  at  every  truss  panel  point.  These  form  the  bottom  mem- 
bers of  the  cross-frames  and  also  support  the  longitudinal  track  girders.  The  latter 
carry  rails  upon  which  the  traveling  maintenance  scaffolds  operate. 

At  each  end  of  each  span  the  cross-frames  are  designed  to  carry  bottom  lateral 
stresses  up  to  the  plane  of  the  top  laterals  and  thence  to  the  towers  or  pylons. 

The  installation  of  a  bottom  lateral  system  as  described  above  proved  to  be  entirely 
adequate  and  feasible. 

STRESSES  AND  SECTIONS.  The  addition  of  bottom  laterals  converted  the  suspended 
structure  into  one  which  is  much  more  resistant  to  torsion.  This  increased  torsional 
stiffness  results  in  a  somewhat  different  stress  pattern  and  these  stresses  have  to  be 
provided  for  wherever  they  occur.  The  lightest  lateral  members  of  the  top  lateral 
system  are  box  sections  composed  of  four  angles  4  x4  x  7/16  laced  on  four  sides.  This 


deal  hangers  were  first  elements  in 
tion  sequence,  followed  by  transverse 
ts,  diagonal  struts,  and  track  girders. 


39 


End  sections  of  90-foot  transverse  struts  were  second  in  erection  sequence. 


minimum  section  occurs  over  the  middle  portion  of  the  center  span.  Here  stresses  from 
torsional  deformation  typical  of  the  first  asymmetric  mode  of  vibration  are  greatest. 
Obviously  nothing  could  be  gained  by  employing  a  heavier  section  for  the  bottom 
laterals  unless  the  top  laterals  were  also  increased. 

Calculations  show  that  this  minimum  lateral  section  is  sufficient  to  withstand 
stresses  induced  by  a  torsional  force  of  18,000  ft.lb.  per  foot  of  center  span  applied  in 
one  direction  over  the  south  half  and  in  the  opposite  direction  over  the  north  half. 
In  terms  of  asymmetric  live  load  this  is  the  torsion  that  would  be  obtained  by  loading 
only  the  southwest  and  northeast  quarters  of  the  roadway  of  the  center  span  with  40  lb. 
per  sq.  ft.  of  roadway  area.  This  torsional  resistance  is  sufficient  for  all  purposes  and 
a  bottom  lateral  system  thus  composed  is  adequate. 

EFFECT  ON  STRUCTURE.  Addition  of  the  bottom  lateral  bracing  affects  the  bridge 
in  many  ways.  It  is  necessary  to  explore  and  evaluate  several  of  these  effects  in  order 
to  be  certain  that  the  benefits  are  not  obtained  through  a  sacrifice  of  some  essential 
quality  of  the  structure.  The  effects  fall  into  two  categories:  (1)  that  which  the  added 
torsional  resistance  has  on  the  behavior  of  the  structure,  and  (2)  that  of  the  added 
weight  on  the  major  load  carrying  elements  of  the  bridge. 


40 


BOTTOM     LATERAL  SYSTEM 


In  one  comparison  made,  the  suspended  structure  of  the  center  span  was  consid- 
ered cut  loose  from  the  cables  and  subjected  to  a  torsional  force  uniformly  distributed 
over  the  south  half  of  the  span  and  a  like  torsional  force  acting  in  the  opposite 
direction  over  the  north  half.  The  structure  without  bottom  laterals  showed  an  angu- 
lar rotation  at  the  quarterpoint  34.8  times  greater  than  that  of  the  structure  with 
bottom  laterals. 

A  similar  comparison  was  made  with  the  structure  suspended  from  the  cables  and 
this  showed  for  the  assembled  structure  without  bottom  laterals  an  angular  rotation 
at  the  quarterpoint  2.7  times  greater  than  that  for  the  structure  with  bottom  laterals. 

By  adding  the  bottom  laterals  the  calculated  frequency  of  the  center  span  in  the 
first  asymmetric  mode  of  torsional  vibration  is  raised  from  7.26  to  12.6  cycles  per  min- 
ute. In  the  first  symmetric  mode  of  torsional  vibration  the  frequency  is  raised  from 
9.61  to  11.08  cycles  per  minute  (neglecting  tower  stiffness).  These  increases  in  frequency 
are  noteworthy,  especially  for  the  first  asymmetric  torsional  mode. 

Torsional  forces  applied  to  the  structure  without  bottom  laterals  are  carried  almost 
entirely  by  the  cables.  In  the  structure  with  bottom  laterals  such  torsional  forces  are 
so  divided  between  the  cables  and  the  suspended  structure  that  the  former  carries 
36%  while  the  latter  carries  64%.  This  is  another  reflection  of  the  reduced  angular 
rotation  referred  to  above. 

Since  the  structure  with  bottom  laterals  resists  torsional  forces  it  must  be  designed 
accordingly.  The  top  and  bottom  lateral  systems,  including  their  respective  stiffening 
truss  chords,  constitute  trusses  lying  in  horizontal  planes  and  they  are  subject  to 
shearing  forces  that  arise  from  any 
torsional  force  applied  to  the  suspend- 
ed structure.  This  may  come  from  live 
load  or  wind.  Calculations  were  made 
for  an  asymmetric  live  load  of  40  lb. 
per  sq.  ft.  on  diagonally  opposite 
quarters  of  the  main  span  roadway. 
This  produces  a  torsional  force,  men- 
tioned before,  of  18,000  ft.  lb.  per 
lineal  foot  of  bridge.  Sixty-four  per- 
cent of  this  torsion  will  be  carried  by 
the  suspended  structure.  The  shearing 
force  thus  produced  in  the  top  and 
bottom  horizontal  trusses  results  in 
maximum  stresses  of  ±176,000  lb.  in 
the  diagonals  of  the  end  panels  and 
at  mid-span.  The  laterals  have  ample 
section  to  resist  this  stress  safely. 
Stresses  in  chords  are  negligible. 


Erection  of  end  section  of  transverse  strut — Steel  fabricator  used  special  shop  jigs  to  ream 
holes  for  high  tensile  bolts  and  eliminate  preassembly  of  elements  in  plant.  Existing  bridge 
steel  was  prepared  by  chipping  and  wire  buffing  at  connections. 


SB 


Center  sections  of  transverse  struts  were  third  in  erection  sequence  and  secured  by  undersized 
erection  bolts.  Center  sections  had  milled  ends. 

The  increased  torsional  resistance  will  have  a  pronounced  effect  on  torsional  oscil- 
lations of  the  center  span.  The  benefits  of  the  higher  frequencies  will  be  felt  in  two 
ways.  First,  it  will  require  much  higher  wind  velocities  and  more  time  to  excite  tor- 
sional oscillations  especially  in  the  first  asymmetric  mode.  This  is  the  mode  with  which 
one  is  most  concerned.  Second,  the  amplitude  of  oscillations  will  be  favorably  affected. 
Knowledge  in  this  field  has  not  advanced  far  enough  to  make  possible  a  precise 
evaluation  of  these  gains.  Unquestionably,  structural  damping  has  been  increased 
considerably  and  consequently  the  structure  has  an  increased  capability  of  dissipating 
energy  by  its  oscillations.  As  a  result,  under  any  given  wind  condition  in  which 
oscillations  are  building  up,  a  steady  state  will  be  reached  at  smaller  amplitude  than 
was  the  case  before  the  bottom  laterals  were  added. 

Although  a  precise  prediction  could  not  be  made  as  to  the  behavior  of  the  bridge 
with  bottom  laterals  in  a  storm,  it  is  reasonable  to  believe  that  the  structure  as  it  now 
stands  with  bottom  laterals  in  place  will  never  experience  objectionable  oscillations 
and  that  the  possibility  of  torsional  oscillations  in  the  first  asymmetric  mode  are 
practically  eliminated.  This  is  the  mode  which  developed  maximum  amplitudes  in 
the  storm  of  December  1,  1951. 


42 


BOTTOM     LATERAL  SYSTEM 


EFFECT  OF  ADDED  LOADS.  The  dead  load  used  in  the  original  design  was  21,000 
lb.  per  foot  of  bridge.  The  addition  of  bottom  laterals  increased  the  dead  load  by 
1,400  lb.  per  foot  and  justifies  an  increase  in  longitudinal  wind  load  to  the  extent  of 
269,000  lb.  per  tower  shaft.  The  effect  of  the  increase  in  weight  extends  to  many  parts 
of  the  structure. 

The  cable  stress  increase  of  about  5*/2%  is  amply  provided  for  in  the  conservative 
design  stress  used.  Furthermore,  the  testing  laboratory  reports  on  cable  wire  show 
that  the  average  tensile  strength  of  the  wire  was  4.7%  above  the  average  specified. 
There  remains  an  ample  safety  margin  in  the  cables. 

The  anchorages  and  their  fastenings  to  the  cables  are  sufficient  to  take  care  of  the 
slight  increase  in  the  cable  tension.  The  eye-bar  chains  which  transmit  the  cable-pull 
into  the  concrete  anchor  blocks  are  made  up  of  heat-treated  eye-bars  which,  according 
to  test  reports  on  full  size  eye- bars  have  an  average  yield  point  7%  above  the  average 
specified.  All  details  employed  will  develop  the  strength  of  the  parts  connected. 

Reports  of  suspended  rope  tests  at  manufacturer's  plant  showed  a  strength  at  least 
19%  above  that  specified.  They  are  more  than  sufficient  to  sustain  the  added  weight. 

Test  reports  show  that  the  tie-down  ropes  have  an  ultimate  strength  10%  above 
that  specified.  This  is  more  than  enough  to  take  care  of  the  increased  weight  of  2.8%. 

Under  the  influence  of  the  added  weight  the  tower  tops  will  have  moved  3  in. 
channelward.  This  adds  to  the  unit  stresses  on  the  channel  face  of  the  tower. 

The  dead  load  cable  reaction  at  the  top  of  each  tower  shaft  is  increased  by  about 
3,078,000  lb.  Direct  load  unit  stresses  are  increased  accordingly. 

The  longitudinal  wind  load  has  been  increased  because  of  wind  area  added  by  the 
bottom  laterals.  A  liberal  allowance  for  this  additional  wind  force  is  269,000  lb.  per 
tower  shaft,  applied  at  the  floor  level. 

It  is  not  necessary  to  add  anything  for  the  slight  change  in  transverse  wind  area 
since  the  original  design  assumptions  are  ample  to  cover  this. 

The  combination  of  unit  stresses  due  to  the  above  added  forces  accounts  for  in- 
creases along  the  extreme  channel  face  of  the  tower.  These  increases  are  on  the  order 
of  1,200  to  1,900  lb.  per  sq.  in.  However,  resulting  total  unit  stresses  exceed  the  de- 
sign unit  stresses  only  in  the  vicinity  of  two  cross-struts.  At  one  of  the  points  the  unit 
stress  in  silicon  steel  is  1,200  lb.  per  sq.  in.  above  the  design  unit  stress  of  23,000  lb. 
per  sq.  in.  At  the  other  point  the  unit  stress  in  carbon  steel  is  1,300  lb.  per  sq.  in. 
above  the  design  unit  stress  of  18,000  lb.  per  sq.  in. 

These  increases  in  unit  stresses  are  less  than  of  the  conservative  design  unit 

stresses.  Since  these  result  from  a  simultaneous  occurrence  of  an  improbable  live  load 
condition,  combined  with  full  transverse  and  longitudinal  wind  and  high  tempera- 
ture, which  combination  will  probably  never  occur,  the  tower  design  is  ample  to 
sustain  the  added  loads. 

The  stiffening  trusses  of  center  and  side  spans  are  affected  in  a  mode  rate  degree 
by  the  added  weight.  Maximum  unit  stress  increases  in  the  chord  members  are  about 


43 


THE     GOLDEN     GATE  BRIDGE 


5%.  Design  assumptions  are  sufficiently  liberal  to  take  care  of  this.  The  average  yield 
point  of  the  material  used  in  the  truss  chords  exceeds  the  average  specified  by  12%. 
The  truss  diagonals  are  not  appreciably  affected  by  the  added  weight. 

COST.  The  installation  of  the  bottom  lateral  system  required  about  4,750  tons  of 
structural  steel.  The  cost  of  the  work,  including  engineering  and  all  incidental 
expenses  was  $3,500,000.00. 

CENTER  STAYS 

As  previously  mentioned  the  installation  of  a  system  of  center  stays  has  been 
studied.  Its  installation  is  recommended  only  as  a  second,  future  step  in  case  the 
bottom  lateral  system  alone  should  prove  not  to  be  entirely  adequate. 

No  quantitative  section  model  tests  could  be  made  to  determine  the  effectiveness 
of  such  stays,  but  from  observation  in  actual  bridges  and  from  the  tests  made  on  the 
full  model  of  the  New  Tacoma  Bridge,  it  is  practically  certain  that  if  made  strong 

Fast  track  mounted  carrier  used  for  main  span  portion  of  erection  equaled  setting  speed  of  truck 
crane  working  from  high  ground  on  Marin  side  span.  First  five  panels  of  Marin  side  span  at  Marin 
tower  were  erected  from  bridge  pavement  by  truck  cranes  boomed  over  the  side.  Remainder  were 
set  from  crane  below. 


CENTER  STAYS 


enough  they  will  effectively  prevent  the  development  of  the  most  critical  asymmetric 
torsional  motions  of  the  center  span,  and  in  this  respect  supplement  the  bottom 
lateral  system.  As  indicated  by  experience  in  the  Whitestone  Bridge  they  will  also 
dampen  asymmetric  vertical  motions  and  prevent  the  longitudinal  motions  of  the 
floor  in  relation  to  the  cables  which  were  observed  to  be  of  considerable  magnitude 
on  the  Golden  Gate  Bridge  in  the  storm  of  December  1,  1951  as  well  as  on  the 
Whitestone  Bridge  prior  to  the  installation  of  center  stays. 

The  proportioning  of  the  center  stays  is  largely  a  matter  of  judgment.  Those  in- 
stalled in  the  first  Tacoma  Narrows  Bridge  proved  inadequate  under  the  severe 
torsional  movements. 

The  first  temporary  installation  of  center  stays  on  the  Whitestone  Bridge,  while  it 
did  not  fail,  indicated  excessive  wear  and  called  for  replacement  and  stronger  connec- 
tions. Those  now  installed  since  1950  appear  to  be  amply  proportioned,  although 
owing  to  other  preventive  measures  they  have  not  and  probably  never  will  be  sub- 
jected to  motions  which  might  induce  in  them  stresses  even  well  within  their  safe 
capacity. 

Erection  of  center  section  of  transverse  strut  —  Once  all  members  were  positioned,  entire  panel, 
representing  25  tons  and  25  feet  of  bridge,  was  tightened  at  once. 


Diagonal  struts,  lightest       The  Board  of  Engineers  in  their  report  of  January  1953  state  "We  have  satisfied 

members  in  the  system,  #  . 

were  fourth  in  erection  ourselves  that  the  installation  of  center  stays,  while  altering  somewhat  the  stress  con- 
sequence, a  complete  set  jition  Qf  j-]^  bridge  under  certain  conditions  of  live  load,  would  have  no  adverse  effect 

of  diagonals  occurred  0 

each  100  feet.  on  the  structure." 

The  unqualified,  unanimous  recommendation  of  the  Board  of  Engineers  that  the 
bottom  lateral  system  be  installed  was  carried  out  without  delay  and  subsequently, 
prior  to  the  date  of  this  publication,  there  has  been  no  objectionable  movement  of  the 
suspended  structure  of  the  bridge.  The  installation  was  completed  late  in  the  year  1955. 


TRAVELING  SCAFFOLDS 

GENERAL.  For  the  safety  of  the  maintenance  crew  and  also  to  provide  for  them  a 
place  to  work  with  greatest  efficiency  it  was  desirable  to  install  four  sets  of  Traveling 
Scaffolds  —  one  in  each  side  span  and  two  in  the  center  span.  Each  set  comprises  one 
Interior  Scaffold,  two  Exterior  Side  Scaffolds,  and  one  Exterior  Underneath  Scaffold. 
The  two  Exterior  Side  Scaffolds  are  positioned  just  outside  the  stiffening  trusses  on 
each  side  of  the  bridge. 

All  of  the  Scaffolds  operate  over  Crane  Rails  and  are  driven  by  electrical  power 
derived  from  generators  located  on  the  Interior  Scaffold  and  on  the  Exterior  Under- 
neath Scaffold. 

TRACKS.  Crane  Rails  placed  on  the  track  girders  which  were  incorporated  in  the 
Bottom  Lateral  construction  form  the  track  for  the  Interior  Scaffolds. 

Crane  Rails  set  on  rail  chairs  which  are  mounted  on  the  top  chords  of  the  stiffen- 
ing trusses  provide  single  rail  tracks  for  the  Exterior  Side  Scaffolds.  These  rail  chairs 
also  carry  a  line  of  Trolley  Beams  which,  engaged  by  rollers  attached  to  the  Scaffold, 
serve  as  a  guide  to  keep  the  Scaffold  in  proper  operating  position  on  the  rails. 

INTERIOR  SCAFFOLD.  This  Scaffold  runs  over  the  track  described  above.  It  is  motor 
driven  by  electrical  power  derived  from  its  own  engine  generator  set.  It  moves  in  the 
clear  space  bounded  by  the  bridge  floor  beam  above,  the  bottom  laterals  below  and 
on  either  side  (transverse  to  the  bridge)  by  vertical  members  which  occur  at  each 
panel  point  (twenty-five  feet  spacing  in  the  longitudinal  direction  of  the  bridge).  The 
clear  distance  between  these  vertical  members  is  about  sixty  feet. 


46 


TRAVELING  SCAFFOLDS 


The  Interior  Scaffold  comprises  three  principal  structural  units,  namely:  one  Car- 
rier Unit  and  two  Retractile  Wings. 

The  Carrier  as  its  name  implies  is  the  main  unit.  It  has  a  top  working  deck  and 
below  deck  it  carries  the  Retractile  Wings.  It  runs  directly  on  the  rails.  Extending  in 
a  direction  transverse  to  the  bridge  it  has  a  tubular  space  of  rectangular  cross  section. 
At  the  bottom  of  this  space  rails  are  provided  on  which  the  Retractile  Wings  can  be 
rolled  in  or  out  in  direction  transverse  to  the  bridge.  The  Scaffold  cannot  be  moved 
past  a  panel  point  unless  the  Retractile  Wings  are  fully  retracted.  When  the  Scaffold 
is  in  position  between  panel  points  the  Retractile  Wings,  one  on  each  side,  may  be 
run  out,  thus  extending  the  working  deck  to  the  inner  sides  of  the  stiffening  trusses. 
Movement  of  the  Retractile  Wings  is  effected  by  means  of  a  rope  drive  motored  by 
electric  power. 

Necessary  limit  switches  and  interlocking  is  provided  to  safeguard  the  units 
against  damage  by  improper  operation  and  to  limit  travel  to  that  intended. 

Machinery  for  driving  the  Carrier  is  located  on  the  Shoreward  side  only  and  it  is 
connected  only  to  wheels  at  the  Shoreward  end  of  the  trucks.  Wheels  at  the  opposite 
end  of  the  trucks  are  idlers.  Rail  Clamps  are  provided  adjacent  to  the  drivers  only  — 
two  per  Scaffold. 

Torque  wrenches  were 

Interior  Scaffolds  for  Center  Span  and  Side  Spans  are  alike  except  that  the  wheels  used  to  check  adjustment 
and  driving  machinery  of  the  Side  Span  Scaffolds  are  set  lower  to  compensate  for  the  of  Pneumatlc  'mPat~t 

o  J  i  i  wrenches  used  tor  high 

difference  in  distance  between  top  of  rail  and  underside  of  floor  beams  in  the  two  spans,  tensile  bolts. 

EXTERIOR  SIDE  SCAFFOLDS.  The 
Exterior  Side  Scaffolds  are  in  pairs,  one 
right-hand  and  one  left-hand.  They 
hang  in  vertical  planes  just  outside 
the  Stiffening  Trusses.  At  the  top  they 
are  provided  with  wheels  which  roll 
on  the  Crane  Rails  previously  de- 
scribed. At  the  bottom  the  two  Scaf- 
folds forming  a  pair  are  joined  by  two 
wire  ropes  which  restrain  them  from 
outward  movement. 

These  Scaffolds  are  thirty  feet  long 
in  the  longitudinal  direction  of  the 
bridge  and  three  feet  wide.  At  each 
end  is  a  latticed  upright  hanger.  At 
their  tops  the  hangers  terminate  in 
trucks  which  extend  inward  in  canti- 
lever fashion  carrying  at  the  cantilev- 
ered  end  a  wheel  which  rolls  on  the 
Crane  Rail.  The  truck  on  the  Shoreward 


THE     GOLDEN     GATE  BRIDGE 


end  is  designated  a  "Driver  Truck"  because  its  wheel  is  driven  by  electric  motor-driven 
machinery  mounted  on  the  truck.  The  truck  at  the  other  end  of  the  Scaffold  is  desig- 
nated a  "Trailer  Truck"  because  its  wheel  is  not  used  for  propulsion.  The  transverse 
wire  ropes  mentioned  above  are  attached  to  the  bottom  ends  of  the  hangers  —  one  to 
each  hanger.  About  eight  feet  up  from  the  bottom  end  of  each  hanger  there  is 
mounted  thereon  a  rubber  tired  wheel  which  in  operation  rolls  along  the  outside 
webs  of  the  bottom  chords  of  the  Stiffening  Trusses.  They  serve  to  restrain  the  Scaf- 
folds against  inward  movement.  At  the  upper  end  of  each  hanger  there  is  mounted 
thereon  a  trolley  which  functions  in  a  horizontal  plane  in  rolling  engagement  with 
the  aforementioned  trolley  beams.  These  are  arranged  to  hold  the  wheels  in  proper 
lateral  relation  with  the  Crane  Rails.  Rail  Clamps  located  six  feet  three  inches  in  from 
the  trucks  provide  means  for  mooring  the  Scaffold  in  any  position. 

Combined  with  each  Rail  Clamp  support  is  a  Safety  Stop  which  just  clears  the  rail 
by  a  fraction  of  an  inch.  This  Safety  Stop  is  capable  of  supporting  the  Scaffold  in  the 
event  of  any  wheel,  truck  or  rail  failure. 

The  outboard  or  outer  plane  of  the  Scaffold  is  provided  with  a  system  of  diagonal 
bracing  and  the  inner  face  is  open  except  for  handrailings  and  one  vertical  tension 
member  on  the  centerline. 

The  top  deck  of  this  Scaffold  which  is  about  one  foot  nine  inches  above  the  top 
chord  of  the  Stiffening  Truss  serves  as  an  auxiliary  operator's  platform  and  a  means  of 
access  to  lower  levels.  Below  the  top  deck  there  are  four  platforms  three  feet  wide 
and  thirty  feet  long.  They  are  spaced  vertically  about  eight  feet  apart  (the  bottom 
space  is  greater)  to  serve  as  working  platforms  for  maintenance  workers. 

The  ends  and  back  side  of  the  Scaffold  are  covered  with  woven  wire  fabric  as  a 
safety  measure  to  prevent  men  or  material  from  falling  off  the  Scaffold. 

Electric  power  for  operating  the  Exterior  Side  Scaffolds  comes  from  an  engine 
generator  set  on  the  Exterior  Underneath  Scaffold.  This  power  is  delivered  by  a  flex- 
ible power  and  control  cable  extending  from  terminal  box  on  each  end  of  the  Under- 
neath Scaffold  to  Cable  Reel  mounted  on  the  lower  end  of  each  Shoreward  hanger. 

EXTERIOR  UNDERNEATH  SCAFFOLD.  The  Exterior  Underneath  Scaffold  comprises 
a  working  platform  eight  feet  wide  extending  the  full  width  of  the  bridge  and  sup- 
ported by  two  trusses  four  feet  deep.  The  Scaffold  is  provided  with  two  trolleys  per 
truss  spaced  forty-five  feet  center  to  center  and  in  rolling  engagement  with  trolley 
beams  attached  to  the  underside  of  the  Track  Girders  which  places  them  just  below 
the  Bottom  Laterial  Bracing  of  the  bridge. 

This  Scaffold  is  operated  in  conjunction  with  the  pair  of  Exterior  Side  Scaffolds 
with  which  it  is  associated.  It  is  propelled  along  the  bridge  by  means  of  wire  ropes 
working  over  drums  (one  at  each  end).  The  ends  of  the  wire  ropes  are  anchored  to 
each  end  of  the  adjacent  Exterior  Side  Scaffold.  The  drums  are  electric  motor  driven, 
power  being  derived  from  an  engine  generator  set  located  on  the  Scaffold. 

A  latching  device  is  provided  at  each  end  which  affords  a  means  of  mooring  the 
Scaffold  to  the  Exterior  Side  Scaffolds. 

48 


Gusset  plate  detail  of  one  transverse  and  two  diagonal  struts  connecting  to  bottom  chord  of  stiffening 
truss  occurs  each  100  feet  at  panel  points  chosen  to  avoid  main  gusset  connections  for  truss  diagonals. 

Track  girders,  45  feet  center  to  center,  were  final  elements  to  be  erected.  Permanent  tracks  sup- 
ported inside  portion  of  movable  painters'  scaffold. 


PLATE  SI 


PLATE  SI 


accz  oa  a  3 


S.F.  PUBLIC  LIBRARY 


-ll 


THE  GOLDEN  GATE  BRIDGE 

SAM  FRANCISCO.  CAL 

REPORT  Of  BOARD  Of  EMCIMttRS 
....  ...  ..  >ii 


PLAN 


PROPOSED  BOTTOM  LATERAL  SYSTEM 
-PLAN  — 


\ 


PLATE  SII 


JBRARY 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO.  CAL. 

REPORT  OF  BOARD  OF  ENGINEERS 
JANUARY,  1953 

OTHMAR  H  AMMANN      CHARLES  E.  ANDREW 
CLIFFORD  E  PAINE 


PROPOSED  BOTTOM  LATERAL  SYSTEM 
-SECTIONS- 


PLATE  SII 


S.F.  PUBLIC  LIBRARY 


THE  GOLDEN  GATE  BRIDGE 

SAN  FRANCISCO.  CAL. 
•  EPO»T  Of  SOAWO  Of  INGINCWS 

JANUAtV,  Ittt 
OTHUAA  M  M«I»MN      OtM>L»  C  «~C»I  * 


PROPOSED  BOTTOM  LATERAL  SYSTEM 
-SECTIONS- 


PLATE  SIII 


EXTERIOR  SIDE  SCAFFOLD- ES2' 


TRAVELING  SCAFFOLDS 

FOR  THE 

GOLDEN    GATE  BRIOGE    8   HIGHWAY  OISTRICT 
OF  CALIFORNIA 


-6ENERAL  DRAWING  - 


CLIFFORD  E  MUNE  —  CONSULT MG  ENGINt  I  H 
FENNVILLE,  MICHIGAN 


ftPMOVEO 

GOLAEM  GATE  MWpBE^A   HIGHWAY  OISTRICT 


GENERAL  MANAGER 


DATF  *—  Mn.  25. 1983 
SCALE  -   W-  I'-Q* 


SHEET  NO  2 


1*1  A  I  I  Mil 


S.F.  PUBLIC  LIBRARY 


S.F..  PUBLIC  LIBRARY